Required information
[The following information applies to the questions
displayed below.]
In 2021, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2023. Information related to the contract is
as follows:
| 2021 | 2022 | 2023 | |||||||
| Cost incurred during the year | $ | 2,604,000 | $ | 4,032,000 | $ | 1,940,400 | |||
| Estimated costs to complete as of year-end | 5,796,000 | 1,764,000 | 0 | ||||||
| Billings during the year | 2,040,000 | 4,596,000 | 3,364,000 | ||||||
| Cash collections during the year | 1,820,000 | 4,000,000 | 4,180,000 | ||||||
Westgate recognizes revenue over time according to percentage of
completion.
5. Calculate the amount of revenue and gross
profit (loss) to be recognized in each of the three years assuming
the following costs incurred and costs to complete information.
(Do not round intermediate calculations and round your
final answers to the nearest whole dollar amount. Loss amounts
should be indicated with a minus sign.)
| 2021 | 2022 | 2023 | |||||||
| Costs incurred during the year | $ | 2,604,000 | $ | 3,820,000 | $ | 3,960,000 | |||
| Estimated costs to complete as of year-end | 5,796,000 | 4,140,000 | 0 | ||||||

Solution 5:
| Computation of % of completion, revenue recognition and Gross Profit - Westgate Construction Company | |||||||||
| Year | Actual cost incurred (A) | Total cost incurred till date (B) | Total estimated Cost ( C ) | % of completion (D) (B/C) |
Contract Price (E) |
Total Revenue to be recoganized (F) (E * D) | Revenue for current period (G) | Gross Profit (H) | |
| 2021 | $2,604,000 | $2,604,000 | $8,400,000 | 31.00% | $10,000,000 | $3,100,000 | $3,100,000 | $496,000 | $3,100,000 - $2,604,000 |
| 2022 | $3,820,000 | $6,424,000 | $10,564,000 | 60.81% | $10,000,000 | $6,081,030 | $2,981,030 | -$1,060,000 | $10,000,000-$10,564,000 - $496,000 |
| 2023 | $3,960,000 | $10,384,000 | $10,384,000 | 100.00% | $10,000,000 | $10,000,000 | $3,918,970 | $180,000 | $10,000,000-$10,384,000 - $496,000 + $1,060,000 |
Required information [The following information applies to the questions displayed below.] In 2021, the Westgate Constr...
Required information
[The following information applies to the questions
displayed below.]
In 2021, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2023. Information related to the contract is
as follows:
2021
2022
2023
Cost incurred during the year
$
2,604,000
$
4,032,000
$
1,940,400
Estimated costs to complete as of year-end
5,796,000
1,764,000
0
Billings during the year
2,040,000
4,596,000
3,364,000
Cash collections during the...
Required Information [The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: 2023 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,604,000 5,796,000 2,040,000 1, 820, 000 2022 $4,032,000 1,764,000 4,596,000 4,000,000...
Required information
[The following information applies to the questions
displayed below.]
In 2021, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2023. Information related to the contract is
as follows:
2021
2022
2023
Cost incurred during the year
$
2,604,000
$
4,032,000
$
1,940,400
Estimated costs to complete as of year-end
5,796,000
1,764,000
0
Billings during the year
2,040,000
4,596,000
3,364,000
Cash collections during the...
Required information
[The following information applies to the questions
displayed below.]
In 2021, the Westgate Construction Company entered into a contract
to construct a road for Santa Clara County for $10,000,000. The
road was completed in 2023. Information related to the contract is
as follows:
2021
2022
2023
Cost incurred during the year
$
2,604,000
$
4,032,000
$
1,940,400
Estimated costs to complete as of year-end
5,796,000
1,764,000
0
Billings during the year
2,040,000
4,596,000
3,364,000
Cash collections during the...
Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered intoo a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2018 2019 2020 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year $4,032,000 1,764,000 4,596,000 4,000,000 $2,604,000 5,796,000 2,040,000 1,820,000 $1,940,400 3,364,000 4,180,000...
olued HW 1 Saved Help (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: of 5 cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,604,000 5,796,000 2,040,000 1,820,000 2023 $1,940,400 2022 $4,032,000...
Required information (The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $ 2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000...
urgent plz
olued HW 1 Saved Help (The following information applies to the questions displayed below.) In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: of 5 cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2021 $2,604,000 5,796,000 2,040,000 1,820,000 2023 $1,940,400...
! Required information [The following information applies to the questions displayed below.] In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 2018 $2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 4,596,000 4,000,000 3,364,000...
Required information (The following information applies to the questions displayed below.) In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2020. Information related to the contract is as follows: 2020 $1,940,400 Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year 2018 $2,604,000 5,796,000 2,040,000 1,820,000 2019 $4,032,000 1,764,000 4,596,000 4,000,000 3,364,000 4,180,000...