The question is based on Concept of PMBOK, where Schedule Performance Index (SPI) and Cost Performance Index (CPI) are two critical ratio, calculated as
SPI = Earned value / Planned Value of a project
If , SPI >1 , ahead of schedule
SPI <1, below the schedule
SPI = 1, as per schedule
CPI = Earned value / Actual Cost
CPI<1, earning less than the amount spent
CPI> 1, earning more than the amount spent
CPI=1 , earning equal to amount spent
As per given data , in 20 days Earned Value = 33,
Planned Value per day = total earning / total days = 200/100 = 2
Planned value in 20 days = 2*20= 40.
SPI =33/40 = 0.825.
SPI<1, Project is running behind schedule
Actual cost data is missing, so cannot say anything about CPI.
4. Design and plot a critical ratio for a computer installation project that had planned constant,...
Problem 1 While performing scheduling work on a project you have determined that one activity has a great deal of variability. A sample of times (30) the task has been completed is provided the table below. Assume that the task is considered to be "late" if the task duration is two days greater than the mean value (rounded to the nearest whole day), and "early" if the task duration is two days less than the mean value (rounded to the...
Project management
Zeus Project-A You are Donald Tuck, the project manager in charge of the Zeus project. Zeus was the code name given to the development of a virtual electronic medical reference guide. Zeus would be designed for emergency medical technicians and paramedics who need a quick reference guide to use in emergency situations, even in offline mode. Donald and his project team were developing a project plan aimed at producing 30 working models in time for InterMedCON 2018, the...
Solve using Minitab.
The table is observations on weekly operational downtime on a critical equipment (order read top to bottom and left to right). The target value for the mean is 25. (a) Estimate the process standard deviation. (b) Set up and apply a tabular cusum chart for this process using standardized values h 5 and k = 2. (c) Interpret the cusum chart - 27 24 22 27 25 27 23 20 28 29 24 28 20 29 21...
Instructions: You are preparing a status report for your project sponsor and stakeholders and it's important to share the project progress using the Earned Value technique. You are preparing your status report for the period ending October 28th. Your project started February 27th. Assume that the project is executed 5 days per week and 8 hours per day with some additional hours that amount to 8 hours every Saturday and Sunday. The project manager's table of activities are noted below....
Question 18 What are the two principles when crashing a project? Focus on the critical path, select the least expensive alternative. Reduce the cost, reduce the duration. Reduce the duration, increase the cost. Reduce the use of resources, reduce the cost 4 points Question 19 The formula for computing the cost/time slope for each activity that can be crashed is . (Crash cost + Normal cost) / (Crash time + Normal time) (Crash cost - Normal cost) / (Crash time...
a. Develop a report that presents a planned schedule and
expected project completion time in
workdays. Include a project network in your report using MS
Project.
b. Explain how does this project compared to the average project.
The average duration for a
construction of a villa project normally takes 120 workdays.
c. Find the probability of finishing this project in 120
workdays?
d. Also find what expected completion time will ensure a 90% chance
of completing the
project in 120...
The computer-science aptitude score, x, and the achievement score, y (measured by a comprehensive final), were measured for 20 students in a beginning computer-science course. The results were as follows. x 3 15 19 14 21 22 14 21 20 15 17 18 7 5 4 19 17 12 18 13 y 19 19 24 36 27 26 25 28 17 27 21 24 18 18 14 28 21 22 20 21 (a) Find the equation of the line of...
Question: 3.897 21 3.885 14 3.778 28 2.540&n... 3.897 21 3.885 14 3.778 28 2.540 22 3.028 21 3.865 31 2.962 32 3.961 27 0.500 29 3.178 26 3.310 24 3.538 30 3.083 24 3.013 24 3.245 33 2.963 27 3.522 25 3.013 31 2.947 25 2.118 20 2.563 24 3.357 21 3.731 28 3.925 27 3.556 28 3.101 26 2.420 28 2.579 22 3.871 26 3.060 21 3.927 25 2.375 16 2.929 28 3.375 26 2.857 22 3.072 24...
Dave Green, an analyst at Hyvee, shared his forecasts of the daily Tide sales for days 1 to 15 with you as given in the table below (actual sales for days 1 to 15 is already given to you in question 4 above). Using Dave’s forecasts given below answer the following questions: Day 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 Dave's Forecast 20 27 14 14 8 11 18 15 8 24...
39. Consider the following project, and answer the next 5 questions based on this data: Task ID Duration (Days) Predecessors 2 70 - 3 30 2 4 120 3 5 120 2 6 120 5 7 120 3,6 8 150 3,6 9 115 3,6 10 130 7,9 11 90 7,9 12 30 7,9 13 120 7,9 14 75 10 15 30 14 16 85 6 17 165 16 18 90 16 19 90 17,18 20 20 8,11,13,15,19 What is the...