The following bar chart shows the activities to complete a project in 6 months (each cell represents 1 month). The total project cost is $700.
After 2 months, Activities A, B, half of C, and half of D are completed, for a cost of $200. For this point in time (2 months after the start date), what are the values of the budgeted cost of work performed, the budgeted cost of work scheduled, and the actual cost of work performed?