Question

On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a priceCompute the amount of revenue and gross profit or loss to be recognized in 2018, 2019, and 2020 using ti completion method? (

it says it's incomplete, please help

0 0
Add a comment Improve this question Transcribed image text
Answer #1
On Feb 2018, Arrow construction company entered into a 3 year construction contract to build a bridge for $ 8600000
During 2018, the cost of $2200000 were incurred and billing of $2700000 was sent and cash collected was$2450000.
Year Numerator / Denominator % of complete to date
2018 2200000 8600000 25.58
2019 7100000 8600000 82.56
2020 11100000 8600000 100.00 (but limited to 100%)
Numerator
2018 Total Expenses incurred on the project 2200000
2019 Total Expenses incurred on the project 4900000
2020 Total Expenses incurred on the project 4000000
Gross Profit to be calculated = Percentage of work completed X Total Project value
Percentage of work completed X Total Project value Total Gross Profit
2018 25.58 X 8600000 2200000
2019 82.56 X 8600000 7100000
2020 100.00 X 8600000 8600000
2018
To date Recognized in prior years Recognized in 2018
Contruction Revenue 2200000 0 2200000
Contruction Expense 2200000 0 2200000
Gross Profit 0 0 0
2019
To date Recognized in prior years Recognized in 2019
Contruction Revenue 7100000 2200000 4900000
Contruction Expense 7100000 2200000 4900000
Gross Profit 0 0 0
2020
To date Recognized in prior years Recognized in 2020
Contruction Revenue 8600000 7100000 1500000
Contruction Expense 11100000 7100000 4000000
Gross Profit(Loss) -2500000 0 -2500000
2a. Journal entry for 2018
In the books of Arroe Contruction company
for the year ended 31, December 2018
Date Particulars Amount$ Amount$
31.12.2018 Various Accounts A/c   Dr 2200000
        To Accounts Payable 2200000
(being cost recorded)
Accounts ReceivablesA/c Dr 2700000
   To Billing 2700000
( being billed amount recorded )
Cash A/c                   Dr 2450000
To Accounts Receivables 2450000
( being cash collected)
2b. Journal entry for 2019
In the books of Arroe Contruction company
for the year ended 31, December 2019
Date Particulars Amount$ Amount$
31.12.2019 Various Accounts A/c   Dr 7100000
        To Accounts Payable 7100000
(being cost recorded)
Accounts ReceivablesA/c Dr 2950000
   To Billing 2950000
( being billed amount recorded )
Cash A/c                   Dr 2675000
To Accounts Receivables 2675000
( being cash collected)
3a. Balance Sheet for the year ended 31 December 2018
Particulars Amount$ Amount$
Liabilities
Accounts Payable 2200000
Total Liabilities 2200000
Assets
Current Assets
Accounts Receivables 250000
Cash 2450000
Total Assets 2700000
3b. Balance Sheet for the year ended 31 December 2019
Particulars Amount$ Amount$
Liabilities
Accounts Payable 7100000
Total Liabilities 7100000
Assets
Current Assets
Accounts Receivables 275000
Cash 2675000
Total Assets 2950000
Contract Cost 8600000
Year Cost Cumulative cost Cumulative % completion Year on Year % Cumulative revenue YR on Yr revenue
2018 2200000 2200000 25.58 25.58 2200000 2200000
2019 4900000 7100000 82.56 56.98 7100000 4900000
2020 4000000 11100000 100.00 17.44 8600000 1500000
11100000 100.00 8600000
Add a comment
Know the answer?
Add Answer to:
it says it's incomplete, please help On February 1, 2018, Arrow Construction Company entered into a...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected. The project was completed in 2020 after additional costs of...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...

  • I am lost. This all that I have so far...... On February 1, 2018, Arrow Construction...

    I am lost. This all that I have so far...... On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,060,000. During 2018, costs of $2,020,000 were incurred with estimated costs of $4,020,000 yet to be incurred. Billings of $2,520,000 were sent, and cash collected was $2,270,000. In 2019, costs incurred were $2,520,000 with remaining costs estimated to be $3,630,000. 2019 billings were $2,770,000 and $2,495,000 cash was collected....

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2021, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2022, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2022 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2023 after additional costs of...

  • On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,240,000. During 2021, costs of $2,080,000 were incurred with estimated costs of $4,080,000 yet to be incurred. Billings of $2,580,000 were sent, and cash collected was $2.330,000. In 2022, costs incurred were $2,580,000 with remaining costs estimated to be $3,720,000. 2022 billings were $2.830,000 and $2,555,000 cash was collected. The project was completed in 2023 after additional costs of...

  • 3. On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2018, costs of $2,100,000 were incurred...

    3. On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,300,000. During 2018, costs of $2,100,000 were incurred with estimated costs of $4,100,000 yet to be incurred. Billings of $2,600,000 were sent, and cash collected was $2,350,000. In 2019, costs incurred were $2,600,000 with remaining costs estimated to be $3,750,000. 2019 billings were $2,850,000 and $2,575,000 cash was collected. The project was completed in 2020 after additional costs...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,450,000. During 2018, costs of $2,180,000 were incurred, with estimated costs of $4,180,000 yet to be incurred. Billings of $2,716,000 were sent, and cash collected was $2,430,000. In 2019, costs incurred were $2,716,000 with remaining costs estimated to be $3,870,000. 2019 billings were $2,966,000, and $2,655,000 cash was collected. The project was completed in 2020 after additional costs of...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2018, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of...

  • please complete it in this format. On February 1, 2021, Arrow Construction Company entered into a...

    please complete it in this format. On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,030,000. During 2021, costs of $2,010,000 were incurred with estimated costs of $4,010,000 yet to be incurred. Billings of $2,510,000 were sent, and cash collected was $2,260,000. In 2022, costs incurred were $2,510,000 with remaining costs estimated to be $3,615,000. 2022 billings were $2,760,000 and $2,485,000 cash was collected. The project was completed...

  • On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a...

    On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,125,000. During 2018, costs of $2,050,000 were incurred, with estimated costs of $4,050,000 yet to be incurred. Billings of $2,560,000 were sent, and cash collected was $2,300,000. In 2019, costs incurred were $2,560,000 with remaining costs estimated to be $3,675,000. 2019 billings were $2,810,000, and $2,525,000 cash was collected. The project was completed in 2020 after additional costs of...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT