  1. (15 points)

Activity

Immediate

Predecessor

Optimistic Time

Most likely Time

Pessimistic Time

A

NONE

4

7

9

B

A

2

4

6

C

A

6

9

9

D

B, C

5

5

5

E

C

2

5

9

F

D, E

3

3

6

Use both the longest path method and ES/EF; LS/LF method for the following questions

(e) What are the slack values for non-critical activities? (4 points)

      (f) What is the probability that the project will be completed in 26 weeks? (2 points)

(g) What is the probability that the project will be completed in 23 weeks? (2 points)

0 0
Add a comment Improve this question Transcribed image text
Answer #1


gewen that Optime the Most Pessimenti Activity Predecessor time Am To Teruete) likely time 14 79 A2 46 A 6919 Bics 55 NONE DIProject Network diagram Bimeste mon-critical activity [123216.59 OF 8:33 A - [{8-a 3 5 = 2. 4 10 91.421-99 CX 5.16 tut tu. shfor Es ar 1932)=(29=136 for F =) -(6-3)=(3) = 0.25 & Standard Normal deviation (2) Be Due time-time required to Complete thea similarly, le 723-25.49 JO:69 +0.25 +1:36 10:25 Z- 105592 from Normal de tribution tables, > Doobability for project to com

Add a comment
Know the answer?
Add Answer to:
(15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT