Here is a practical example of EVM (Earned Value Management). Three values, BCWS, BCWP, and AC, are all cumulative.
Acronyms:
BCWS (Budgeted Cost of Work Scheduled) is equal to PV (Planned Value).
BCWP (Budgeted Cost of Work Performed) is equal to EV (Earned Value).
AC (Actual Cost) is the actual costs that we pay for the works.
Variances:
Schedule variance: when BCWP - BCWS is negative, the project is behind schedule, when the value is 0, it is on schedule, and when the value is positive, it is ahead of schedule.
Cost variance: when AC - BCWP is negative, the project is under budget, when the value is 0, it is on budget, and when the value is positive, it is over budget.
Fill out the blanks.
The painter agrees to paint 1 wall per day for $100. Let's assume a large 8 sided room. We predict 8 days for the job and $800. Each day, the painter gets paid $100 (he is paid by the hour and works 10 hours a day to keep it simple). If all goes according to plan, the values of BCWS, AC and BCWP will each increase by $100 every day.
Day1: Assume the painter is very good and gets two walls painted
in half a day and he leaves after 5 hours. At the end of
Day1:
BCWS (or PV)=$100, AC=$( ), BCWP (or EV)=$( ) (the value of the two
painted walls).
We are ( ) schedule and ( ) budget.
*** AC (Actual Costs) is $100 because we pay $100 if the painter works 10 hours regardless the amount of work.
*** BCWP (or Earned Value) is $200 because he finished 2 walls ($100 each).
*** The project is ahead of schedule because EV is great than PV.
*** The project is under budget because AC is lower than EV.
*** Do this for the following days. Remember all three values, AC, EV, PV, are cumulative.
Day2: The going gets tough and he does not complete any walls,
but works the whole day. At the end of Day2:
BCWS=$( ), AC=$( ), BCWP=$200.
We are ( ) schedule and ( ) budget.
Day3: The going is still tough, he works like mad but no more
walls are completed. At the end of Day3:
BCWS=$( ), AC=$( ), BCWP=$( ).
We are ( ) schedule and ( ) budget.
Day 4: He brings a buddy at the same rate. They complete the one
wall (so we have three walls complete). At the end of Day4:
BCWS=$( ), AC=$450, BWCP=$( ).
We are ( ) schedule and ( ) budget.
Day 5 - They all play golf. At the end of Day5:
BCWS=$( ), AC=$( ), BCWP=$300.
We are ( ) schedule and ( ) budget.
Day 6 - Three guys work and complete 4 more walls. At the end of
Day6:
BCWS=$600, AC=$750, BCWP=$( ).
We are ( ) schedule but ( ) budget.
Day 2 -
BCWS = As two walls would have been completed by now, 2*100 = 200
AC = The payment for the two days work would be done, 2*100 = 200
BCWP=$200
We on schedule and on budget on day 2
Day 3 -
BCWS = As three walls would have been completed by now, 3*100 = 300
AC = The payment for the three days work would be done, 3*100 = 300
BCWP= He has completed only two walls till now, 2*100 = 200
As BCWP - BCWS is negative, the project is behind schedule and as AC - BCWP is positive, we are over budget
Day 4 -
BCWS = As four walls would have been completed by now, 4*100 = 400
AC = 450
BCWP= He has completed three walls till now, 3*100 = 300
As BCWP - BCWS is negative, the project is behind schedule and as AC - BCWP is positive, we are over budget
Day 5 -
BCWS = As five walls would have been completed by now, 5*100 = 500
AC = As they are on leave, no payment would be made = 450
BCWP= He has completed three walls till now, 3*100 = 300
As BCWP - BCWS is negative, the project is behind schedule and as AC - BCWP is positive, we are over budget
Day 6 -
BCWS = As six walls would have been completed by now, 6*100 = 600
AC = 750
BCWP= He has completed 3+4 = 7 walls till now, 7*100 = 700
As BCWP - BCWS is positive, the project is ahead of schedule and as AC - BCWP is positive, we are over budget
Please Like & Provide your reviews in comments. :-)
Here is a practical example of EVM (Earned Value Management). Three values, BCWS, BCWP, and AC,...
Earned Value 1. Complete the calculations Case BCWS or PV ACWP or AC BCWP or EV CV SV CPI SPI 1 800 800 800 2 800 600 400 3 800 400 600 4 800 600 600 5 800 800 600 6 800 800 1000
Earned value calculation Based on the following Project data, answer the questions a and b. Activity Duration Predecessors Task Budget A 7 days -- $16,850 B 10 days -- $22,500 C 8 days B $16,000 D 10 days A $12,790 E 7 days B $8,500 F 4 days D $10,550 At the end of Day 10, the status of the project is as follows. Activity % Complete Actual Cost A 100% $18,000 B 100% $23,000 C 0% $0 D 10%...
2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...
You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...
QUESTION 1 3.8 points Save Ans The cost management plan has all of the following characteristics EXCEPT It may specify variance thresholds for monitoring cost performance to indicate an agreed-upon amount of variation to be allowed before some action needs to be taken. It describes how the project costs will be planned, structured, and controlled. It is based on project cost estimates and is separate from the project management plan. It may specify the level of precision, which is the...
You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. 2. Explain your assessment on how the project is doing: Is it ahead or behind schedule? Is it under or over budget? Use calculated variances and indexes to support your argument. [50- 100-word response. 3. Use the CPI to calculate the estimate at completion (EAC) for this project....
You are given the following information for a one-year project: Planned Value (PV) = $23,000, Earned Value (EV) = $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Explain your assessment on how the project is doing: Is it ahead or behind schedule? Is it Page 6 of 8 IS8100-01 Fa2019 under or over budget? Use all of the calculated variances and indexes from above to support your argument. [50-100-word response.]
Your organization is preparing a new marketing campaign. The test marketing project plan and the information reported at the end of week 6 are presented in the table below: Duration (weeks) Activity Predecessors Budget, $ Actual Cost, $ % Complete 400 200 a: Build items b: Supply stores c: Create ad program d: Schedule ads e: Check sale results 180 300 Solo bc 200 Ignore the last column "% complete" and use the rule 50-50 percent completion rule for the...
I need help with the attached assignment. I attached the
question and completed assigment. I just need help with answering
one more question which is which is:
Discuss a strategy that you would use to communicate the status
of the project to stakeholders?
Project Monitoring and Control Assignment Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project Case in Larson and Gray. Respond to Questions 1 and 2 of the case. Use Microsoft...
Select two of the discussion questions and analyze the case study using project management principles. Apply your knowledge of project management to the facts presented in the case study to describe how you would proceed. We only need to answer one of the questions. A thorough answer will probably require 300 to 500 words for each question. Feel free to use text bullets, tables, or graphics to summarize your points. Questions Q1: Make or Buy decision – Describe the make...