How do you put this into excel
QM? which method do you select?
| From | To | Path | Distance |
| 1 | 2 | 12 | 100 |
| 1 | 3 | 13 | 200 |
| 2 | 3 | 23 | 100 |
| 2 | 4 | 24 | 150 |
| 2 | 5 | 25 | 200 |
| 3 | 4 | 34 | 150 |
| 3 | 5 | 35 | 300 |
| 4 | 5 | 45 | 250 |
| 4 | 6 | 46 | 200 |
| 5 | 6 | 56 | 100 |
We create a Allocation matrix , Distance Matrix , Total Distance matrix like this

Total Distance matrix is obtained by multiplying Distance matrix with allocation.
Then we will put the following objective function & constraints in the solver :
Objective : To minimize the distance , i.e Total Distance should be minimum
Decision Variable : We change the allocation matrix
Constraints :
1. The Allocation matrix should be binary, i.e 0 or 1.
2. The sum of allocations in one row should be maximum of 1.
3. The sum of allocations in one column should be maximum of 1.
4. The sum of Allocated Distances should be greater than equal to 100 in each row.
The parameters used in the solver are shown below :

Hope this helps
How do you put this into excel QM? which method do you select? Given the following...
Given the following distances between destination nodes, what is the minimum distance that connects all the nodes? From Node To Node Distance 1 1 2 150 2 1 3 200 3 2 3 100 4 2 4 200 5 2 5 50 6 3 4 350 7 3 5 300 8 4 6 100 9 5 6 100 NOTE: You have to show your work. Do not use EXCEL QM Identify decision variables Formulate the LP problem by showing objective...
Show work on excel QM to do this thanks
Consider the bill of material for Product "T'h: To make one unit of"T, it needs one unit of"x" and two units of"M. To make one unit of K, it requires 4 units (Corrected) of ". The gross requirements for J are 200 units in week 6 and 250 units in week 8. Use the data given in the following table, develop the MRP tables for each item for an 8-week planning...
Using QM for Excel, construct a Gantt chart for the following set of activities and indicate the project completion time and slack for each activity. ACTIVITY ACTIVITY PREDECESSOR TIME (WEEKS) 1 - 3 2 - 7 3 1 2 4 2 5 5 3 6 6 4 1 7 5 4
9.1) Given the pipeline fluid flows indicated below, determine the maximum flow from Node 1 to Node 5 Fluid From Node Node Flow To 1 1 2 300 2 2 1 1 3 3 1 150 200 200 100 5 4 6 4 1 7 1 5 2 1 100 200 200 250 300 3300 250 4 10 4 2 11 3 4 12 13 14 4 3 5 3 15 4 5 100 16 4 0 mint 寸m |寸|...
no
you dont. let someone else answer it.
1. Given the following horizontal curve and spiral data: Total tangent deflection angle (A) = 30° Rt. D= 5° Design Speed = 50 mph Two lane road in Southern Climate PI Station @ 64+20.00 Find and e from Table 13.8 or 13.9 (see handouts) Compute: = R P= Compute the stations of: T.S. = S.C. C.S. = S.T. = Compute the Long Tangent and the Short Tangent Table 13.9 SPIRAL CURVE LENGTHS...
I
am completely lost in how to do this on excel.
4. Consider the following reaction: NO (9) ► NO(g) + O(g) The concentration of NO, was monitored at a fixed temperature as a function of time during the decomposition reaction and the data is tabulated below 2nd Order Time (s) 0 INO.1 (M) 0.0100 .00887 0.00797 0.00723 0.00662 50 100 150 200 INO.1 (M) 0.00329 0.00316 0.00303 0.00292 0.00282 Time isi INO.1MI Time (s) INO.1 (M) 250 000611 5...
please do step by step how you got the answer
Figure 3-14 Arturo's Production Possibilities Frontier Dina's Production Possibilities Frontier durritos durritos 500 500 450 450 400 400 350 350 300 300 250 250 200 + 200 150 150 100 100 50 50 50 100 150 200 250 300 350 400 tacos 50 100 150 200 250 300 350 400 tacos ab Refer to Figure 3-14. Suppose Arturo is willing to trade 6 burritos to Dina for each 10 tacos...
Given the following MRP matrix for Item Z, prepare a material requirements plan for component P. Lot-for-lot ordering will be used for component P. ITEM: Z Lot Size: Q=100 LT: 1 Project on Hand : 200 Period 1 2 3 4 5 6 7 Gross Requirements 600 300 270 200 Schedule Receipts 250 150 Project on Hand 200 Net Requirements Planned Order Receipts Planned Order Releases ps fr unit 1 is 100 and i do not have the tree
1. Given the following horizontal curve and spiral data: Total tangent deflection angle (A) = 30° Rt. D = 5° Design Speed = 50 mph Two lane road in Southern Climate PI Station @ 64+20.00 Find Land e from Table 13.8 or 13.9 (see handouts) Compute: As = Ac Y Xs es = R= P= TS Compute the stations of: T.S. = S.C. = C.S. = S.T. = Compute the Long Tangent and the Short Tangent Spiral Curve Equations Spiral...
Please assist with pipe analysis. Please clearly show
your formulas. Thank you in advance
Please neatly set your calculations/tables and show all necessary steps. Thanks in advance. Use the Hardy-Cross Method to analyse the system. Determine the flows in all pipes and residual heads at the various nodes for the node draw-offs given in Figure 1. Use the Hazen- Williams friction formula and assume a friction factor C of 110 for all pipes. The minimum pipe size is 100 mm...