Question

Question 18 What are the two principles when crashing a project? Focus on the critical path,...

Question 18

  1. What are the two principles when crashing a project?

    Focus on the critical path, select the least expensive alternative.

    Reduce the cost, reduce the duration.

    Reduce the duration, increase the cost.

    Reduce the use of resources, reduce the cost

4 points

Question 19

  1. The formula for computing the cost/time slope for each activity that can be crashed is .

    (Crash cost + Normal cost) / (Crash time + Normal time)

    (Crash cost - Normal cost) / (Crash time - Normal time)

    (Normal cost + Crash cost) / (Normal time - Crash time)

    (Normal cost - Crash cost) / (Normal time - Crash time)

4 points

Question 20

  1. The             schedule compression technique overlaps the design and builds phases of a project to expedite its completion.

    crashing

    leading

    fast-tracking

    blitzing

2 points

Question 21

  1. The points between the extreme points of the relationship between time use and resource use represent ________.

    Time constrained projects

    Resource constrained projects

    Alternatives for trade-offs between time and resources

    A non-feasible solution space of trade-off alternatives related to time and resource use

4 points

Question 22

  1. Project task E has the following estimates: (1) optimistic time – 10 days, (2) Pessimistic time - 20 days, and (3) Most likely time - 12 Days. The expected time using the beta statistical distribution is __________ days.

    22

    9

    14

    13

4 points

Question 23

  1. The usual purpose of the             scheduling heuristic is to delay cash outflows as long as possible.

    minimum slack first

    shortest task first

    most successors

    as late as possible

4 points

Question 24

  1. Which of the following effects will be observed in a network if a date-constrained project is scheduled from the ending date constraint using the “as late as possible” heuristic?

    Eacy activity will have zero slack and be located on the critical path.

    The network will not have any critical activities because everything can be done prior to the final date constraint.

    It would never be possible to override the "as late as possible" heuristic with a "must start no later than" date constraint.

    It would never be possible to schedule an activity prior to the start date of the project.

4 points

Question 25

  1. Given that task A will use three carpenters and have duration of six days, task A requires __________ labor days of work.

    9

    12

    18

    24

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Question 18

Correct answer is Focus on the critical path, select the least expensive alternative.

During crashing we need to Focus on the critical path, select the least expensive alternative.

Question 19

Correct answer is (Crash cost - normal cost) / (crash time - normal time)

The formula for computing the cost/time slope for each activity that can be crashed is (Crash cost - normal cost) / (crash time - normal time)

Question 20

Correct answer is Fast-tracking

The Fast-tracking schedule compression technique overlaps the design and builds phases of a project to expedite its completion

Question 21

Correct answer is Alternatives for trade-offs between time and resources

The points between the extreme points of the relationship between time use and resource use represent Alternatives for trade-offs between time and resources


Question 22

Correct answer is 13

expected time using the beta statistical distribution = (optimistic+pessimistic+4*most likely time)/6 = (10+20+4*12)/6 = 13

Question 23

Correct answer is as late as possible

The usual purpose of the as late as possible scheduling heuristic is to delay cash outflows as long as possible.

Question 24

Correct answer is Each activity will have zero slack and be located on the critical path.

In “as late as possible” heuristic , each activity will make use of all the available slack


Question 25

Correct answer is 18

Given that task A will use three carpenters and have duration of six days, task A requires 18 labor days of work.

Add a comment
Know the answer?
Add Answer to:
Question 18 What are the two principles when crashing a project? Focus on the critical path,...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Given below is the crashing data for a project along with other data. The project completion...

    Given below is the crashing data for a project along with other data. The project completion time is 20 davs. Determine: (a) the crash slope (i.e crash cost/day) for all activities, (b) the normal total project cost, (c) prioritized the list of activities for crashing from best to worst, (d) the best activity to crash if the project has to be completed in 19 days and alternative critical paths, if any, (e) the earliest time the project can be completed,...

  • What is the minimum cost of crashing the following project that Roger Solano manages at Slippery...

    What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4​ days? A)By how many days should each activity be crashed to reduce the project completion time by 4​ days? Fill in the table below. ​(Enter your responses as whole numbers.​) B) The total cost of crashing the project by 4 days is $. (Enter your response as a whole number.) Normal Crash Time Normal Total Cost Activity Time (days) (days)...

  • What is the minimum cost of crashing the following project that Roger Solano manages at Slippery...

    What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Crash Time Normal Activity Time (days) (days) Cost $800 $250 $600 $750 $1,200 Uw > A Awarw Total Cost with Crashing Immediate Predecessor(s) $1,100 $600 $650 $1,500 $1,650 OD By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.)...

  • 1. Explain the cost structure for reducing the project duration (crashing). Which cost is used to...

    1. Explain the cost structure for reducing the project duration (crashing). Which cost is used to crash the project? Discuss why this cost is important to use for the crashing? 2. Reducing the project scope is one of the options used to accelerate the project completion. What are other options that may be considered when crashing the project, operating under resource constrained? Are there any risks associated with reducing the project duration? Briefly explain.

  • QUESTION 9 Consider the following project; for which activities is it possible that the slack can...

    QUESTION 9 Consider the following project; for which activities is it possible that the slack can be greater than zero? Activity Immediate Predecessors B, E a. Only activities B or E could have slack, but they could not both have slack. Ob. Only activities B or C could have slack, but they could not both have slack. Oc. It is possible for any or all activities in this project to have slack. Od. It is possible for either all three...

  • 5.) Consider a project whose activities are listed in the table below. Activity A will have...

    5.) Consider a project whose activities are listed in the table below. Activity A will have slack time as long as…    Activity Immediate Predecessors A None B None C A D B E C, D F E G E a. Duration of A < Duration of B b. Duration of A + Duration of C > Duration of B + Duration of D c. Duration of A + Duration of C < Duration of B + Duration of D...

  • Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3...

    Normal Time Crash Time Normal with Activity (weeks) (weeks) Cost Crashing Immediate Predecessor(s) $1,400 A 3 2 $2,050 $2,800 B 2 1 $2,100 1 1 $350 $350 7 $1,400 $1,700 A 6 3 $900 $1,200 $5,000 $2,000 F 2 $4,000 $1,500 C 4 G 2 D, E weeks a) Based on the given information regarding the activities for the project, the project completion date b) To reduce the duration of the project to 10 weeks at the least cost, the...

  • 1. When finding the approximate probability of project duration, it is necessary to know which of...

    1. When finding the approximate probability of project duration, it is necessary to know which of following? a. The mean and variance of each activity b. The mean of each activity on the CP c. The sd of only the activities on the CP d. Each activity's probability of completion e. The distribution of activity times 2. The sd of a path is computed as: a. the sum of the sd of all activities on the path b. the square...

  • What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days?...

    What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? IMMEDIATE PREDECESSOR(S) ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) NORMAL TIME (DAYS) 9 7 5 6 CRASH TIME NORMAL (DAYS) COST 7 200 6 800 4 600 4 1,100 6 1,200 CRASH COST 300 875 675 1,300 1,875 9 A,B с The minimum cost of crashing the following project at Sawaya Robotics by. 4 days is $ whole number)....

  • 62. Task ID Predecessors Normal Time Maximum Crash Time Normal Cost Crash Cost (Slope) 1 -...

    62. Task ID Predecessors Normal Time Maximum Crash Time Normal Cost Crash Cost (Slope) 1 - 5 1 50 20 2 - 3 2 60 60 3 1 4 0 70 0 4 1 2 1 50 10 5 2 5 3 100 60 6 3 2 1 90 100 7 4 5 1 50 30 8 5 2 0 60 40 9 6,7,8 3 1 200 200 Consider the project above. If the indirect costs of the project are:...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT