The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is
4 comma 5004,500
units per 40-hour workweek:
Task |
Performance Time (seconds) |
Predecessors |
|
A |
2424 |
minus− |
|
B |
3030 |
A |
|
C |
1414 |
A |
|
D |
1515 |
A |
|
E |
1212 |
B, C |
|
F |
3030 |
D, E |
This exercise only contains parts b, c, d, e, and f.
b) Given the demand, the cycle time for the production of the new train set =
nothing
seconds (round your response to one decimal place).
c) The theoretical minimum number of workstations = (round your response up to the next whole number)
d) Using the longest operation time rule, the assignment of tasks to workstations should: (Hint: Number workstations
e) The total idle time per cycle for the process = nothing seconds (enter your response as a whole number.)
f) The efficiency of the assembly line with 5 workstations = nothing % (enter your response as a percentage rounded to one decimal place).
If one used 6 workstations instead of 5, the efficiency of the assembly line would be = nothing % (enter your response as a percentage rounded to one decimal place).
b)
Cycle time = 40 hours * 60 minutes * 60 seconds / 4500 units = 32 seconds per unit
c)
Sum of all task times = 24+30+14+15+12+30 = 125 seconds
Theoretical minimum number of workstations = 125 / 32 = 3.9 or 4 stations
d)
Station | Remaining time | Eligibles | Was Fit | Assigned time | Time remains | Idle time | Improved Cycle time | Idle time based on improved cycle time |
I | 32 | A | A | 24 | 8 | |||
8 | B, C, D | - | - | 8 | 8 | 24 | 6 | |
II | 32 | B, C, D | B | 30 | 2 | |||
2 | C, D | - | - | 2 | 2 | 30 | 0 | |
III | 32 | C, D | D | 15 | 17 | |||
17 | C | C | 14 | 3 | ||||
3 | E | - | - | 3 | 3 | 29 | 1 | |
IV | 32 | E | E | 12 | 20 | |||
20 | F | - | - | 20 | 20 | 12 | 18 | |
V | 32 | F | F | 30 | 2 | |||
2 | - | - | - | 2 | 2 | 30 | 0 | |
Totals | 125 | 35 | 25 |
So, the assignment is as follows:
Station-I --> A
Station-II --> B
Station-III ---> C, D
Station-IV ---> E
Station-V ---> F
For (e) and (f), there can two sets of answers - using improved cycle time and using the required cycle time. Both are shown below.
e)
Total idle time (based on improved cycle time) = 25 seconds per cycle
Total idle time (based on required cycle time) = 35 seconds per cycle
f)
Efficiency (based on improved cycle time) = Sum of all task time / (# stations * max cycle time) = 125 / (5*30) = 83.3%
Efficiency (based on required cycle time) = Sum of all task time / (# stations * reqd. cycle time) = 125 / (5*32) = 78.1%
The Action Toy Company has decided to manufacture a new train set, the production of which...
Hello,
I need to see the solution, how they got these numbers? Will
appreciate help.
The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,600 units per 40-hour workweek: Predecessors Task A B С D E F Performance Time (seconds) 22 27 14 15 10 28 А A А B, C DE This exercise only contains parts b, c, d, e, and...
The Action Toy Company has decided to manufacture a new toy tractor, the production of which is broken into six steps. The demand for the tractor is 4,800 units per 40-hour workweek. TASK, PERFORMANCE TIME(SECONDS), PREDECESSORS A 20 None B 30 A C 15 A D 15 A E 10 B,C F 30 D,E A) Draw a precedence diagram B) What is the cycle time? C) What is the theoretical minimum number of workstations? D) Assign tasks to workstations E)...
Layout Strategies Homework The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps describe in the table below. The demand for the train is 4,800 units per 40 hour workweek. PLEASE ANSWER ALL QUESTIONS ONE BY ONE. Task Performance Time (second) Predecessors 20 А 15 15 DE 30 120 a) Draw a precedence diagram of this operation. b) Given the demand, what is the cycle time for this operation?...
Question d) The idle time for the assembly line per cycle =
_____ minute(s)
The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 60 boats. Given the following information: Task Predecessors Performance Time (mins) 2. 1 1 A B...
I
need help with the total idle time per cycle question, please
include steps with explanations
& Problem 9.15 The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. T Question Help he demand for the train is 4,800 units p 40-hour workweek Performance Time Task Predecessors 20 27 B, C D.E 12 This exeroise only contains parts b, c, d, e, and f b) Given the demand, the...
For the set of tasks given below, do the following: Task Task Time(seconds) Immediate Predecessor A 45 - B 11 A C 9 B D 50 - E 26 D F 11 E G 12 C H 10 C I 9 F, G, H J 10 I 193 b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a seven-hour day. (Round your answers to 1 decimal place.) The minimum cycle...
A toy company has decided to manufacture a new toy tractor, the production of which is broken into six steps. The demand for the tractor is 3800 units per 40-hour workweek: Performance Time (Seconds) 20 30 15 as Predecessor None 10 B, C 30 D, E What is the maximum cycle time that will ensure that the demand is met? (That is, what is a threshold on the cycle time, which is in seconds, that will ensure that demand is...
Wild Widget must set up an assembly line for widgets. Forecasts show that 68 units per hour should be produced. The tasks required, task times, and precedence relationships are as follows: TTT Task A B Time (seconds) 10 21 20 Predecessors A A 28 E 12 D 10 D G 40 E,F b. What is the takt time? (Round your answer to the nearest whole number.) Takt time seconds per unit c. What is the theoretical number of workstations? (Round...
Tailwind, Inc, produces high-quality but expensive training shoes for runners. The Tailwind shoe, which sells for $210, contains both gas- and liquid filed compartments to provide more stability and better protection against knee, foot, and back injuries Manufacturing the shoes requires 10 separate tasks. There are 400 minutes available for manufacturing the shoes in the plant each day. Daily demand is 62. The information for the tasks is as follows Task Performance Time (mins) Predecessors <UO a-b) The correct precedence...
em 9.14 Question Help 3 per Sue Hains Appliances wants to establish an assembly line to manufacture its new product, the Micro Popcom Popper. The goal is to produce five poppers per hour The tasks, task times, and immediate predecessors for producing one Micro Popcorn Popper are as follows: estions: 3 Task tion 1 (0/1) А Performance Time Task Must Follow (mins Task Usted Below 10 12 А B 11 B,C 7 С 5 DE B D E F a)...