Estimated activity times and precedences are given below:
| Activity | Optimistic | Most Likely | Pessimistic | Required Precedence |
| A | 6 | 7 | 14 | |
| B | 8 | 10 | 12 | |
| C | 2 | 3 | 4 | |
| D | 6 | 7 | 8 | A |
| E | 5 | 5.5 | 9 | B, C |
| F | 5 | 7 | 9 | B, C |
| G | 4 | 6 | 8 | D, E |
| H | 2.7 | 3 | 3.5 | F |
What is the probability that the project will be completed within:
A. 21 Days
B. 22 Days
C. 25 Days
Solution:
| Activity | Optimistic time-a | Expected completion time-m | Pessimistic time-b | Expected time= (a+4*m+ b)/6 | Variance, (sigma)^2= (b-a/6)^2 |
| A | 6 | 7 | 14 | 8.00 | 1.78 |
| B | 8 | 10 | 12 | 10.00 | 0.44 |
| C | 2 | 3 | 4 | 3.00 | 0.11 |
| D | 6 | 7 | 8 | 7.00 | 0.11 |
| E | 5 | 5.5 | 9 | 6.00 | 0.44 |
| F | 5 | 7 | 9 | 7.00 | 0.44 |
| G | 4 | 6 | 8 | 6.00 | 0.44 |
| H | 2.7 | 3 | 3.5 | 3.03 | 0.02 |
| Path | Duration |
| ADG | 21.00 |
| BEG | 23.00 |
| BFH | 20.03 |
| CEG | 15.00 |
| CFH | 13.03 |
Expected project duration is 23 days through BEG
Answer: the probability that the project will be completed within:
A. 21 Days: 0.0416
| step 1 | we will find the variance of the tasks which lie on critical path | 1.33 | |||
| step 2 | mean project time (u) of critical path is= | 23.00 | |||
| step 3 | Required completion time is | 21 | |||
| step 4 | standard deviation= sqrt(variance)= | 1.155 | |||
| step 5 | because Z= (given completion time- u)/standard deviation | -1.732 | |||
| step 6 | P(z)= using NORM.S.DIST(z,true) | 0.0416 | |||
Answer: the probability that the project will be completed within:
B. 22 Days: 0.1932
| step 1 | we will find the variance of the tasks which lie on critical path | 1.33 | |||
| step 2 | mean project time (u) of critical path is= | 23.00 | |||
| step 3 | Required completion time is | 22 | |||
| step 4 | standard deviation= sqrt(variance)= | 1.155 | |||
| step 5 | because Z= (given completion time- u)/standard deviation | -0.866 | |||
| step 6 | P(z)= using NORM.S.DIST(z,true) | 0.1932 | |||
Answer: the probability that the project will be completed within:
C. 25 Days: 0.9584
| step 1 | we will find the variance of the tasks which lie on critical path | 1.33 | |||
| step 2 | mean project time (u) of critical path is= | 23.00 | |||
| step 3 | Required completion time is | 25 | |||
| step 4 | standard deviation= sqrt(variance)= | 1.155 | |||
| step 5 | because Z= (given completion time- u)/standard deviation | 1.732 | |||
| step 6 | P(z)= using NORM.S.DIST(z,true) | 0.9584 | |||
Please ask, if you have any doubts through the comment section
Do rate the answer
Estimated activity times and precedences are given below: Activity Optimistic Most Likely Pessimistic Required Precedence A...
Given the following activity list and times in days: (15 points) Activity Optimistic Most Likely Pessimistic Time Time Time A 7 10 12 B 6 8 14 C 5 9 12 D 12 14 21 E 10 12 15 F 4 5 8 G 1 3 8 H 12 15 17 NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”. Calculate the schedule duration of the critical path in days. What is the probability of the project being completed...
123) Given (Time in weeks): Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6 7 14 C 2 3 10 D 6 9 12 E 4 5 12 F 1 3 11 G 1 2 9 H 2 5 8 I 1 4 7 Determine: (a) the critical path. ( HOW DO I DO THIS WITH OUT A PREDECESSOR?) (b) the probability that the project will be completed in 22 weeks.
The following table shows estimates of activity times (weeks) for a project: Activity Optimistic Time Most Probable Time Pessimistic Time A 3 4.5 9 B 1.5 2 2.5 C 5 6 7 D 4 4.5 8 E 5 6 7 F 1 2.5 7 G 7 9 11 Suppose that the critical path is A-B-D-F-G. Use Appendix A to answer the questions. Do not round intermediate calculations. Round your answers to three decimal places. What is the probability that the...
Suppose that the following estimates of activity times (in weeks) were provided for the network shown below: Activity Optimistic Most Probable Pessimistic A 4 6 8 B 2.5 4.5 5.5 C 5 6.5 8 D 4 5.5 8 E 6.5 7.5 9 F 2 3.5 5 G 7 9 12 H 5 6 13 What is the probability that the project will be completed. If required, round your answers to four decimal places. Within 20 weeks? Within 22.5 weeks? Within...
Suppose that the following estimates of activity times (in weeks) were provided for the network shown below: Activity Optimistic Most Probable Pessimistic A 4 6 8 B 2.5 4.5 5.5 C 5 6.5 8 D 4 5.5 8 E 6.5 7.5 9 F 2 3.5 5 G 7 9 12 H 5 6 13 What is the probability that the project will be completed. If required, round your answers to four decimal places. Within 20 weeks? Within 22.5 weeks? Within...
Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B - 4 6 10 C A,B 2 5 8 D B 3 5 9 E A,C 3 6 9 F C,E 1 3 5 G C,D 3 4 9 H D 4 6 10 I F,G 3 4 9 J H 2 4 6 A).Draw the project network b).what is the expected completion time of the project. c) after your calculation, if you find one...
(15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7 9 B A 2 4 6 C A 6 9 9 D B, C 5 5 5 E C 2 5 9 F D, E 3 3 6 Use both the longest path method and ES/EF; LS/LF method for the following questions (e) What are the slack values for non-critical activities? (4 points) (f) What is the probability that the project will be...
Consider the following precedence chart: ACTIVITY PRECEDING ACTIVITIES OPTIMISTIC TIME (days) PESSIMISTIC TIME days) MOST LIKELY TIME (days) 10 10 10 B.C DE The total slack for activity D is O 2 O O O
Activity Predecessor Optimistic Most Likely Pessimistic A -- 12 16 25 B -- 7 14 22 C -- 5 10 14 D A 15 18 25 E C 8 12 18 F B 9 12 15 G F 18 22 29 H D,E,G 15 19 27 Using the table above, what is the probability that the project will be completed in 65 or fewer weeks? -greater than 20% but less than or equal to 24% -less than or equal to...
TIMES (days)
Activity
Start Node
Finish Node
OPTIMISTIC
to
MOST LIKELY
tm
PESSIMISTIC
tp
A
1
2
24
30
42
B
1
3
20
23
32
C
2
5
15
27
39
D
3
4
25
43
61
E
4
5
15
42
69
Given the Activity on Arrow Diagram and the data found in the table
above, calculate each of the following values:
Activity A………te = 31
Standard Deviation = 3
Activity B………te =
Standard Deviation =
Activity C………te...