| activity | preceding | optimistic | probability | pessimistic |
| a | -- | 7 | 9 | 14 |
| b | a | 2 | 2 | 8 |
| c | a | 8 | 12 | 16 |
| d | a | 3 | 5 | 10 |
| e | b | 4 | 6 | 8 |
| f | b | 6 | 8 | 10 |
| g | c,f | 2 | 3 | 4 |
| h | d | 2 | 2 | 8 |
| i | h | 6 | 8 | 16 |
| j | g,i | 4 | 6 | 14 |
| k | e,j | 2 | 2 | 5 |
a. What is the estimated time of completing the project if the critical path is A-D-H-I-J-K?
b. calculate the project variance?
c. Compute the project standard deviation?
d. Find the probability that the project will be completed in less than the project completion time?
Answer:
|
Activity |
Optimistic time-a |
Expected completion time-m |
Pessimistic time-b |
Expected time= (a+4*m+ b)/6 |
Variance, (sigma)^2= (b-a/6)^2 |
|
A |
7 |
9 |
14 |
9.50 |
1.36 |
|
B |
2 |
2 |
8 |
3.00 |
1.00 |
|
C |
8 |
12 |
16 |
12.00 |
1.78 |
|
D |
3 |
5 |
10 |
5.50 |
1.36 |
|
E |
4 |
6 |
8 |
6.00 |
0.44 |
|
F |
6 |
8 |
10 |
8.00 |
0.44 |
|
G |
2 |
3 |
4 |
3.00 |
0.11 |
|
H |
2 |
2 |
8 |
3.00 |
1.00 |
|
I |
6 |
8 |
16 |
9.00 |
2.78 |
|
J |
4 |
6 |
14 |
7.00 |
2.78 |
|
K |
2 |
2 |
5 |
2.50 |
0.25 |
|
Answer a: |
the project is expected to take 36.50 days along critical path ADHIJK |
||||
|
Answer b: |
total project variance= 9.53 (sum of the variance of activities on critical path) |
||||
|
Answer c: |
standard deviation= sqrt(variance)= sqrt(9.53)= 3.08 |
||||
|
step 1 |
we will find the variance of the tasks which lie on critical path ADHIJK |
||||
|
step 2 |
mean project time (u) of the critical path is= |
36.50 |
|||
|
step 3 |
Required completion time is 36.5 weeks |
||||
|
step 4 |
standard deviation= sqrt(variance)= sqrt(9.53)= |
3.087 |
|||
|
step 5 |
because Z= (given completion time- u)/standard deviation= |
0 |
|||
|
step 6 |
P(z<0)= |
0.5000 |
50.00% |
||
|
Answer d: |
probability= 50% |
||||
activity preceding optimistic probability pessimistic a -- 7 9 14 b a 2 2 8 c...
Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B - 4 6 10 C A,B 2 5 8 D B 3 5 9 E A,C 3 6 9 F C,E 1 3 5 G C,D 3 4 9 H D 4 6 10 I F,G 3 4 9 J H 2 4 6 A).Draw the project network b).what is the expected completion time of the project. c) after your calculation, if you find one...
Activity Predecessor Optimistic Time (a) Most Probable Time (m) Pessimistic Time (b) A None 2 6 10 B None 2 4 6 C A 2 4 6 D A 4 6 8 E B 6 8 22 F B 6 8 10 G C,D 2 8 12 H E,F 2 7 12 I G,H 4 8 16 Question for Blank 1: What is the Critical Path? Question for Blank 2: What is the Expected Duration of the Project? round to...
123) Given (Time in weeks): Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6 7 14 C 2 3 10 D 6 9 12 E 4 5 12 F 1 3 11 G 1 2 9 H 2 5 8 I 1 4 7 Determine: (a) the critical path. ( HOW DO I DO THIS WITH OUT A PREDECESSOR?) (b) the probability that the project will be completed in 22 weeks.
Data regarding the activities for a project are presented below. The times are in weeks. The critical path for this project is A - D - H - I - J - K. Activity Optimistic Time Most Likely Time Pessimistic Time A 7 9 14 B 2 2 8 C 8 12 16 D 3 5 10 E 4 6 8 F 6 8 10 G 2 3 4 H 2 2 8 I 6 8 16 J 4 6...
A partially solved PERT problem is detailed in the table below. Times are given in weeks. Activity Preceding Optimistic Time Probable Time Pessimistic Time Expected Time Variance A -- 7 9 14 1.361 B A 2 2 8 0 C A 8 12 16 0 D A 3 5 10 1.361 E B 4 6 8 0 F B 6 8 10 0 G C, F 2 3 4 0 H D 2 2 8 1.000 I H 6 8...
Given the following activity list and times in days: (15 points) Activity Optimistic Most Likely Pessimistic Time Time Time A 7 10 12 B 6 8 14 C 5 9 12 D 12 14 21 E 10 12 15 F 4 5 8 G 1 3 8 H 12 15 17 NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”. Calculate the schedule duration of the critical path in days. What is the probability of the project being completed...
Activity Predecessor Optimistic Most Likely Pessimistic A -- 12 16 25 B -- 7 14 22 C -- 5 10 14 D A 15 18 25 E C 8 12 18 F B 9 12 15 G F 18 22 29 H D,E,G 15 19 27 Using the table above, what is the probability that the project will be completed in 65 or fewer weeks? -greater than 20% but less than or equal to 24% -less than or equal to...
Estimated activity times and precedences are given below: Activity Optimistic Most Likely Pessimistic Required Precedence A 6 7 14 B 8 10 12 C 2 3 4 D 6 7 8 A E 5 5.5 9 B, C F 5 7 9 B, C G 4 6 8 D, E H 2.7 3 3.5 F What is the probability that the project will be completed within: A. 21 Days B. 22 Days C. 25 Days
(15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7 9 B A 2 4 6 C A 6 9 9 D B, C 5 5 5 E C 2 5 9 F D, E 3 3 6 Use both the longest path method and ES/EF; LS/LF method for the following questions (e) What are the slack values for non-critical activities? (4 points) (f) What is the probability that the project will be...
Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m b Time (t) o 2 3 2 1 B с D NWN mlm A 1 A,B 2 4 1 6 7 9 F 1 с с DE F,G 4 2 5 3 G 4 12 H 2 4 From the table above find the flowing answers. 1. Construct the project Network 2. Find the expected duration and Variance of each activity 3. Find the...