Hello, could you please answer and explain the questions BELOW and please explain in great detail to how you got each answer by explaining it to me step by step, please. thanks!
Question - You are
analyzing a tea bag production line. (You just love tea.)
There are five processes, labeled A through E, and your tea bags
start at Process A, then go to Process B, C, D, and E. The process
map looks a bit like this:
Start -> A -> B -> C -> D -> E ->
Finish. You have the following process information:
Process A requires 14 minutes per tea bag. Process B can do 4.8 tea
bags per hour. Process C can make 3.4 tea bags per hour. Process D
does 33.1 tea bags per 8-hour shift. Process E requires 6.33
minutes per tea bag.
Question - The production processes in Chapter 7 include four major types: process focus, repetitive focus, product focus, and mass customization. Consider Anytown USA’s general hospital. The manager claims he is using a process focus. He says that is the best way to do a hospital business, because it focuses on specific activities, uses general purpose equipment (such as surgical suites or X-ray machines), has a high degree of product flexibility (anything from strokes to car accidents to well-baby clinics), and planning and scheduling is a huge challenge. Costs are really high.
An Operations Management consultant suggests that the hospital manager move away from a process focus and into one of the other three (repetitive focus, product focus, or mass customization.)
Question - Chapter 7 covered process strategy
and sustainability. Consider some denim blue jeans. Below are three
ways to manufacture that pair of jeans.
* process focus, * product focus, * mass customization focus.
For each of these three ways, please describe the volume, level
of variety, and any other relevant details.
If you could accomplish it, which strategy is likely to be the most difficult to implement for blue jeans? How would you do it anyways? Be specific in your answer.
Question - We are thinking about layout strategies for production now. This is a problem about workstation layout.
A firm must produce 40 units/day during an 8-hour workday. Tasks, times, and predecessor activities are given below. You want to group the tasks below into workstations, each workstation staffed by one person.
|
Task |
Time (Minutes) |
Predecessor(s) |
|
A |
2 |
- |
|
B |
2 |
A |
|
C |
8 |
- |
|
D |
6 |
C |
|
E |
3 |
B |
|
F |
10 |
D, E |
|
G |
4 |
F |
|
H |
3 |
G |
|
Total |
38 minutes |
A) What is the cycle time you would need in order to produce your target of 40 units during 8 hours?
B) Use the cycle time you computed in part A above. What is the minimum number of workstations you would need in order to achieve this cycle time at all workstations?
C) Suggest a workstation grouping which would work. In your answer, clearly specify which tasks you would assign to which station. For example, you might want to put Tasks A, B, C, and D together in Workstation 1. Determine the cycle time and the appropriate number of workstations to produce the 40 units per day.
Question - Susan has a part-time business producing seasonal plywood yard ornaments for resale at local craft fairs and bazaars. She currently works 8 hours per day to produce 20 ornaments.
a. What is her productivity?
b. She thinks that by redesigning the ornaments and switching from use of a wood glue to a hot-glue gun she can increase her total production to 30 ornaments per day. What is her new productivity?
c. What is her percentage increase in productivity?
Question - Which is NOT true regarding differences between goods and services? Explain why.
Time taken by each process
A- 14 minutes
B-60/4.8= 12.5 minutes
C- 60/3.4= 17.6 minutes
D-480/33.1= 14.5 minutes
E- 6.33 minutes
None of the process seems to be bottleneck because time taken by each activity are more or less same.
Process E will be completed after= 14+12.5+17.6+14.5+6.33 =65 minutes
Yes we can save 13.5 minutes from D so it will reach faster to process E.
Hello, could you please answer and explain the questions BELOW and please explain in great detail...
John is installing a production line in the kitchen of his successful restaurant “Light of the World” to make vanilla soufflé with caramel sauce. He figures his layout can be broken down into the following tasks: A. Egg separation – 8.5 min. B. Flour, milk, vanilla, egg yolk and sugar blend – 6.5 min. C. Fold egg whites into blend – 2.0 min. D. Bake – 8.9 min. E. Remove from oven, apply topping, garnish, stage, deliver – 8.0 min....
Francis Johnson's plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 12 units per hour, and there is room for only five workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TIME IMMEDIATE TASK (MINUTES) PREDECESSOR 2.5 2.0 2.0 3.0 3.0 3.0 3.0 A,B, C b....
Problem 6-22 Francis Johnson's plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 24 units per hour, and there is room for only five workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task TASK TIME IMMEDIATE TASK (MINUTES) PREDECESSOR 1.0 1.0 2.5 1.5 A, B, C 1.5...
Hello,
I need to see the solution, how they got these numbers? Will
appreciate help.
The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,600 units per 40-hour workweek: Predecessors Task A B С D E F Performance Time (seconds) 22 27 14 15 10 28 А A А B, C DE This exercise only contains parts b, c, d, e, and...
Answer questions 32-37, they are all oart of the same
question
Theres no more information provided,what are you asking for?
Questions 32 to 37 refer to the following: The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved...
I
need help with the total idle time per cycle question, please
include steps with explanations
& Problem 9.15 The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. T Question Help he demand for the train is 4,800 units p 40-hour workweek Performance Time Task Predecessors 20 27 B, C D.E 12 This exeroise only contains parts b, c, d, e, and f b) Given the demand, the...
Problem Statement: A factory producing the new COVID-19 at-home testing kits is determining how to best line balance their production process. There are 12 steps to the production process, and they are presented below, along with their predecessors and how long it takes to complete each task. Assume all times are in minutes. This facility operates for 7 hours per day. Task C D E F G H I J K L A B Nil A B B B B...
3. Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 48 chairs. the eight tasks required to produce the chair and the precedence diagram are shown below TASK PERFORMANCE TIME (min) ULUI Precedence diagram a. What is the cycle time for...
A producer of inkjet printers is planning to add a new line of printers, and you have been asked to balance the process, given the following task times and precedence relationships. Assume that cycle time is to be the minimum possible. Task Length (minutes) Immediate Predecessor a 0.2 - b 0.4 a c 0.3 - d 1.3 b, c e 0.1 - f 0.8 e g 0.3 d, f h 1.2 g a. Do each of the following: (2) Assign...
EXAMPLE 8.2: Assembly-Line Balancing The Model J Wagon is to be assembled on a conveyor belt. Five hundred wagons are required per day. Production time per day is 420 minutes, and the assembly steps and times for the wagon are given in Exhibit 8.9A. Assignment: Find the balance that minimizes the number of workstations, subject to cycle time and precedence constraints SOLUTION I. Draw a precedence diagram. Exhibit 8.9B illustrates the sequential relationships identi- fied in Exhibit 8.9A. (The length...