Question

Earned value calculation Based on the following Project data, answer the questions a and b. Activity...

Earned value calculation

Based on the following Project data, answer the questions a and b.

Activity

Duration

Predecessors

Task Budget

A

7 days

--

$16,850

B

10 days

--

$22,500

C

8 days

B

$16,000

D

10 days

A

$12,790

E

7 days

B

$8,500

F

4 days

D

$10,550

At the end of Day 10, the status of the project is as follows.

Activity

% Complete

Actual Cost

A

100%

$18,000

B

100%

$23,000

C

0%

$0

D

10%

$4,000

E

0%

$0

F

0%

$0

  1. Calculate the cost and schedule variances and indexes for Tasks A, B, C, D, and E and the Cost and Schedule variance and the CPI and SPI for the entire project.

(b) As project manager, write a brief summary of the status of the project at this time.

Task

Sch'D Comp.

% Complete

EV BCWP

PV BCWS

AC ACWP

CV

SV

CPI

SPI

A

B

C

D

E

F

Project Totals

0 0
Add a comment Improve this question Transcribed image text
Answer #1

We prepare project network diagram as shown below:

As seen from above network diagram, the project can be completed in 21 days

As end of 10th day, activity A and B should have been 100% completed, activity D should be started and should have been completed (3/10) = 30%. Since, activity A takes 7 days and the rest 3 days activity D is performed.

Hence, we get 2nd table as follows:

a) We calculate cost and schedule variances and indexes for Tasks A, B, C, D, and E and the Cost and Schedule variance and the CPI and SPI for the entire project as follows:

The figures in red means negative figures. The variance and indices for entire project as shown in last row (Total).

b) The project summary is as follows:

Total project budget is $87,190. After 10 days, work equivalent to planned value of $43,187 should have been completed. However, work equivalent to $40,629 is completed but actual cost for this work spent is $45,000. The project is over-budget by $4,371 and behind schedule.by equivalent duration to $2,558. Activity A and B are on schedule but over-budget, D is behind schedule and over budget. Other activities are not planned to start and have not started.

Add a comment
Know the answer?
Add Answer to:
Earned value calculation Based on the following Project data, answer the questions a and b. Activity...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 1: The following data and table illustrate a small project: Activity A was completed on...

    Question 1: The following data and table illustrate a small project: Activity A was completed on schedule • Activity B started as planned but it is expected to take four weeks more Activity C started as planned but finished one week later • %age of completion of activity D is 60% ACWP at the end of week 10 = SR 90400 Activity Original Planned Start Time Original Planned Finish Time Wage Complete Amount Completed BCWP Amount Scheduled BCWS Amount Spent...

  • what is the % complete? what is the BCWP? what is the ACWP? what is the...

    what is the % complete? what is the BCWP? what is the ACWP? what is the BCWS? what is the CV? what is the SV? what is the CPI? what is the SPI? what is the FCV? what is the FSV? A flooring subcontractor has to install 2,600sqft of carpet for an existing building for unit cost of $2.30 per sq ft. The subcontractor was given 10 days to finish all the work. Four days after the start of the...

  • 1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 20...

    1. Consider the following project. Activity Duration (weeks)5 Immediate Predecessor(s) Cost (S) 1000 | 400 I 200 | 1200 | 500 | 700 | 1200 | 800 | 1800 | 1500 | 400 (a) Construct the activity-on-node (AoN) network for the relations among the activities in the (b) Using the activity-on-node (Ao) network developed in part (a), determine the critical path and the minimum time required to complete the project. Develop the earliest start and finish times, the latest finish...

  • Aflooring subcontractor has to install 2,600sq ft of carpet for an existing building for unit cost...

    Aflooring subcontractor has to install 2,600sq ft of carpet for an existing building for unit cost of $2.30 per sq ft. The subcontractor was given 10 days to finish all the work. Four days after the start of the work, he found out 1,500sqft of the carpet is installed and its actual cost was $3,150 to that date. Perform EV (earned value) analysis on the task above and answer Questions 1-11 Next → Question 1 5 pts What is the...

  • 3) You are in charge of the Aurora Project. Given the following project network, baseline, and...

    3) You are in charge of the Aurora Project. Given the following project network, baseline, and status information, (40 Points) B DI OA E • Develop status reports for periods 7 and complete the performance indices table. . Calculate the EAC, and VAC. Based on your data, what is the current status of the project? At completion? Rule 1 0% complete 2-50/50 3 - 0/100 ID LF SL Schedule information Total 0 1 2 PV 3 4 30 5 6...

  • Earned Value Management (EVM) Following is a cost/schedule status report (C/SSR), a document that is generated...

    Earned Value Management (EVM) Following is a cost/schedule status report (C/SSR), a document that is generated each month. It demonstrates the cost and schedule status of a project at a given moment in time. Answer the questions associated with the accompanying C/SSR after reading the appropriate sections on earned value in Managing Projects in Organizations, The New Project Management, and A Guide to the Project Management Body of Knowledge (PMBOK). Task Budget Task begun Task ended Actual Cost A 30,000...

  • Here is a practical example of EVM (Earned Value Management). Three values, BCWS, BCWP, and AC,...

    Here is a practical example of EVM (Earned Value Management). Three values, BCWS, BCWP, and AC, are all cumulative. Acronyms: BCWS (Budgeted Cost of Work Scheduled) is equal to PV (Planned Value). BCWP (Budgeted Cost of Work Performed) is equal to EV (Earned Value). AC (Actual Cost) is the actual costs that we pay for the works. Variances: Schedule variance: when BCWP - BCWS is negative, the project is behind schedule, when the value is 0, it is on schedule,...

  • At week 10 of a project below to improve distance learning platform, assume that the planned...

    At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks. ACTIVITY PRE- DECESSORS DURATION (WEEKS) BUDGET ($) ACTUAL COST ($) % COMPLETE A - 5 500 640 100 B A 3 300 400 100 C B 4 320 310 80 D B 6 600 250 60 E C,D 3 300...

  • please answer in details, thank you The Project below is currently at the end of Week...

    please answer in details, thank you The Project below is currently at the end of Week 6. Use the table below to find the PV, EV, CPI, SPI, and CSI. Use the % Complete column where applicable for these calculations. What conclusions can you make on the project given your calculated CPI, SPI, and CSI values? Activity Predecessors Duration (weeks) Budget, $ $350 $550 $250 $400 $450 $600 Actual Cost, $ $400 $550 $200 $300 $150 А % Complete 100%...

  • PLEASE SHOW ALL CALCULATIONS. PLEASE DRAW A NETWORK DIAGRAM AS WELL. The following project is at...

    PLEASE SHOW ALL CALCULATIONS. PLEASE DRAW A NETWORK DIAGRAM AS WELL. The following project is at the end of its 6th week. Find the cost and schedule variances. Also find the CPI and SPI. Then find the critical ratio of the project using earned value calculations. Finally, calculate the EAC for the project by at least two different methods. Activity Predecessor Duration (wks) Budget      ($) Actual Cost ($) %Complete a - 2 600 400 100 b - 3 150 180...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT