1. When finding the approximate probability of project duration, it is necessary to know which of following?
a. The mean and variance of each activity
b. The mean of each activity on the CP
c. The sd of only the activities on the CP
d. Each activity's probability of completion
e. The distribution of activity times
2. The sd of a path is computed as:
a. the sum of the sd of all activities on the path
b. the square root of the sum of the sd of all activities on the path
c. the sum of variances of all activities on the path
d. the square root of the sum of variances of all activities on the path
e None of above
3. An activity has an optimistic time estimate of three days, a most like time estimate of eight days, and a pessimistic time estimate of ten days. The expected duration of the activity is?
4. Activity C in a project network has an optimistic time estimate of five days, a most like time estimate of seven days, and a pessimistic time estimate of nine days. The expected duration of the activity is?
5. There are four activities on the critical path, and they have sd of 1,2,4 and 2 days. The sd of the critical path is?
6. There are four activities on the critical path. Coincidentally, their sd are all equal to 4. The sd of the critical path is therefore equal to?
7. The project management strategy of injecting additional resources in order to reduce the length of the project is called?
8. In crashing a project, a manager will generally focus on activities which:
a. are not on the critical path
b. are the least costly to crash
c. are costly to crash and are on the critical path
d. are on the cp and are the least costly to crash
e. none of above
9. At which point does crashing of a project cease?
a. when the project is completed
b. when no additional crashing is possible
c. when the cost to crash equals or exceeds the benefit of crashing
d. all of above
e. none of above
10. which of the following are ways of crashing an activity?
a. using overtime
b. hiring more workers
c. using specialized equipment
d. all of the above
e. none of the above
11. When using linear programming to make crashing decisions, the objective is to minimize
a. the total cost of crashing the project
b. the total of the durations of the activities on the cp
c. the latest finish time of the finish node
d. the total number of activities on the cp
e. none of the above
12. PERT/Cost
a. finds the penatly cost if a project is not completed on time
b. compares the actual budget with the planned budget
c. shows management where to focus attention during the project
d. a and b only
e. b and c only
1. b - The mean of each activity on the CP
2. d. the square root of the sum of variances of all activities on the path
3. Pert Estimate = (Optimistic + (4 X Most Likely) + Pessimistic)/6
Pert Estimate = (3+(4*8)+10)/6 = 45/6 = 7.5 days
4. Pert Estimate = (Optimistic + (4 X Most Likely) + Pessimistic)/6
Pert Estimate = (5+(4*7)+9)/6 = 42/6 = 7
1. When finding the approximate probability of project duration, it is necessary to know which of...
5. A project has critical path activities A, B, and C. A is the predecessor of B. B is the predecessor of C. The duration estimate for activity A, B and C is shown in the following table. Fill the table with mean duration, standard deviation, and variance for activities and the whole project (critical path). Determine what is the probability of completing this project within 80 days? (10 points) Activity Optimistic Pessimistic Most likely Mean Standard Variance deviation duration...
It was determined on the following project that the duration for the tasks contained some uncertainty. After more research, the optimistic and pessimistic values were determined. 1. a. Calculate the expected time and variance (using the 95 percent level of confidence) for each activity. b. Determine the critical path and time for completion c. Calculate the probably that the project will finish in 30 days. Calculate the probably of completing the project in 27 days. Other than the critical path,...
Question 18 What are the two principles when crashing a project? Focus on the critical path, select the least expensive alternative. Reduce the cost, reduce the duration. Reduce the duration, increase the cost. Reduce the use of resources, reduce the cost 4 points Question 19 The formula for computing the cost/time slope for each activity that can be crashed is . (Crash cost + Normal cost) / (Crash time + Normal time) (Crash cost - Normal cost) / (Crash time...
Find the optimal way to achieve a project duration of 27 days? Use the template below to record your steps InClass – Project Crashing Exercise Project details: Task Predecessor N (days) C (days) D1 ($) D2 ($) A start 7 5 40 80 B A 9 8 60 70 C B 12 10 90 150 D start 10 7 60 120 E D 5 4 50 60 F E 10 6 80 140 Fin C, F Find the optimal way...
1. Sid Orland is involved in planning a scientific research project. The activities are displayed in the following diagram. Optimistic, most likely, and pessimistic time estimates are displayed in the following table. Figure for Problem 1. r e 14 16 E 4 H 4 7 11 7 11 16 20 G 5 0 33 611 16 11 16 D 3 Most Likely Pessimistic Activity Optimistic 4 4 (a) Determine the expected times and variances for each activity along the critical...
5.) Consider a project whose activities are listed in the table below. Activity A will have slack time as long as… Activity Immediate Predecessors A None B None C A D B E C, D F E G E a. Duration of A < Duration of B b. Duration of A + Duration of C > Duration of B + Duration of D c. Duration of A + Duration of C < Duration of B + Duration of D...
1. State whether each of the following statement is true or false. a) The sequence of activities in a project is depicted by the precedence (0.5 mark) (0.5 mark) relationships. The critical path is the shortest path through the project network. Slack is the amount of time an activity can be delayed without delaying the project. In PERT, three time estimates (optimistic, most likely and pessimistic) provide an estimate of the mean and variance for each activity based on the...
The table below gives the optimistic, most-likely, and pessimistic time estimates (in weeks) for all activities in a project. (Statistical tables are available in appendix I) Activ Predecessor totm t 2.0 5.0 8.0 3.0 4.0 5.0 4.06.08.0 5.0 6.0 7.0 3.0 6.0 9.0 D, E (i) Calculate the estimated time and variance for each task (ii) Draw the AON diagram and identify the critical path. (iii) What is the expected critical path duration and estimate a standard deviation for the...
Use a PERT network to establish the expected duration for the project described in the table below: (SHOW the PERT NETWORK) Activity Predecessors Duration a m b Exp. Duration Var. Crash Week 1 Crash Week 2 A - 3 6 9 700 100 B A 6 7 14 600 200 C A 4 6 14 400 600 D B, C 4 6 8 200 600 E B, C 6 9 12 400 300 F C 4 6 14...
Consider a project having the following six activities: Immediate Max Crash cost Activity Predecessors Time (weeks) Crash* per week A none 6 6 N/A B none 5 2 $500 C A 3 2 $1000 D A, B 4 2 $2000 E C, D 5 2 $1250 F D 6 2 $1000 *Shortest possible time for the task 1. Draw the project network and list...