variable overhead cost variance is the difference between standard cost for actual production and actual variable overhead cost.
Now, the standard cost per hour = budgeted variable overhead / budgeted direct labor hours
$15000/610hours
=24.59$ per hour
variable overhead cost variance = (Standard cost - actual cost)*actual quantity
($24.59*480hours)-$15,100
=$11,808-$15,100
=$3296 unfavorable [ as the actual cost is higher than standard cost the variance is unfavorable]
Judd Company uses standard costs for its manufacturing division. Standards specify 0.1 direct labor hours per...
Wave Fashions uses standard costs for its manufacturing division. The allocation base for overhead costs is direct labor hours. From the following data, calculate the total fixed overhead variance. Actual fixed overhead $ 32,000 Budgeted fixed overhead $ 26,000 Allocated fixed overhead $ 28,350 Standard overhead allocation rate $ 6.75 Standard direct labor hours per unit 2.1 DLHr Actual output 2,000 units A. $ 3,650 F B. $ 3,650 U C. $ 13,500 F D. $ 13,500 U
Desue Corporation makes a product with the following standards for labor and variable overhead: Standard Quantity or Hours Standard Price or Rate Standard Cost Per Unit Direct labor 0.1 hours $19.00 per hour $1.90 Variable overhead 0.1 hours $7.00 per hour $0.70 The company budgeted for production of 6,500 units in December, but actual production was 6,300 units. The company used 610 direct labor-hours to produce this output. The actual variable overhead rate was $6.40 per hour. The company applies...
Question 6 Not yet answered Wave Fashions uses standard costs for its manufacturing division. The allocation base for overhead costs is direct labor hours. From the following data, calculate the total fixed overhead variance. Marked out of 2.00 $36,000 $24,500 $28,000 P Flag question Actual fixed overhead Budgeted fixed overhead Allocated fixed overhead Standard overhead allocation rate Standard direct labor hours per unit Actual output $7.00 2.00 DLHO 2000 units Select one: O A. $14,000 V O B. $14,000 F...
Standard Price and Volume Standards: Direct materials 21.0 yards per awning at $15.00 per yard Direct labor 5.0 hours per awning at $17.00 per hour Variable MOH standard rate $4.00 per direct labor hour Predetermined fixed MOH standard rate $7.00 per direct labor hour Total budgeted fixed MOH cost $78,200 Print Done X Actual Results 1 Purchased 51,750 yards at a total cost of $755,550 Used 47,500 yards in producing 2,300 awnings Actual direct labor cost of $194,256 for a...
The following data relate to direct materials costs for February: Materials cost per yard: standard, $1.98; actual, $2.04 Standard yards per unit: standard, 4.63 yards; actual, 4.91 yards Units of production: 9,100 Calculate the direct materials quantity variance. a.$5,045.04 favorable b.$5,045.04 unfavorable c.$5,197.92 unfavorable d.$5,197.92 favorable Flapjack Corporation had 7,768 actual direct labor hours at an actual rate of $12.40 per hour. Original production had been budgeted for 1,100 units, but only 971 units were actually produced. Labor standards were...
Prado Company applies fixed manufacturing overhead costs to products based on direct labor hours. Information for the month of April appears below. Prado's expected to produce and sell 500 units for the month. Budgeted fixed overhead costs $240,000 Budgeted direct labor hours ÷ 12,000 Standard cost per direct labor hour $ 20 Standard direct labor hours per unit 18 Actual production 520 units Actual fixed overhead costs $210,000 Required: Calculate the fixed overhead spending variance and production volume variance. Clearly...
1. Lee Manufacturing uses a standard cost system with overhead applied based on direct labor hours. The manufacturing budget for the production of 5,000 units for the month of May included the following information. Direct labor (10,000 hours at $15 per hour) $150,000 Variable overhead $30,000 Fixed overhead $80,000 During May, 6,000 units were produced and the direct labor efficiency variance was $1,500 unfavorable. Based on this information, the actual number of direct labor hours used in...
BUDGETED Direct Materials 5.00 lbs. per unit $30.00 per lbs. Direct Labor 2.00 hours per unit $25.00 per hour VMOH $3,200,000 FMOH $5,600,000 MHRS 80,000 MHRS Production volume 40,000 units Allocation base MHRS ACTUAL Direct Materials 4.50 lbs. per unit $32.00 per lbs. Direct Labor 2.50 hours per unit $22.00 per hour VMOH $3,192,000 FMOH $5,300,000 MHRS 84,000 MHRS Production volume 35,000 units Variable Manufacturing Overhead Variances Actual Costs Allocated: AQ AR AQ BR SQA BR VMOH SP Var VMOH...
is based on budgeted direct labor-hours. The direct labor budget indicates that 7,200 direct labor-hours will be required in May. The variable overhead rate is $7.70 per direct labor-hour. The company's budgeted fixed manufacturing overhead is $139,680 per month, which includes depreciation of $24,850. All other fixed manufacturing overhead costs represent current cash flows. The company recomputes its predetermined overhead rate every month. The predetermined overhead rate for May should be: Multiple Choice $23.60 $7.70 $19.40 $23.60 $770 $19.40 $2710...
A. The standard costs and actual costs for direct materials for the manufacture of 2,240 actual units of product are as follows: Standard Costs Direct materials 2,240 kilograms @$8.60 Actual Costs Direct materials 2,300 kilograms The direct materials quantity variance is? Choose the correct answer below $413 favorable $516 unfavorable $516 favorable $413 unfavorable B. The following data relate to direct labor costs for the current period: Standard costs 7,200 hours at $11.30 Actual costs 6,400 hours at $10.80 What...