1) Villanova, Inc., has done a cost analysis for its production of rubber stamps. The following activities and cost drivers have been developed:
| Activity | Cost Formula |
| Design | $5,000 + $0.05 per machine hour |
| Machining | $25,000 + $0.01 per machine hour |
| Setups | $35 per batch |
| Purchasing | $50 + $15 per purchase order |
Following are the actual costs of producing 35,000 rubber stamps:
1,000 machine hours; 5 batches; 30 purchase orders
| Design | $5,080 |
| Machining | ? |
| Setups | ? |
| Purchasing | $600 |
The following variances were given in the activity performance
report:
| Design | ? |
| Machining | $40 F |
| Setups | $15 F |
| Purchasing | ? |
What is the activity variance for design?
a.$100 U
b.$40 F
c.$30 U
d.$15 F
2)
Selling and administrative costs are classified as
a.conversion costs.
b.factory overhead.
c.product costs.
d.period costs.
3)
The Davidson Company uses a weighted average process costing
system. The following information was reported for the Assembly
Process for January. Materials are added at the beginning of the
process and are 100%.
| Units: | units | % complete for conversions |
| work in process, 1/1 | 60,000 | 15% |
| started | 105,000 | |
| work in process, 1/31 | 40,000 | 20% |
| Costs: | ||
| Materials | Conversion | |
| beginning work in process | $ 16,500 | $ 33,250 |
| current costs | $643,500 | $332,500 |
What is the cost per unit for materials?
a.$3.90
b.$2.75
c.$4.96
d.$4.00
e.None of these choices are correct.
Solution 1:
Standard cost of design at 1000 machine hours = $5,000 + 1000*$0.05 = $5,050
Actual cost of design = $5,080
Activity variance for design = Standard cost - Actual cost - $5,050 - $5,080 = $30 U
Hence option c is correct.
Solution 2:
Selling and administrative costs are classified as "Period costs"
Hence option d is correct.
Solution 3:
Equivalent units of material = Units completed and transferred out + Units in ending WIP
= (60000 + 105000 - 40000) + 40000 = 165000 units
Total cost to be accounted for material = Beginning WIP + current cost = $16,500 + $643,500 = $660,000
Cost per equivalent unit of material = Total cost to account for / Equivalent unit of material
= $660,000 / 165000 = $4 per unit
Hence option d is correct,
1) Villanova, Inc., has done a cost analysis for its production of rubber stamps. The following...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. (Round your answers to 2 decimal places.) Activity Rate per Machine Hour Activity Machining Design Costs Setup per Design...
Gable Company uses three activity cost pools. Each pool has a cost driver. Information for Gable Company follows: Activity Cost Pools Machining Designing costs Setup costs Total Cost of Pool Cost Driver $312,000 Number of machine hours 73,600 Number of design hours 71,600 Number of batches Estimated Cost Driver 80,000 8,000 500 Required: 1. Compute the activity rate for each activity. (Round your answers to 2 decimal places.) Activity Rate per Machine Hour Activity Machining Design Costs Setup per Design...
CALCULATOR PAINTER VERSION BACK NEXT Question 1 Morgana Company identifies three activities in its manufacturing process: machine setups, machining, and inspections. Estimated annual overhead cost for each activity is $205,900, $265,100, and $78,400, respectively. The cost driver for each activity and the estimated annual usage are number of setups 2,900, machine hours 24,100, and number of inspections 1,600 Compute the overhead rate for each activity. Machine setups $ per setup Machining $ per machine hour Inspections per inspection
Question 1 --/1 View Policies Current Attempt in Progress Morgana Company identifies three activities in its manufacturing process: machine setups, machining, and inspections. Estimated annual overhead cost for each activity is $177,500, $306,000, and $57,600, respectively. The cost driver for each activity and the estimated annual usage are number of setups 2,500, machine hours 25,500, and number of inspections 1,200. Compute the overhead rate for each activity. Machine setups $ per setup Machining per machine hour Inspections र per inspection...
Please answer all :))
Exercise 4-1 (Video) Saddle Inc. has two types of handbags: standard and custom. The controller has decided to use a plantwide overhead rate based on direct labor costs. The president has heard of activity-based costing and wants to see how the results would differ if this system were used. Two activity cost pools were developed: machining and machine setup. Presented below is information related to the company's operations. Direct labor costs Machine hours Setup hours Standard...
Question 1 Swifty Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Swifty accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Cost Drivers Estimated Use of Cost Product Drivers per Activity BC113 Product AD908 Activity Cost Pools Machine setup...
Flynn Industries has three activity cost pools and two
products. It estimates production 2,000 units of Product BC113 and
1,000 of Product AD908. Having identified its activity cost pools
and the cost drivers for each pool, Flynn accumulated the following
data relative to those activity cost pools and cost drivers.
Annual Overhead Data
Estimated Use of
Cost Drivers per Product
Activity Cost Pools
Cost Drivers
Estimated
Overhead
Estimated Use of Cost
Drivers per Activity
Product
BC113
Product
AD908
Machine setup...
Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Product AD908 Activity Cost Pools Machine setup Machining Packing Estimated Overhead $18,500 106,920 35,640 Cost Drivers Setups Machine hours...
Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Use of Cost Drivers per Product Estimated Use of Cost Product Product Drivers BC113 AD908 per Activity Estimated Overhead Activity Cost Pools Cost Drivers Machine setup...
Flynn Industries has three activity cost pools and two products. It estimates production 2,000 units of Product BC113 and 1,000 of Product AD908. Having identified its activity cost pools and the cost drivers for each pool, Flynn accumulated the following data relative to those activity cost pools and cost drivers. Annual Overhead Data Estimated Overhead $17,500 120,750 28,670 Activity Cost Pools Machine setup Machining Packing 20 Estimated Use of Cost Drivers per Product Estimated Use of Cost Product Product Drivers...