Question

in 5 percentage of completion KSON HAS THE FOLLOWING INFORMATION PERTAINING TO A LONG TERM PROJECT 10) COUNTED FOR UNDER THE need this answered ASAP please help!
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Hi,

Please note that we have passed only receivable journal entries. Due to lack of information, it is assumed that no amount has been received for the accounts receivable.

Solution 18. Noi Porticulars | 2015 Il can. Contract Price 6,20,000 I cost to date 1,40,000 o Estimated remaining cost 2,60,0Year | Accounts title Debit ($) Credit ($) 2015 140,000 Construction in Process (CIP) Accounts payable (Cost incurred for the

Add a comment
Know the answer?
Add Answer to:
need this answered ASAP please help! in 5 percentage of completion KSON HAS THE FOLLOWING INFORMATION PERTAINING TO...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • need help with solution please in 5 percentage of completion KSON HAS THE FOLLOWING INFORMATION PERTAINING TO A LON...

    need help with solution please in 5 percentage of completion KSON HAS THE FOLLOWING INFORMATION PERTAINING TO A LONG TERM PROJECT 10)COUNTED FOR UNDER THE PERCENTAGE OF COMPLETION METHOD: CONTRACT PRICE 2015 COSTS TO DATE 2015 ESTIMATED REMAINING COSTS 2016 COSTS TO DATE 2016 ESTIMATED REMAINING COSTS 2017 COSTS TO DATE PROJECT COMPLETED IN 2017 620,000 140.000 260,000 313.500 104,500 418,000 REQUIRED: PREPARE JOURNAL ENTRY 4 FOR THE FIRST TWO YEARS OF THE PROJECT (2015 AND 2016) (10 POINTS) 2015...

  • Question6. Long-term contract based on percentage of completion method (32 (4) Prepare journal entry to record...

    Question6. Long-term contract based on percentage of completion method (32 (4) Prepare journal entry to record gross profit for 2017(6 points) (5) Show at end of 2017 and 2018, what are the balance af CIP ( points) points) lim's Construction Co. has a $85,000,000 contract to build a new football stadium The project began on January 1, 2016 with an expected completion date of October 31, 2018. The following table provides infomation gathered during the construction period. Jim uses the...

  • Need help with comprehensive project (PLEASE MAKE SURE CHECK TOTALS ARE CORRECT) TIA!!! T- Accounts Adjusted...

    Need help with comprehensive project (PLEASE MAKE SURE CHECK TOTALS ARE CORRECT) TIA!!! T- Accounts Adjusted Trial Balance Income Statement Statement of Retained Earnings Balance Sheet Closing Entries Post-closing trial balance Read ALL instructions before getting started! ABC Corporation is a new company that buys and sells office supplies. Business began on January 1, 2016. Given on the first two tabs are ABC's 12/31/16 Unadjusted Trial Balance and a list of needed adjustments. 1. Make all 12 adjustments on the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT