Following is a cost/schedule status report (C/SSR), a document that is generated each month. It demonstrates the cost and schedule status of a project at a given moment in time. Answer the questions associated with the accompanying C/SSR after reading the appropriate sections on earned value in Managing Projects in Organizations, The New Project Management, and A Guide to the Project Management Body of Knowledge (PMBOK).
|
Task |
Budget |
Task begun |
Task ended |
Actual Cost |
|
A |
30,000 |
√ |
√ |
30,000 |
|
B |
40,000 |
√ |
√ |
43,000 |
|
C |
20,000 |
√ |
√ |
22,000 |
|
D |
30,000 |
√ |
18,000 |
|
|
E |
30,000 |
|||
|
F |
40,000 |
√ |
44000 |
|
|
G |
20,000 |
√ |
√ |
21,000 |
|
Total |
210,000 |
178,000 |
This C/SSR shows the cost and schedule status of our project as of the end of last month. The numbers in the “Budget” column represent how much money was budgeted to be spent on each of the tasks at the end of reporting period. Applying earned value management (EVM) principles, answer the following six questions:
AC = actual cost,EV = Earned value,PV = Planned value
a)
SV = EV-PV
EV = (4/7)*210000 = 120000
PV = 210000
SV = EV-PV = 120000-210000 = -90000
b)
CV = EV-AC = 120000-178000 = -58000
c)
CPI = EV/AC = 120000/178000 = 0.674157303
d)
SPI = EV/PV = 120000/210000 = 0.571428571
e)
EAC = budget at completion + AC -EV
=600000 + 178000 – 120000 = 658000
f)
CPI < 1 suggests that project is over budget which means project may run out of money before completion. SPI < 1 suggests the project is behind schedule
CPI < 1
Earned Value Management (EVM) Following is a cost/schedule status report (C/SSR), a document that is generated...
Remaining Time: 57 minutes, 05 seconds Less than half of the team Question Comeletion Status Question 10 Save A You have a project to be completed in 12 months. The budget for the project is 100.000 USD. Six months have passed, and 60.000 USD has been spent. On closer review, you find that only 40% of the work has become to date. Based on these figures, answer the following questions to receive full grade you must show your work 1....
A project has an Earned Value (EV) = $5, Actual Cost (AC) = $7 and both Cost Performance Index (CPI) and Schedule Performance Index (SPI) equal 0.90. The original project budget is $10. Assuming the remaining work will be impacted by the current cost performance and current schedule performance, what is the estimate at completion (EAC) of the project? $12.96 $13.17 $14.75 $15 What is your reasoning? ________________________________________________________
Use the following project status information to calculate each
of the requested EVM numbers below. The project status is reported
at the end of week 13.
5. Cost performance index:
6. Schedule performance index
7. Budget at completion
8. Estimate to complete
9. Estimate at completion
Task Budget Cost Budget Duration Status as of Week 13 A $5,000 2 weeks 100 percent com- plete, $5,000 B $8,500 3 weeks 100 percent com- plete, $9,000 с $15,000 4 weeks 75 percent...
to chapter 1. Given the following information for a one-year project, answer the following questions. Recall that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a. What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? b. How is the project doing? Is it ahead...
2. You are 4.5 months into a 6-month, $12,000 project with a planned linear spend rate. You have an earned value of $8,500 and you have spent $10,000. What is your EAC? (2 points) 3. The earned value on your project is $15,000, the planned value is $20,000, and the actual cost is $18,000. What is your current schedule variance (in $)? (1 point) 5. You are working on a large project and have determined that your cost variance is...
You are given the following information for a one-year project: Planned Value (PV) - $23,000, Earned Value (EV) - $20,000, Actual Cost (AC) = $20,000, and Budget at Completion (BAC) = $120,000. Answer each of the questions below to complete your assignment. Use the same numbers as the assignment when you give your answer, I only grade answers that correspond the assignment questions. 1. For this one-year project calculate: a. cost variance, b. schedule variance, C. cost performance index (CPI),...
Which of the following is correct about who uses Earned Value Management (EVM) data for analysis in the Program Management Office (PMO)? Government technical personnel, such as engineers, logisticians and test personnel, rely on EVM analysts and schedulers to understand cost and schedule performance for their areas of responsibility. Cost estimators do not need to use EVM data since they are only interested in building the life cycle cost estimates for the entire system. Only specialized EVM analysts and schedulers...
Using the below information answer only part e bolded. Given the following information for a one-year project, answer the following questions. Note that PV is the planned value, EV is the earned value, AC is the actual cost, and BAC is the budget at completion. PV = $22,000 EV = $20,000 AC = $25,000 BAC = $120,000 a.What is the cost variance, schedule variance, cost performance index (CPI), and schedule performance index (SPI) for the project? (CV) is -$5,000 (SV)...
Here is a practical example of EVM (Earned Value Management). Three values, BCWS, BCWP, and AC, are all cumulative. Acronyms: BCWS (Budgeted Cost of Work Scheduled) is equal to PV (Planned Value). BCWP (Budgeted Cost of Work Performed) is equal to EV (Earned Value). AC (Actual Cost) is the actual costs that we pay for the works. Variances: Schedule variance: when BCWP - BCWS is negative, the project is behind schedule, when the value is 0, it is on schedule,...
Complete the following exercises and submit them in a word document (10 points). Project ABC Scope = 10 chairs @ $10.00 = $100.00 PV = Timeframe = 10 days At the End of the 5th day 4 chairs were EV = Completed at a cost of $11.00 each CPLE SV = SPIE To install a 10,000 feet fence at a cost of $10.00/per foot. It is estimated that 500 feet of fence can be installed per week for a total...