Suppose that the following estimates of activity times (in weeks) were provided for the network shown below:
| Activity | Optimistic | Most Probable | Pessimistic |
| A | 4 | 6 | 8 |
| B | 2.5 | 4.5 | 5.5 |
| C | 5 | 6.5 | 8 |
| D | 4 | 5.5 | 8 |
| E | 6.5 | 7.5 | 9 |
| F | 2 | 3.5 | 5 |
| G | 7 | 9 | 12 |
| H | 5 | 6 | 13 |
What is the probability that the project will be completed. If required, round your answers to four decimal places.
Within 20 weeks?
Within 22.5 weeks?
Within 25 weeks?
The formula for the mean time and variance is:
Mean Time (t) = (a+4b+c)/6
Variance = [(c-a)/6]2
|
Activity |
Optimistic (a) |
Most Probable (b) |
Pessimistic (c) |
Mean Time (t) |
Variance |
|
A |
4 |
6 |
8 |
6 |
0.444444 |
|
B |
2.5 |
4.5 |
5.5 |
4.34 |
0.25 |
|
C |
5 |
6.5 |
8 |
6.5 |
0.25 |
|
D |
4 |
5.5 |
8 |
5.67 |
0.444444 |
|
E |
6.5 |
7.5 |
9 |
7.58 |
0.17361 |
|
F |
2 |
3.5 |
5 |
3.5 |
0.25 |
|
G |
7 |
9 |
12 |
9.16 |
0.69444 |
|
H |
5 |
6 |
13 |
7 |
1.777777 |
Calculation of critical path:
1. ACH=20
2. ADFH=22
3. ADG=21
4. BEG=20
5. BEFH=21
The highest value is 22, so, the critical path is ADFH and time is 22 weeks.
Variance of critical path = var. A + var. D + var. F +var. H = 2.91
Standard deviation of critical path = (Variance)2 = (2.91)2 = 8.468
Z score calculation = [Weeks (x) - mean]/sd
· Within 20 weeks
Here, x = 20, mean = 22 and sd = 8.468
So, Z = -0.2361
Therefore, the probability = 0.5793
· Within 22.5 weeks
Here, x = 22.5, mean = 22 and sd = 8.468
So, Z = 0.059
Therefore, the probability = 0.5
· Within 25 weeks
Here, x = 25, mean = 22 and sd = 8.468
So, Z = 0.354
Therefore, the probability = 0.383
If you like my answer please encourage me by giving up-vote.
Thank you
Suppose that the following estimates of activity times (in weeks) were provided for the network shown...
Suppose that the following estimates of activity times (in weeks) were provided for the network shown below: Activity Optimistic Most Probable Pessimistic A 4 6 8 B 2.5 4.5 5.5 C 5 6.5 8 D 4 5.5 8 E 6.5 7.5 9 F 2 3.5 5 G 7 9 12 H 5 6 13 What is the probability that the project will be completed. If required, round your answers to four decimal places. Within 20 weeks? Within 22.5 weeks? Within...
The following table shows estimates of activity times (weeks) for a project: Activity Optimistic Time Most Probable Time Pessimistic Time A 3 4.5 9 B 1.5 2 2.5 C 5 6 7 D 4 4.5 8 E 5 6 7 F 1 2.5 7 G 7 9 11 Suppose that the critical path is A-B-D-F-G. Use Appendix A to answer the questions. Do not round intermediate calculations. Round your answers to three decimal places. What is the probability that the...
Estimated activity times and precedences are given below: Activity Optimistic Most Likely Pessimistic Required Precedence A 6 7 14 B 8 10 12 C 2 3 4 D 6 7 8 A E 5 5.5 9 B, C F 5 7 9 B, C G 4 6 8 D, E H 2.7 3 3.5 F What is the probability that the project will be completed within: A. 21 Days B. 22 Days C. 25 Days
An activity on a PERT network has these time estimates: optimistic = 4, most likely = 5, and pessimistic = 3. What is its expected activity time and variance? A) 3.5, 0.028 B) 4.5,1 C) 3.5, 1 D) 4.5, 0.028 E) none of the above
2. Consider the network described in the table below. Immediate Activity Predecessor(s)Pessimistic Probable Optimistic 15 10 8 K 9 8 7 L 10 6 5 M 3 3 3 N KM 9 5 1 O KM 10 7 4 P LN 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path. (c) Calculate the probability that the project will...
QUESTION 1 G E. H. C A Finish Start D. Complete the network activity diagram using the table below to answer questions 1-15. The expected activity completion times are provided in days. Each question is 1 point. Most Probable Activity Optimistic Pessimistic A 7 B 12 C 5 12 7 E 10 15 20 6 9 18 G 6 13 H 11 What is the early start (ES) time for activity F? 13 12 10 None of the above are...
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time Pessimistic Time Expected Time Variance A -- 7 9 14 1.361 B A 2 2 8 0 C A 8 12 16 0 D A 3 5 10 1.361 E B 4 6 8 0 F B 6 8 10 0 G C, F 2 3 4 0 H D 2 2 8 1.000 I H 6 8...
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Time Estimates (weeks) Activity a m b Activity Predecessor A 3 5 7 -- B 4 8 10 A C 2 3 5 A D 6 9 12 B, C E 5 9 15 D Table 9.2 Reference: Ref 9-2 Using Table 9.2, the variance for activity E is Select one: A. 2.582. B. 1.667. C. 1.291. D. 2.778.
The following table of probabilistic time estimates (in weeks) and activity predecessors are provided for a project. Time Estimates (weeks) Activity a m b Activity Predecessor A 3 5 7 -- B 4 8 10 A C 2 3 5 A D 6 9 12 B, C E 5 9 15 D Table 9.2 Reference: Ref 9-2 Using Table 9.2, the earliest start (ES) time for activity D is Select one: A. 21.67 weeks. B. 8.17 weeks. C. 12.67 weeks....
Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D - H - I - J - K. Activity Optimistic Time Most Likely Time Pessimistic Time A 7 9 14 B 2 2 8 C 8 12 16 D 3 5 10 E 4 6 8 F 6 8 10 G 2 3 4 H 2 2 8 I 6 8 16 J 4 6...