Question

Scraper tare (empty) 65000 kg Average load carried 32 m3 Density of material, in bank...

Scraper tare (empty)

65000 kg

Average load carried

32 m3

Density of material, in bank

1550 kg/ m3

Load factor I

0.6

Distribution of load to driving wheels (% of gross weight)

59 %

Uphill grade on haul road, loaded

4 %

Traction coefficient, haul road

0.55

Rolling Resistance Factor, loaded

0.39 kN/t

Average speed, haul

18 km/hr

Haul distance

1020 m

Average speed, return empty

44 km/hr

Return distance (by different route)

1130 m

Efficiency factor (operator and scraper together)

41 min/hr

Fixed time is made up of:

Spot time

0.6 min

Load time

2.7 min

Dump time

1.4 min

Using the information above calculate the following:

a) Calculate the gross vehicle weight (GVW) (kg).

b) Calculate maximum tractive force (kN) on road at driving wheels when loaded.

c) Calculate the effective grade % on the haul road.

d) Calculate total resistance (kg or kN) while hauling.

e) Calculate the total cycle time (minutes).

f) Calculate production rate, in Bank m3/hr.

0 0
Add a comment Improve this question Transcribed image text
Answer #1

acter Au. load Cs Scanned with CamScanner= GS00+ 297Go 947Go diung coheed 5CHapex tate (erm Vehicle colap toseJ racon ccet TOl toad factex cned with CamScanner0. C 49 100 ο.kq Total k9e% t 어. vehicle Colon todes Tracion coic 0.SS 0.1003G Scanned with CamScarrner(田 fdade .38 4D 40 039 .03 stoce V) cohile Scanned withGsoooG0o Grade 4% 004 58 tou 54 anned with CamScanner14G9. Kas. ,了 Q052.4 e) Total cycle Lie = 1020 m Scanhed with CamScanger44000 m Total cjcle Li* Hau Speed Kettsn speed 300 133.33 4-1 1 l03 Cle lisne Scanned with- CamScanner CSTe ao pooducl o soapex mache the SCHape bocol.me 업 the emply Scxapex the load ime (LT), accelevalig, decetexaliq ond og at e,Scanned with CamScanner

Add a comment
Know the answer?
Add Answer to:
Scraper tare (empty) 65000 kg Average load carried 32 m3 Density of material, in bank...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 12. A truck carrying a load of 9 kN has a mass of 450 kg. The...

    12. A truck carrying a load of 9 kN has a mass of 450 kg. The driving wheels are 1.066 m in diameter. The total coefficient of air and road resistance is 0.22. The gear ratio and efficiencies are e = 8:1, 1-92% for the transmission and e = 5:1, n=95% for the differential, respectively. T e-8:1, 7-92% I Engine e-5:1, n=95% Differential Transmission Address the following: a) compute the total tracking force (N) b) compute the wheel rotational speed...

  • please help me. Problem 2: Evaluate cost and production using a 3-cy hoe to load wet gravel (2980 lb/lcy) into 14 cy...

    please help me. Problem 2: Evaluate cost and production using a 3-cy hoe to load wet gravel (2980 lb/lcy) into 14 cy trucks. Assume a bucket fill factor of 105% and that the hoe bucket swing cycle time is 24 sec. the truck empty weight is 36860 lb, and a rated payload of 40000 lb. Dump time will be 1.3 min. the haul distance is 2.5 miles from the pit to the plant up a 3% grade. The rolling resistance...

  • (50) 7. Analyze the following operation. A 385C Excavator will be used to load material into a CAT 740 (no ejector) articulated truck. The excavator is equipped with a 6 cy heaped bucket and is...

    (50) 7. Analyze the following operation. A 385C Excavator will be used to load material into a CAT 740 (no ejector) articulated truck. The excavator is equipped with a 6 cy heaped bucket and is capable of cycling every 30 seconds. The material being loaded weighs 3,300 lbs cy. The job efficiency is 90%. The trucks will be hauling the nmaterial 4000 feet over a road with a total rolling resistance of 9% to the dumpsite and 10% total rolling...

  • Part 1 Complete the following Earthwork Sheet Material: Earth and Gravel, Swell Factor: 83 Strip fill(cy...

    Part 1 Complete the following Earthwork Sheet Material: Earth and Gravel, Swell Factor: 83 Strip fill(cy Total till och Total cut beyl Adj fill (byl Sum (beyl Mass ordinate 1.23 056 2.37 1.20 2.36 3.07 3.60 3.77 3.09 3.01 4.65 Strip cut (boyil 0.04 1.04 097 3.22 2.08 2.33 2.51 1.85 161 1.74 0.88 109 35.70 5.58 18 3.12 2.03 6.77 2.01 2.53 0.82 1.08 1.20 1.92 1.59 1.82 3.95 3.25 2.74 150 7.42 556 80 End-area End area cut...

  • Part 2 Based upon the results to part 1, the project requires hauling materials to, or...

    Part 2 Based upon the results to part 1, the project requires hauling materials to, or from, the site. The following equipment is available for earthwork operations: - One 5-cy heaped capacity bucket loader; a 0.5 min cycle time; 90% fill capacity. - One 7-cy heaped capacity bucket loader; a 0.6 min cycle time; 90% fill capacity. 45.9-cy heaped capacity off-road trucks; a 0.5 min dump time; 100% fill capacity. - Loaded trucks travel through the following three sections: Haul...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT