Question

critical path method

Draw the network compute the project completion time and identify the critical path Activity Duration (Weeks) 1-2 2 1-3 2 1-4 1 2-5 4 3-6 5 3-7 8 4-7 3 5-8 1 6-8 4 7-95 8-9 3
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The following information is given for a project. Draw thenetwork, compute the project

completion time and identify the critical path.

Activity : 1-2 1- 3 1-4 2-5 3-6 3-7 4-7 5-8 6-8 7-9 8-9

Duration : 2 2 1 4 5 8 3 1 4 5 3

(Weeks)

The following information is given for a project. Draw thenetwork, compute the project

completion time and identify the critical path.

Activity : 1-2 1- 3 1-4 2-5 3-6 3-7 4-7 5-8 6-8 7-9 8-9

Duration : 2 2 1 4 5 8 3 1 4 5 3

(Weeks)
answered by: wissam
Add a comment
Know the answer?
Add Answer to:
critical path method
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT