Note: In case of any clarification, please do comment. Thank you.
A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000...
A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 6,700 4,690 6,300 6,700 CON 9,200 7,360 2,600 4,800 20,700 3,840 15,890 15,600 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($52,190 + 2,000) $15,600 20,700 15,890 $52,190 $26.10 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...
Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg, bal Jan 6,300 6,700 4,690 6,700 9,200 7,360 2,600 3,840 4,800 20,700 15,600 15,890 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($52,190 + 2,000) $15,600 20,700 15,890 $52, 190 $26.10 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work in Process Inventory on January 1 if this was the...
A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 1 5,500 6,700 4,690 6,700 8,800 7,040 2,900 4,000 19,500 3,200 14,930 15,100 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($49,530 + 2,000) $15,100 19,500 14,930 $49,530 $24.77 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...
A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Direct Materials Direct Labor Manufacturing Overhead Date Beg. bal. Jan. 1 5,100 7,000 4.900 7,000 8,000 6,000 2,800 5,000 3,750 14,900 20,000 14,650 Cost of completed job: Direct materials $14,900 Direct labor 20,000 Manufacturing overhead 14,650 Total cost $49,550 Unit cost ($49,550 = 2,000) $24.78 (a) On the basis of the foregoing data, answer the following questions. (a) On the basis of the...
A job order cost sheet for Ryan Company is shown
below.
Job No. 92
For 2,000 Units
Date
Direct
Materials
Direct
Labor
Manufacturing
Overhead
Beg. bal. Jan. 1
6,400
6,560
4,592
8
6,560
12
10,000
7,500
25
2,800
27
4,000
3,000
15,760
20,560
15,092
Cost of completed job:
Direct materials
$15,760
Direct labor
20,560
Manufacturing overhead
15,092
Total cost
$51,412
Unit cost ($51,412 ÷ 2,000)
$25.71
(a) On the basis of the foregoing data, answer the following
questions.
(1) What...
A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 6,500 6,000 4,200 6,000 8,000 6,800 25 3,000 4,000 18,000 15,500 3,400 14,400 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost (547,900 = 2.000) $15,500 18,000 14,400 $47.900 $23.95 (a) on the basis of the foregoing data, answer the following questions. (1) What was the balance...
A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Materials Labor Direct Manufacturing Date Overhead Beg. bal. 5,9007,400 5,180 Jan. 1 7,400 12 25 27 6,800 5,100 2,400 4,400 15,700 18,600 3,300 13,580 Cost of completed job: Direct materials 15,700 18,600 13,580 $47,880 $23.94 Direct labor Manufacturing overhead Total cost Unit cost ($47,880 2,000) (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance...
A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Manufacturing Direct Materials Labor Date Overhead Beg. bal 5,9007,400 5,180 Jan. 1 7,400 12 25 27 6,800 5,100 2,400 4,400 15,700 18,600 3,300 13,580 Cost of completed job: Direct materials 15,700 18,600 13,580 $47,880 $23.94 Direct labor Total cost Unit cost ($47,880 2,000) (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work...
Exercise 2-3 A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing | Overhead Date Beg. bal. Jan. 1 6,700 7,000 4,900 7,000 10,000 7,500 2,800 4,000 21,000 3,000 15,400 16,500 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($52,900 + 2,000) $16,500 21,000 15,400 $52,900 $26.45 (a) On the basis of the foregoing data, answer the following questions. (1) What was...
A job order cost sheet for Ryan Company is shown below. (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work in Process Inventory on January 1 if this was the only unfinished job? Balance in Work in Process Inventory on January 1 _______ (2) If manufacturing overhead is applied on the basis of direct labor cost, what overhead rate was used in each year? (b) Prepare summary entries at January 31 to record the current...