Question

Which method of recovery required concurrent activities? Select one: a. Fast Tracking b. All of these...

Which method of recovery required concurrent activities?

Select one:

a. Fast Tracking

b. All of these

c. Crashing

d. Analogous

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer

Method of recovery required concurrent activities:

b) all of these

(Fast tracking and scheduling are the methods used to compress the activities in a project. These requires activities to be concurrent for parallel or partial parallel compression. And analogous us a method of recovery requiring concurrent activities in data base management systems. )

Add a comment
Know the answer?
Add Answer to:
Which method of recovery required concurrent activities? Select one: a. Fast Tracking b. All of these...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT