Question

Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects...

Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the shorter payback, some value may be forgone. How much value will be lost in this instance? Note that under some conditions choosing projects on the basis of the shorter payback will not cause value to be lost.

WACC: 8%

Year 0 1 2 3 4
CFS -$1,100 $390 $390 $390 $390
CFL -$2,200 $735 $735 $735 $735

$42.68

$40.12

$38.80

$36.44

$34.72

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer : There will be loss of value of $ 42.68

Calculated as

Pay back period S = $1100/$390 = 2.82 yrs

Pay back period of Project L = $2200/735 = 2.99 years

So Project S will be selected it has shorter pay back period

Calculation of Loss in Value

YEAR CASH INFLOW PV @ 10% PRESENT VALUE
1 TO 4 $                  390 3.312100 $            1,291.72
$            1,291.72
initial investment $          (1,100.00)
npv $                191.72
YEAR CASH INFLOW PV @ 10% PRESENT VALUE
1 TO 4 $                  735 3.312100 $            2,434.39
$            2,434.39
initial investment $          (2,200.00)
npv $                234.39
Loss in Value = $191.72-$234.39 = $                (42.67)

Hit Thumbs up if satisfied

Have any query mention in comment section please

Thank you

Add a comment
Know the answer?
Add Answer to:
Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 8 of 24 Yonan Inc. is considering Projects Sand L, whose cash flows are shown...

    Question 8 of 24 Yonan Inc. is considering Projects Sand L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the shorter payback, some value may be forgone. How much value will be lost in this instance? Note that under some conditions choosing projects on the basis of the shorter payback will not cause value to be lost. WACC: 10.25% 1 3 $500...

  • Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...

    Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? Note that under some conditions choosing projects on the basis of the MIRR will cause $0.00 value to be lost. WACC: 10.75% 4 -$1,100 -$2,200 12 $375 $375 $725...

  • Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects...

    Nast Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher MIRR rather than the one with the higher NPV, how much value will be forgone? WACC: 8% Year 0 1 2 3 4 CFS -$1,100 $380 $380 $380 $380 CFL -2,200 $730 $730 $730 $730 Options: 59.24, 52,83, 48,56, 43.70, 39.24

  • Question 20 1 pts Yonan Inc. is considering Projects S and L, whose cash flows are...

    Question 20 1 pts Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the shorter payback, some value may be forgone. How much value will be lost in this instance? Note that under some conditions choosing projects on the basis of the shorter payback will not cause value to be lost. WACC: 9.50% -$950 $500...

  • Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects...

    Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, so no value...

  • Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects...

    Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under some conditions choosing projects on the basis of the IRR will cause $0.00 value to be lost. Identify also the range of discounting rates in which project L will be selected. WACC: Year...

  • Tesar Chemicals is considering Projects S and L, whose cash flows are shown below. These projects...

    Tesar Chemicals is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone, i.e., what's the chosen NPV versus the maximum possible NPV? Note...

  • Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These...

    Moerdyk & Co. is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. If the decision is made by choosing the project with the higher IRR, how much value will be forgone? Note that under certain conditions choosing projects on the basis of the IRR will not cause any value to be lost because the one with the higher IRR will also have the higher NPV, i.e., no...

  • Question 3 of 24 Tesar Chemicals is considering Projects S and L, whose cash flows are...

    Question 3 of 24 Tesar Chemicals is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and not repeatable. The CEO believes the IRR is the best selection criterion, while the CFO advocates the NPV. If the decision is made by choosing the project with the higher IRR rather than the one with the higher NPV, how much, if any, value will be forgone, i.e., what's the chosen NPV versus the...

  • Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects...

    Carolina Company is considering Projects S and L, whose cash flows are shown below. These projects are mutually exclusive, equally risky, and are not repeatable. WACC: 7.75%                                               Year            0                 1           2           3          4 CFS        −$1,050     $675     $650               CFL         −$1,050     $360     $360    $360   $360 If the decision is made by choosing the project with the higher IRR, how much value will be forgone? What is the underlying...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT