A job order cost sheet for Ryan Company is shown
below.
|
Job No. 92 |
For 2,000 Units |
|||||
|
|
Direct |
Direct |
Manufacturing |
|||
| Beg. bal. Jan. 1 | 6,400 | 6,560 | 4,592 | |||
| 8 | 6,560 | |||||
| 12 | 10,000 | 7,500 | ||||
| 25 | 2,800 | |||||
| 27 | 4,000 | 3,000 | ||||
| 15,760 | 20,560 | 15,092 |
| Cost of completed job: | ||
| Direct materials | $15,760 | |
| Direct labor | 20,560 | |
| Manufacturing overhead | 15,092 | |
| Total cost | $51,412 | |
| Unit cost ($51,412 ÷ 2,000) | $25.71 |
(a) On the basis of the foregoing data, answer the following
questions.
(1) What was the balance in Work in Process Inventory on January 1
if this was the only unfinished job?
| Balance in Work in Process Inventory on January 1 | $
|
(2) If manufacturing overhead is applied on the basis of direct
labor cost, what overhead rate was used in each year?
(Round answers to 0 decimal places, e.g.
55%.)
| Last year | Current year | ||||
| Overhead rate |
|
% |
|
% What is the current year %? |
(b) Prepare summary entries at January 31 to record the
current year’s transactions pertaining to Job No. 92.
(Credit account titles are automatically indented when amount
is entered. Do not indent manually.)
Cost accounting is an accounting process in which the costs involved in the process, project are recorded and analyzed. The purpose of cost accounting is to allocate costs to different products and thereby determine the selling price per unit.
Work in Progress: Work in progress in cost accounting implies a value of goods whose production has not yet been completed. Work in progress is the stage of production between raw material and the finished goods. Work in progress includes the cost of material, labor and overhead expenses applied at a different stage of production.
Direct materials: These are the materials which are used in the Production process which constitutes an integral portion of the final product, the cost of which is identifiable and traceable directly to it. The cost of direct material can be directly chargeable to the final product as compared to the indirect material.
Direct labor: Workers or employees directly involved in the manufacture of goods and services are called direct labor. Direct labor can be directly traceable to a specific product or cost center.
Predetermined overhead rate: It is that rate based on which the overhead expenses are absorbed over the period. It is generally a blanket rate which is further multiplied with the most important factor of production which can be labor hours or machine hours to calculate the overhead expense for the year.
(a) (1)
Calculate opening WIP using the equation as follows:
Hence, opening WIP on January 1 is $17,552.
[Part a1]
Part a1
Part a1
(a) (2)
Compute the manufacturing overhead rate using MS Excel as follows:

Hence, the overhead rate as a percentage of labor cost in the previous year is 70% and 75% in the current year.
Working Notes:
Compute the total manufacturing overheads in the current year using the equation as follows:
Hence, the manufacturing overheads in the current year are $10,500.
Compute the total direct labor in the current year using the equation as follows:
Hence, the direct labor expenses incurred in the current year are $14,000.
Compute the overhead rate for the previous year using the equation as follows:
Hence, the overhead rate in the previous year is 70%.
Compute the overhead rate for the current year using the equation as follows:
Hence, the overhead rate in the current year is 75%.
[Part a2]
Part a2
Part a2
(b)
Pass a journal entry to record transfer of direct material expense to WIP inventory using MS Excel as follows:

Working Note:
Compute the direct materials inventory using the equation as follows:
Hence, the direct materials purchased in January are $9,360.
[Part b]
Part b
Part b
Pass a journal entry to record transfer of wages payable to WIP inventory using MS Excel as follows:

Working Note:
Compute the direct labor wages payable using the equation as follows:
Hence, the direct materials purchased in January are $14,000.
Pass a journal entry to record transfer of manufacturing overheads to WIP Inventory using MS Excel as follows:

Working Note:
Compute the total manufacturing overheads using the equation as follows:
Hence, the manufacturing overheads expenditure in January is $10,500.
Pass a journal entry to record the transfer of finished goods from WIP inventory to finished goods inventory using MS Excel as follows:

Working Note:
Compute the total work in progress inventory using the equation as follows:
Ans: Part a1
Opening WIP on January 1 is $17,552
Part a2The overhead rate as a percentage of labor cost in the previous year is 70% and 75% in the current year.
Part b



A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000...
A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Direct Materials Direct Labor Manufacturing Overhead Date Beg. bal. Jan. 1 5,100 7,000 4.900 7,000 8,000 6,000 2,800 5,000 3,750 14,900 20,000 14,650 Cost of completed job: Direct materials $14,900 Direct labor 20,000 Manufacturing overhead 14,650 Total cost $49,550 Unit cost ($49,550 = 2,000) $24.78 (a) On the basis of the foregoing data, answer the following questions. (a) On the basis of the...
A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Manufacturing Direct Materials Labor Date Overhead Beg. bal 6,300 6,700 4,690 Jan. 1 8 12 25 27 6,700 9,200 7,360 2,600 4,800 3,840 15,60020,700 15,890 Cost of completed job Direct materials $15,600 20,700 15,890 $52,190 $26.10 Direct labor Manufacturing overhead Total cost Unit cost ($52,190 2,000) (a) On the basis of the foregoing data, answer the following questions (1) What was the...
A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Manufacturing Direct Materials Labor Date Overhead Beg. bal 5,9007,400 5,180 Jan. 1 7,400 12 25 27 6,800 5,100 2,400 4,400 15,700 18,600 3,300 13,580 Cost of completed job: Direct materials 15,700 18,600 13,580 $47,880 $23.94 Direct labor Total cost Unit cost ($47,880 2,000) (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work...
A job order cost sheet for Ryan Company is shown below Job No. 92 For 2,000 Units Direct Materials Labor Direct Manufacturing Date Overhead Beg. bal. 5,9007,400 5,180 Jan. 1 7,400 12 25 27 6,800 5,100 2,400 4,400 15,700 18,600 3,300 13,580 Cost of completed job: Direct materials 15,700 18,600 13,580 $47,880 $23.94 Direct labor Manufacturing overhead Total cost Unit cost ($47,880 2,000) (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance...
A job order cost sheet for Ryan Company is shown below. Job No. 92 For 2,000 Units Date Direct Materials Direct Labor Manufacturing Overhead Beg. bal. Jan. 1 6,500 6,000 4,200 6,000 8,000 6,800 25 3,000 4,000 18,000 15,500 3,400 14,400 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost (547,900 = 2.000) $15,500 18,000 14,400 $47.900 $23.95 (a) on the basis of the foregoing data, answer the following questions. (1) What was the balance...
Exercise 2-3
A job order cost sheet for Ryan Company is shown below.
Job No. 92
For 2,000 Units
Date
Direct
Materials
Direct
Labor
Manufacturing
Overhead
Beg. bal. Jan. 1
5,200
6,000
4,200
8
6,000
12
10,000
7,500
25
2,700
27
4,000
3,000
13,900
20,000
14,700
Cost of completed job:
Direct materials
$13,900
Direct labor
20,000
Manufacturing overhead
14,700
Total cost
$48,600
Unit cost ($48,600 ÷ 2,000)
$24.30
(a) On the basis of the foregoing data, answer the following
questions....
A Job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 1 5,500 6,700 4,690 6,700 8,800 7,040 2,900 4,000 19,500 3,200 14,930 15,100 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($49,530 + 2,000) $15,100 19,500 14,930 $49,530 $24.77 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...
A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Materials Direct Labor For 2,000 Units Manufacturing Overhead Date Beg. bal. Jan. 6,700 4,690 6,300 6,700 CON 9,200 7,360 2,600 4,800 20,700 3,840 15,890 15,600 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($52,190 + 2,000) $15,600 20,700 15,890 $52,190 $26.10 (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in...
A job order cost sheet for Ryan Company is shown below. (a) On the basis of the foregoing data, answer the following questions. (1) What was the balance in Work in Process Inventory on January 1 if this was the only unfinished job? Balance in Work in Process Inventory on January 1 _______ (2) If manufacturing overhead is applied on the basis of direct labor cost, what overhead rate was used in each year? (b) Prepare summary entries at January 31 to record the current...
A job order cost sheet for Ryan Company is shown below. Job No. 92 Direct Labor Direct Materials 5,200 7,000 For 2,000 Units Manufacturing Overhead 4,900 7,000 Date Beg. bal. Jan. 1 8 12 25 27 10,000 8,000 2,900 5,000 4,000 16,900 15,100 22,000 Cost of completed job: Direct materials Direct labor Manufacturing overhead Total cost Unit cost ($54,000 = 2,000) $15,100 22,000 16,900 $54,000 $27.00 (a) On the basis of the foregoing data, answer the following questions. (1) What...