Question

62. Task ID Predecessors Normal Time Maximum Crash Time Normal Cost Crash Cost (Slope) 1 -...

62.

Task ID

Predecessors

Normal Time

Maximum Crash Time

Normal Cost

Crash Cost (Slope)

1

-

5

1

50

20

2

-

3

2

60

60

3

1

4

0

70

0

4

1

2

1

50

10

5

2

5

3

100

60

6

3

2

1

90

100

7

4

5

1

50

30

8

5

2

0

60

40

9

6,7,8

3

1

200

200

Consider the project above. If the indirect costs of the project are: $90 at 15 days, $75 at 14 days, $50 at 13 days, $40 at 12 days, and $30 at 11 days.

Please help crash this project in a manner that minimizes the sum of the total direct and indirect costs. Answer the next 9 questions based on this data.

What is the current estimated project duration in days without any crashing?

11

14

13

15

63.

What is the current critical path?

1-3-6-9

1-4-6-9

2-5-8-9

None of the above

64.

Currently, which is the cheapest task to crash that can reduce project duration?

Task 4

Task 3

Task 1

Task 7

65.

After the first iteration of crashing, what is/are the critical path(s)?

More than one path is critical

1-4-7-9

1-3-6-9

2-5-8-9

66.

After the first iteration of crashing, what is the total sum of direct and indirect costs of the project?

840

815

830

825

67.

Which is the cheapest task to crash for the second iteration that can reduce project duration?

Task 2

Task 5

Task 1

Task 6

68.

After the second iteration of crashing, what is/are the critical path(s)?

1-3-6-9

1-4-7-9

2-5-8-9

All of the above

69.

After the second iteration of crashing, what is the total sum of direct and indirect costs of the project?

810

825

830

840

70.

What is the maximum time we can reduce the duration of the project by, for the third iteration of crashing?

0

3

1

2

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer summary: precedence diagram and finding the critical paths, duration, crashing.

Add a comment
Know the answer?
Add Answer to:
62. Task ID Predecessors Normal Time Maximum Crash Time Normal Cost Crash Cost (Slope) 1 -...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT