Answer #1

Earned Value of the project can be computed by the following formula

%age completion of the project X the cost of completion

In the given case the Earned value can be computed as folllows

Activity %completed Cost to complete $

Earned value $

% completed X cost to complete

Conceptual Design 100% (10,000+6000)=16,000 16,000
Graphics Design 75% (12+6+4)*1000=22,000 16,500
Copyright 5% (4+5+6)*1000=15,000 750
Samples 25% (4+2)*1000=6,000 1500
Tooling 10% (6+9+4)*1000=19,000 1900
Production 10% (2+6+14)*1000=22,000 2200
Total 38850

So, the answer is A)38,850

Add a comment
Know the answer?
Add Answer to:
ate the earned value for the project. All amounts are in Ise the data to caleulate...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Earned value calculation Based on the following Project data, answer the questions a and b. Activity...

    Earned value calculation Based on the following Project data, answer the questions a and b. Activity Duration Predecessors Task Budget A 7 days -- $16,850 B 10 days -- $22,500 C 8 days B $16,000 D 10 days A $12,790 E 7 days B $8,500 F 4 days D $10,550 At the end of Day 10, the status of the project is as follows. Activity % Complete Actual Cost A 100% $18,000 B 100% $23,000 C 0% $0 D 10%...

  • > The accompanying data are the number of wins and the earned run averages (mean number...

    > The accompanying data are the number of wins and the earned run averages (mean number of earned runs allowed per nine innings pitched) for eight baseball pitchers in a recent season. Find the equation of the regression line. Then construct a scatter plot of the data and draw the regression line. Then use the regression equation to predict the value of y for each of the given x-values, if meaningful. If the x-value is not meaningful to predict the...

  • 1) Suppose that you calculate the NPV of a project, and obtain a value of $100...

    1) Suppose that you calculate the NPV of a project, and obtain a value of $100 million dollars. After completing your analysis, you find out that the corporate tax rate will change from 40% to 30%. If nothing else changes, what is the effect of this tax change on the NPV you had calculated? Assume that your company has no debt. a) The new NPV will be lower than $100 b) The new NPV will be higher than $100 c)...

  • (discontinues all old products and switches to igadgets, accepts the new project, rejects the new project,...

    (discontinues all old products and switches to igadgets, accepts the new project, rejects the new project, delays the new project) Complete the decision tree table by calculating the net present values (NPVS) and joint probabilities, as well as products of joint probabilities and NPVS for each decision branch. Assume that the weighted average cost of capital (WACC) is 10% for all decision branches. Hint: Use either a spreadsheet program's functions or a financial calculator for this task. Round the NPVS...

  • Alpha’s balance-of-payments data for 2016 are shown below. All figures are in billions of dollars. Category...

    Alpha’s balance-of-payments data for 2016 are shown below. All figures are in billions of dollars. Category Value Goods exports $+ 50 Goods imports – 35 Service exports + 25 Service imports – 10 Net investment income – 5 Net transfers + 10 Balance on capital account 0 Foreign purchases of Alpha assets + 25 Alpha purchases of assets abroad – 60 Instructions: Input all amounts as positive values. a. What is the balance on goods?    b. What is the...

  • Use the following data for questions 33-35 General Electrie wants to find the value of a Japanese...

    Use the following data for questions 33-35 General Electrie wants to find the value of a Japanese firm. Pro-For (All Yen figures below are in millions), Revenue Costs Y 200 Y (160) Depreciation Y (10) Interest Y (10) Y 20 Y 12 Pre-Tax After Tax It is expected that these cashflows will occur in perpetuity. Further, the depreciation amount will equal the capital expenditures throughout in the future. Unlevered cost of equity i 20% (in Yens). Interest rate on debt...

  • Use the following data for questions 33-35 General Electrie wants to find the value of a Japanese...

    Use the following data for questions 33-35 General Electrie wants to find the value of a Japanese firm. Pro-For (All Yen figures below are in millions), Revenue Costs Y 200 Y (160) Depreciation Y (10) Interest Y (10) Y 20 Y 12 Pre-Tax After Tax It is expected that these cashflows will occur in perpetuity. Further, the depreciation amount will equal the capital expenditures throughout in the future. Unlevered cost of equity i 20% (in Yens). Interest rate on debt...

  • 1. Now change all of the dollar amounts in the data area of your worksheet so...

    1. Now change all of the dollar amounts in the data area of your worksheet so that it looks like this 1 Chapter 1: Applying Excel 3 Data 4 Sales $ 20,000 5 Variable costs: $10,000 $1000 800 6 7 8 9 Fixed costs: 10 Fixed selling 11 Fixed administrative Cost of goods sold Variable selling Variable administrative 2,500 $1,500 If your formulas are correct, you should get the correct answers to the following questions (a) What is the gross...

  • THE QUEEN ANNE CURIOSITY SHOP PROJECT QUESTIONS Figure 2-36 shows typical sales data for the Queen...

    THE QUEEN ANNE CURIOSITY SHOP PROJECT QUESTIONS Figure 2-36 shows typical sales data for the Queen Anne Curiosity Shop, and Figure 2.37 shows typical purchase data. A. Using these data, state assumptions about functional dependencies among the columns of data. Justify your assumptions on the basis of these sample data and also on the basis of what you know about retail sales. FIGURE 2-36 Sample Sales Data for the Queen Anne Curiosity Shop LastName FirstName Phone InvoiceDate Shire Robert 206-524-2433...

  • from 13-20 Thank you Apperciate it they choos htsP wy ate oe Prie Eamnge Ratio Page...

    from 13-20 Thank you Apperciate it they choos htsP wy ate oe Prie Eamnge Ratio Page 2 of s Comparative financial statements for ABC, a merchandising company for the calendar year ended 12/31/18 are below. The Company did not issue any new common stock during the year. A total of 800,000 shares of common stock were outstanding. The interest rate on the bond payable was 12%o, the income tax rate was 40% and the dividend per share of common stock...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT