| Arrow Construction Company | ||||
| Ans to 1 | Calculation of Gross Profit | |||
| Particulars | 2021 | 2022 | 2023 | |
| Contract Price | 8,210,000 | 8,210,000 | 8,210,000 | A |
| Cost Incurred during the year | 2,070,000 | 2,570,000 | 3,870,000 | B |
| Estimated cost to complete | 4,070,000 | 3,705,000 | - | C |
| Cost Incurred to date | 2,070,000 | 4,640,000 | 8,510,000 | D |
| (Sum total of the cost incurred during the year) | ||||
| Estimated total cost | 6,140,000 | 8,345,000 | 8,510,000 | E=C+D |
| Percentage complete | 33.71% | 55.60% | 100.00% | F=D/E |
| (Cost Incurred to date/Estimated total cost) | ||||
| Revenue to be recognized | 2,767,866 | 1,797,071 | 3,645,063 | G |
| (Contract Price*Percentage complete)- revenue previously recognized | ||||
| Year 2021: 33.71% completed. Revenue recognized = 33.71% x $ 8,210,000 = $ 2,767,866. | ||||
| Year 2022: 55.60% completed. Revenue recognized = 55.60% x $ 8,210,000 – $ 2,767,866 (previously recognized) = $ 1,797,071. | ||||
| Year 2023: 100% completed. Revenue recognized = 100% x $ 8,210,000 – $ 2,767,866- $ 1,797,071 (previously recognized) = $ 3,645,063. | ||||
| Gross Profit/(Loss) | 697,866 | (772,929) | (224,937) | H=G-B |
| Billings during the year | 2,570,000.00 | 2,820,000.00 | ||
| Collection during the year | 2,320,000.00 | 2,545,000.00 | ||
| 2021 | 2022 | |||||
| Ans to 2a and 2b | Journal Entries | Debit $ | Credit $ | Debit $ | Credit $ | |
| Costs Incurred | CIP (Work-in-progress) | 2,070,000 | 2,570,000 | |||
| Cash | 2,070,000 | 2,570,000 | ||||
| Billing | Accounts Receivable | 2,570,000 | 2,820,000 | |||
| Billing on CIP | 2,570,000 | 2,820,000 | ||||
| Receiving Payments | Cash | 2,320,000 | 2,545,000 | |||
| Accounts Receivable | 2,320,000 | 2,545,000 | ||||
| Period end adjustments for Revenue | Construction Expense | 2,070,000 | ||||
| (Gross Profit entry) | CIP (Work-in-progress) | 697,866 | ||||
| Construction Revenue | 2,767,866 | |||||
| Period end adjustments for Revenue | Construction Expense | 2,570,000 | ||||
| (Gross Loss entry) | CIP (Work-in-progress) | 772,929 | ||||
| Construction Revenue | 1,797,071 | |||||
| Workings for Balance Sheet | |
| CIP (Work-in-progress) | |
| Account | Amount ($) |
| Cash | 2,070,000 |
| Construction Revenue | 697,866 |
| Balance at the end of 2021 | 2,767,866 |
| Cash | 2,570,000 |
| Construction Revenue | (772,929) |
| Balance at the end of 2022 | 4,564,937 |
| Accounts Receivable | |
| Account | Amount ($) |
| Billing on CIP | 2,570,000 |
| Cash | (2,320,000) |
| Balance at the end of 2021 | 250,000 |
| Billing on CIP | 2,820,000 |
| Cash | (2,545,000) |
| Balance at the end of 2022 | 525,000 |
| Billing on CIP | |
| Account | Amount ($) |
| Accounts Receivable | 2,570,000 |
| Balance at the end of 2021 | 2,570,000 |
| Accounts Receivable | 2,820,000 |
| Balance at the end of 2022 | 5,390,000 |
| Ans to 3a and 3b | ||
| Balance Sheet (Partial) | 2021 | 2022 |
| Current Assets: | ||
| CIP (Work-in-progress) | 2,767,866 | 4,564,937 |
| Accounts Receivable | 250,000 | 525,000 |
| 3,017,866 | 5,089,937 | |
| Current Liabilities: | ||
| Billing on CIP | 2,570,000.00 | 5,390,000.00 |
| 2,570,000.00 | 5,390,000.00 |
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2.330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2.830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,390,000. During 2021, costs of $2.130,000 were incurred with estimated costs of $4,130,000 yet to be incurred. Billings of $2,630,000 were sent, and cash collected was $2,380,000. In 2022, costs incurred were $2.630,000 with remaining costs estimated to be $3,795,000.2022 billings were $2,880,000 and $2,605,000 cash was collected. The project was completed in 2023 after additional costs of $3,930,000...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2023 after additional costs of...
Please help!
On February 1, 2021, Arrow Construction Company entered into a three-vear construction contract to build a bridge for a price of $8,200,000. During 2021, costs of $2,080,000 were incurred, with estimated costs of $4,080,000 yet to be incurred. Billings of $2,596,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,596,000 with remaining costs estimated to be $3.720.000. 2022 billings were $2,846,000, and $2,555,000 cash was collected. The project was completed in 2023 after additional...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,500,000. During 2021, costs of $2,200,000 were incurred, with estimated costs of $4,200,000 yet to be incurred. Billings of $2,740,000 were sent, and cash collected was $2,450,000. In 2022, costs incurred were $2,740,000 with remaining costs estimated to be $3,900,000. 2022 billings were $2.990,000, and $2,675,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2,330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2,830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,120,000. During 2021, costs of $2,040,000 were incurred with estimated costs of $4,040,000 yet to be incurred. Billings of $2,540,000 were sent, and cash collected was $2,290,000. In 2022, costs incurred were $2,540,000 with remaining costs estimated to be $3,660,000. 2022 billings were $2,790,000 and $2,515,000 cash was collected. The project was completed in 2023 after additional costs of...
On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,120,000 were incurred, with estimated costs of $4,120,000 yet to be incurred. Billings of $2,644,000 were sent, and cash collected was $2,370,000. In 2022, costs incurred were $2,644,000 with remaining costs estimated to be $3,780,000. 2022 billings were $2,894,000, and $2,595,000 cash was collected. The project was completed in 2023 after additional costs of...