Question

Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B -...

Activity

Predecessor

Optimistic time

Most likely time

Pessimistic time

A

-

3

5

8

B

-

4

6

10

C

A,B

2

5

8

D

B

3

5

9

E

A,C

3

6

9

F

C,E

1

3

5

G

C,D

3

4

9

H

D

4

6

10

I

F,G

3

4

9

J

H

2

4

6

A).Draw the project network b).what is the expected completion time of the project. c) after your calculation, if you find one path that has the longest completion time, why it is not necessarily critical path? d.) what are the variances for each activity. e) assuming that the path completion times are independent, what is the probability of completing the project in 25 weeks? f.) given the assumption in part(e), what is the probabilitu of completing the project in 20 weeks?

0 0
Add a comment Improve this question Transcribed image text
Request Professional Answer

Request Answer!

We need at least 10 more requests to produce the answer.

0 / 10 have requested this problem solution

The more requests, the faster the answer.

Request! (Login Required)


All students who have requested the answer will be notified once they are available.
Know the answer?
Add Answer to:
Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B -...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Similar Homework Help Questions
  • (15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7...

    (15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7 9 B A 2 4 6 C A 6 9 9 D B, C 5 5 5 E C 2 5 9 F D, E 3 3 6 Use both the longest path method and ES/EF; LS/LF method for the following questions (e) What are the slack values for non-critical activities? (4 points)       (f) What is the probability that the project will be...

  • 123) Given (Time in weeks): Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6...

    123) Given (Time in weeks): Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6 7 14 C 2 3 10 D 6 9 12 E 4 5 12 F 1 3 11 G 1 2 9 H 2 5 8 I 1 4 7 Determine: (a) the critical path. ( HOW DO I DO THIS WITH OUT A PREDECESSOR?) (b) the probability that the project will be completed in 22 weeks.

  • PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A -...

    PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....

  • Activity Predecessor Optimistic Time (a) Most Probable Time (m) Pessimistic Time (b) A None 2 6...

    Activity Predecessor Optimistic Time (a) Most Probable Time (m) Pessimistic Time (b) A None 2 6 10 B None 2 4 6 C A 2 4 6 D A 4 6 8 E B 6 8 22 F B 6 8 10 G C,D 2 8 12 H E,F 2 7 12 I G,H 4 8 16 Question for Blank 1: What is the Critical Path? Question for Blank 2: What is the Expected Duration of the Project? round to...

  • activity preceding optimistic probability pessimistic a -- 7 9 14 b a 2 2 8 c...

    activity preceding optimistic probability pessimistic a -- 7 9 14 b a 2 2 8 c a 8 12 16 d a 3 5 10 e b 4 6 8 f b 6 8 10 g c,f 2 3 4 h d 2 2 8 i h 6 8 16 j g,i 4 6 14 k e,j 2 2 5 a. What is the estimated time of completing the project if the critical path is A-D-H-I-J-K? b. calculate the project...

  • Activity Predecessor Optimistic Most Likely Pessimistic A -- 12 16 25 B -- 7 14 22...

    Activity Predecessor Optimistic Most Likely Pessimistic A -- 12 16 25 B -- 7 14 22 C -- 5 10 14 D A 15 18 25 E C 8 12 18 F B 9 12 15 G F 18 22 29 H D,E,G 15 19 27 Using the table above, what is the probability that the project will be completed in 65 or fewer weeks? -greater than 20% but less than or equal to 24% -less than or equal to...

  • Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m...

    Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m b Time (t) o 2 3 2 1 B с D NWN mlm A 1 A,B 2 4 1 6 7 9 F 1 с с DE F,G 4 2 5 3 G 4 12 H 2 4 From the table above find the flowing answers. 1. Construct the project Network 2. Find the expected duration and Variance of each activity 3. Find the...

  • 1- Consider the table shown below: Task Predecessor Time (weeks) Expected time Variance of time Optimistic...

    1- Consider the table shown below: Task Predecessor Time (weeks) Expected time Variance of time Optimistic Most likely Pessimistic A - 1 3 5 B A 2 6 10 C B 4 7 10 D B, C 1 2 9 E D 2 4 6 F D,E 4 7 10 G F 1 3 5 a) Calculate expected time and variance for each task.   b) Find the critical path and expected project competition time? c) What is the probability of...

  • Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic...

    Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic                         Time                Time                Time A                     7                      10                    12 B                     6                      8                      14 C                     5                      9                      12 D                     12                    14                    21 E                      10                    12                    15 F                      4                      5                      8 G                     1                      3                      8 H                     12                    15                    17 NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”. Calculate the schedule duration of the critical path in days. What is the probability of the project being completed...

  • The following table shows estimates of activity times (weeks) for a project: Activity Optimistic Time Most...

    The following table shows estimates of activity times (weeks) for a project: Activity Optimistic Time Most Probable Time Pessimistic Time A 3 4.5 9 B 1.5 2 2.5 C 5 6 7 D 4 4.5 8 E 5 6 7 F 1 2.5 7 G 7 9 11 Suppose that the critical path is A-B-D-F-G. Use Appendix A to answer the questions. Do not round intermediate calculations. Round your answers to three decimal places. What is the probability that the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT