| Activity | Predecessor | Optimistic | Most Likely | Pessimistic |
| A | -- | 12 | 16 | 25 |
| B | -- | 7 | 14 | 22 |
| C | -- | 5 | 10 | 14 |
| D | A | 15 | 18 | 25 |
| E | C | 8 | 12 | 18 |
| F | B | 9 | 12 | 15 |
| G | F | 18 | 22 | 29 |
| H | D,E,G | 15 | 19 | 27 |
Using the table above, what is the probability that the project will be completed in 65 or fewer weeks?
-greater than 20% but less than or equal to 24%
-less than or equal to 20%
-greater than 28%
-greater than 24% but less than or equal to 28%
1. B. LESS THAN OR EQUAL TO 20%
EXPLANATION:
|
ACTIVITY |
OPTIMISTIC a |
MOST LIKELY m |
PESSIMISTIC b |
EXPECTED |
VARIANCE |
|
(a + (4m) + b) / 6 |
((b - a) / 6) ^ 2 |
||||
|
A |
12 |
16 |
25 |
17 |
4.69 |
|
B |
7 |
14 |
22 |
14 |
6.25 |
|
C |
5 |
10 |
14 |
10 |
2.25 |
|
D |
15 |
18 |
25 |
19 |
2.78 |
|
E |
8 |
12 |
18 |
12 |
2.78 |
|
F |
9 |
12 |
15 |
12 |
1 |
|
G |
18 |
22 |
29 |
23 |
3.36 |
|
H |
15 |
19 |
27 |
20 |
4 |
CPM ANALYSIS
|
ACTIVITY |
DURATION |
ES |
EF |
LS |
LF |
SLACK |
|
A |
17 |
0 |
17 |
13 |
30 |
13 |
|
B |
14 |
0 |
14 |
0 |
14 |
0 |
|
C |
10 |
0 |
10 |
27 |
37 |
27 |
|
D |
19 |
17 |
36 |
30 |
49 |
13 |
|
E |
12 |
10 |
22 |
37 |
49 |
27 |
|
F |
12 |
14 |
26 |
14 |
26 |
0 |
|
G |
23 |
26 |
49 |
26 |
49 |
0 |
|
H |
20 |
49 |
69 |
49 |
69 |
0 |
FORWARD PASS
We calculate the ES and EF values using a forward pass where the ES of an activity is the maximum EF of all the predecessor activities.
BACKWARD PASS
We calculate the LS and LF values using a backward pass where the LF of the activity is the minimum of all the successor activities.
SLACK
Slack is the value which is determined by subtracting EF from the LF or ES from the LS.
CRITICAL PATH
Critical path is the chain in the project network where the slack value of all the activities is 0, what this means is that any delay in these activities would result in delaying the entire project.
CRITICAL PATH & DURATION
B + F + G + H = 69
PROBABILISTIC ESTIMATE
VARIANCE OF CRITICAL PATH = 6.25 + 1 + 3.36 + 4 = 14.61
WITH THE GIVEN DATA
Due time = 65
Expected time = 69
Variance = 14.61
Stdev = sqrt(variance) = sqrt(14.61) = 3.82(ROUNDED)
Z = DUE - EXPECTED / STDEV
Z = 65 - 69 / 3.82 = -1.05
Z value of -1.05 gives a distribution of 0.1469 OR 14.69 % probability of completion of the project by the due time of 65
*Leave a like for the answer if you found it helpful.
Activity Predecessor Optimistic Most Likely Pessimistic A -- 12 16 25 B -- 7 14 22...
123) Given (Time in weeks): Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6 7 14 C 2 3 10 D 6 9 12 E 4 5 12 F 1 3 11 G 1 2 9 H 2 5 8 I 1 4 7 Determine: (a) the critical path. ( HOW DO I DO THIS WITH OUT A PREDECESSOR?) (b) the probability that the project will be completed in 22 weeks.
Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B - 4 6 10 C A,B 2 5 8 D B 3 5 9 E A,C 3 6 9 F C,E 1 3 5 G C,D 3 4 9 H D 4 6 10 I F,G 3 4 9 J H 2 4 6 A).Draw the project network b).what is the expected completion time of the project. c) after your calculation, if you find one...
(15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7 9 B A 2 4 6 C A 6 9 9 D B, C 5 5 5 E C 2 5 9 F D, E 3 3 6 Use both the longest path method and ES/EF; LS/LF method for the following questions (e) What are the slack values for non-critical activities? (4 points) (f) What is the probability that the project will be...
PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....
Estimated activity times and precedences are given below: Activity Optimistic Most Likely Pessimistic Required Precedence A 6 7 14 B 8 10 12 C 2 3 4 D 6 7 8 A E 5 5.5 9 B, C F 5 7 9 B, C G 4 6 8 D, E H 2.7 3 3.5 F What is the probability that the project will be completed within: A. 21 Days B. 22 Days C. 25 Days
Activity Predecessor Optimistic Time (a) Most Probable Time (m) Pessimistic Time (b) A None 2 6 10 B None 2 4 6 C A 2 4 6 D A 4 6 8 E B 6 8 22 F B 6 8 10 G C,D 2 8 12 H E,F 2 7 12 I G,H 4 8 16 Question for Blank 1: What is the Critical Path? Question for Blank 2: What is the Expected Duration of the Project? round to...
Given the following activity list and times in days: (15 points) Activity Optimistic Most Likely Pessimistic Time Time Time A 7 10 12 B 6 8 14 C 5 9 12 D 12 14 21 E 10 12 15 F 4 5 8 G 1 3 8 H 12 15 17 NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”. Calculate the schedule duration of the critical path in days. What is the probability of the project being completed...
activity preceding optimistic probability pessimistic a -- 7 9 14 b a 2 2 8 c a 8 12 16 d a 3 5 10 e b 4 6 8 f b 6 8 10 g c,f 2 3 4 h d 2 2 8 i h 6 8 16 j g,i 4 6 14 k e,j 2 2 5 a. What is the estimated time of completing the project if the critical path is A-D-H-I-J-K? b. calculate the project...
The table below gives the optimistic, most-likely, and pessimistic time estimates (in weeks) for all activities in a project. (Statistical tables are available in appendix I) Activ Predecessor totm t 2.0 5.0 8.0 3.0 4.0 5.0 4.06.08.0 5.0 6.0 7.0 3.0 6.0 9.0 D, E (i) Calculate the estimated time and variance for each task (ii) Draw the AON diagram and identify the critical path. (iii) What is the expected critical path duration and estimate a standard deviation for the...
2. Consider the network described in the table below. Immediate Activity Predecessor(s)Pessimistic Probable Optimistic 15 10 8 K 9 8 7 L 10 6 5 M 3 3 3 N KM 9 5 1 O KM 10 7 4 P LN 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path. (c) Calculate the probability that the project will...