Question

123) Given (Time in weeks): Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6...

123) Given (Time in weeks):

Activity

Optimistic

Most Likely

Pessimistic

A

3

4

5

B

6

7

14

C

2

3

10

D

6

9

12

E

4

5

12

F

1

3

11

G

1

2

9

H

2

5

8

I

1

4

7

Determine:

(a) the critical path. ( HOW DO I DO THIS WITH OUT A PREDECESSOR?)

(b) the probability that the project will be completed in 22 weeks.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Conver the table like this:

Activity Optimistic time estimate(to) 4 * Most likely time estimate(tm) Pessimistic time estimate(tp) to+4tm+tp Time estimate = to+4tm+tp/6
A 3 16 5 24 4
B 6 28 14 48 8
C 2 12 10 24 4
D 6 36 12 54 9
E 4 20 12 36 6
F 1 12 11 24 4
G 1 8 9 18 3
H 2 20 8 30 5
I 1 16 7 24 4

And without the predecessor, it's not able to calculate the critical path because, we never know how these paths are connected and we can randomly assume any paths to obtain our solution.

For example, If Source is A and destination is H, and

A,C,F,H might be a solution

AGDH might be a solution

and we get numerous amount of solutions and critical path can be calculated accordingly.

The probability can be calculated by No.of required cases/ total no.of cases. If you get 22 weeks for 3 paths out of 8, 3/8 will be your probability

Note: I tried my best answering the question. It'd be appreciated if you leave an upvote. Thanks in advance.

Add a comment
Know the answer?
Add Answer to:
123) Given (Time in weeks): Activity Optimistic Most Likely Pessimistic A 3 4 5 B 6...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • (15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7...

    (15 points) Activity Immediate Predecessor Optimistic Time Most likely Time Pessimistic Time A NONE 4 7 9 B A 2 4 6 C A 6 9 9 D B, C 5 5 5 E C 2 5 9 F D, E 3 3 6 Use both the longest path method and ES/EF; LS/LF method for the following questions (e) What are the slack values for non-critical activities? (4 points)       (f) What is the probability that the project will be...

  • Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B -...

    Activity Predecessor Optimistic time Most likely time Pessimistic time A - 3 5 8 B - 4 6 10 C A,B 2 5 8 D B 3 5 9 E A,C 3 6 9 F C,E 1 3 5 G C,D 3 4 9 H D 4 6 10 I F,G 3 4 9 J H 2 4 6 A).Draw the project network b).what is the expected completion time of the project. c) after your calculation, if you find one...

  • Activity Predecessor Optimistic Time (a) Most Probable Time (m) Pessimistic Time (b) A None 2 6...

    Activity Predecessor Optimistic Time (a) Most Probable Time (m) Pessimistic Time (b) A None 2 6 10 B None 2 4 6 C A 2 4 6 D A 4 6 8 E B 6 8 22 F B 6 8 10 G C,D 2 8 12 H E,F 2 7 12 I G,H 4 8 16 Question for Blank 1: What is the Critical Path? Question for Blank 2: What is the Expected Duration of the Project? round to...

  • Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic...

    Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic                         Time                Time                Time A                     7                      10                    12 B                     6                      8                      14 C                     5                      9                      12 D                     12                    14                    21 E                      10                    12                    15 F                      4                      5                      8 G                     1                      3                      8 H                     12                    15                    17 NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”. Calculate the schedule duration of the critical path in days. What is the probability of the project being completed...

  • The following table shows estimates of activity times (weeks) for a project: Activity Optimistic Time Most...

    The following table shows estimates of activity times (weeks) for a project: Activity Optimistic Time Most Probable Time Pessimistic Time A 3 4.5 9 B 1.5 2 2.5 C 5 6 7 D 4 4.5 8 E 5 6 7 F 1 2.5 7 G 7 9 11 Suppose that the critical path is A-B-D-F-G. Use Appendix A to answer the questions. Do not round intermediate calculations. Round your answers to three decimal places. What is the probability that the...

  • PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A -...

    PERT Analysis: The following represents a project with four activities. All times are in weeks. Activity Immediate Predecessor Optimistic Time Most Likely Time Pessimistic Time A - 3 8 14 B - 8 8 8 C A 6 9 18 D B 6 11 17 According to the data in the above Table: What is the critical path? What is the minimum expected completion time for the project? According to the above Table, there are four activities in the project....

  • Estimated activity times and precedences are given below: Activity Optimistic Most Likely Pessimistic Required Precedence A...

    Estimated activity times and precedences are given below: Activity Optimistic Most Likely Pessimistic Required Precedence A 6 7 14 B 8 10 12 C 2 3 4 D 6 7 8 A E 5 5.5 9 B, C F 5 7 9 B, C G 4 6 8 D, E H 2.7 3 3.5 F What is the probability that the project will be completed within: A. 21 Days B. 22 Days C. 25 Days

  • Activity Predecessor Optimistic Most Likely Pessimistic A -- 12 16 25 B -- 7 14 22...

    Activity Predecessor Optimistic Most Likely Pessimistic A -- 12 16 25 B -- 7 14 22 C -- 5 10 14 D A 15 18 25 E C 8 12 18 F B 9 12 15 G F 18 22 29 H D,E,G 15 19 27 Using the table above, what is the probability that the project will be completed in 65 or fewer weeks? -greater than 20% but less than or equal to 24% -less than or equal to...

  • Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m...

    Pert project method Activity Predecessors A group 5 optimistic Most likely Pessimistic Expected Variance a m b Time (t) o 2 3 2 1 B с D NWN mlm A 1 A,B 2 4 1 6 7 9 F 1 с с DE F,G 4 2 5 3 G 4 12 H 2 4 From the table above find the flowing answers. 1. Construct the project Network 2. Find the expected duration and Variance of each activity 3. Find the...

  • 1- Consider the table shown below: Task Predecessor Time (weeks) Expected time Variance of time Optimistic...

    1- Consider the table shown below: Task Predecessor Time (weeks) Expected time Variance of time Optimistic Most likely Pessimistic A - 1 3 5 B A 2 6 10 C B 4 7 10 D B, C 1 2 9 E D 2 4 6 F D,E 4 7 10 G F 1 3 5 a) Calculate expected time and variance for each task.   b) Find the critical path and expected project competition time? c) What is the probability of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT