| Jackson | 2015 | 2016 | ||||||||||
| Calculation of Gross Profit | Ans to 2a and 2b | Journal Entries | Debit $ | Credit $ | Debit $ | Credit $ | ||||||
| Particulars | 2015 | 2016 | 2017 | Costs Incurred | CIP (Work-in-progress) | 140,000 | 173,500 | |||||
| Contract Price | 620,000 | 620,000 | 620,000 | A | Cash | 140,000 | 173,500 | |||||
| Cost Incurred to date | 140,000 | 313,500 | 418,000 | B | ||||||||
| Cost Incurred during the year | 140,000 | 173,500 | 104,500 | C | ||||||||
| (Cost incurred to date of the current year less Cost incurred to date of the previous year) | Period end adjustments for Revenue | Construction Expense | 140,000 | 173,500 | ||||||||
| Estimated cost to complete | 260,000 | 104,500 | - | D | (Gross Profit entry) | CIP (Work-in-progress) | 77,000 | 74,500 | ||||
| Estimated total cost | 400,000 | 418,000 | 418,000 | E=B+D | Construction Revenue | 217,000 | 248,000 | |||||
| Percentage complete | 35.00% | 75.00% | 100.00% | F=B/E | ||||||||
| (Cost Incurred to date/Estimated total cost) | ||||||||||||
| Revenue to be recognized | 217,000 | 248,000 | 155,000 | G | ||||||||
| (Contract Price*Percentage complete)- revenue previously recognized | ||||||||||||
| Year 2015: 35% completed. Revenue recognized = 35% x $ 620,000 = $ 217,000. | ||||||||||||
| Year 2016: 75% completed. Revenue recognized = 75% x $ 620,000 – $ 217,000 (previously recognized) = $ 248,000. | ||||||||||||
| Year 2017: 100% completed. Revenue recognized = 100% x $ 620,000 – $ 217,000- $ 248,000 (previously recognized) = $ 155,000. | ||||||||||||
| Gross Profit/(Loss) | 77,000 | 74,500 | 50,500 | H=G-C | ||||||||
need help with solution please in 5 percentage of completion KSON HAS THE FOLLOWING INFORMATION PERTAINING TO A LON...
need this answered ASAP please help!
in 5 percentage of completion KSON HAS THE FOLLOWING INFORMATION PERTAINING TO A LONG TERM PROJECT 10) COUNTED FOR UNDER THE PERCENTAGE OF COMPLETION METHOD: CONTRACT PRICE 2015 COSTS TO DATE 2015 ESTIMATED REMAINING COSTS 2016 COSTS TO DATE 2016 ESTIMATED REMAINING COSTS 2017 COSTS TO DATE PROJECT COMPLETED IN 2017 620,000 140,000 260,000 313,500 104,500 418,000 REQUIRED: PREPARE JOURNAL ENTRY 4 FOR THE FIRST TWO YEARS OF THE PROJECT (2015 AND 2016) (10...