Question

22) Noah Construction Company is building a large complex for a contract price of $5,000,000 This is a three-year project and
0 0
Add a comment Improve this question Transcribed image text
Answer #1

Correct option is "B"-625000

Year 1 2 3
Cost incurred Till date 1000 1000(till year 1 )+1500=2500 2500 (till year 2) +1250=3750
Estimated cost to complete 3000 1500 0
Total cost of contract 4000 4000 3750
% of completion [cost incurred till date /Total cost ]

1000/4000

25%

2500/4000

62.5%

3750/3750

100%

Year 1 2 3
Contract price 5000 5000 5000
Less:Total cost (4000) (4000) (3750)
Gross profit 1000 1000 1250
% of completion 25% 62.5% 100%
Gross profit to be recognized till date 1000*25%=250 1000*62.5%=625 1250*100%=1250
Less:Gross profit recognized till prior year 0 -250 -625
Gross profit to be recognized in current period 250 375 625
Add a comment
Know the answer?
Add Answer to:
22) Noah Construction Company is building a large complex for a contract price of $5,000,000 This...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 23) A right of return exists when: A) the customer is entitled to a full or...

    23) A right of return exists when: A) the customer is entitled to a full or partial refund. B) the customer is entitled to a credit against amounts owed. C) the customer is entitled to another product in exchange. D) any one of these conditions is met. 19) Noah Construction Company is building a large complex for a contract price of $5,000,000. This is a three-year project and the requirements for recognizing revenue over time are met. The total estimated...

  • Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began...

    Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Estimated Costs to Complete Costs Incurred During Year (As of the End of the Year) Situation 2021 2022 2023 2021 2022 2023 1 1,500 2,100 900 3,000 900 — 2 1,500...

  • King Corporation started the construction of a building during 2017 at a contract price of $5,000,000....

    King Corporation started the construction of a building during 2017 at a contract price of $5,000,000. The contract to build was non-cancellable and they managed to complete the project in 2019 as anticipated. Billings are nonrefundable and under the terms of the project, King sends billings to the vendor as revenues are earned. The following additional information is available: 2017 2018 2019 Costs to-date $ 800,000 $2,500,000 $4,800,000 Estimated costs to complete $2,400,000 $2,500,000 $0 Required: a. Calculate the amount...

  • Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began...

    Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2013 and was completed in 2015. The following are a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars Costs Incurred During Year Situation 2013 2014 2015 1 1,500 2,100 900 3,000 900 %u2014 2 1,500 900 2,400 3,000 2,400 %u2014 3 1,500 2,100 1,600 3,000 1,500 %u2014 4 500...

  • 2. Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction...

    2. Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Situation о» от дома Costs Incurred During Year 2021 2022 2023 1,500 2,100 900 1,500 900 2,400 1,500 2,100 1,600 500 3,000 1,000 500 3,000 1,300 500 3,000 1,800 Estimated...

  • Fender period. Construction Company receives a contract to construct a building over a 3 year Information...

    Fender period. Construction Company receives a contract to construct a building over a 3 year Information relating to the performance of the contract is summarized as follows: 2015 2016 2017 S 16,000,000 Cumulative construction costs incurred to date Estimated costs to complete Billings during the year Cash collected during the year 6,000,000 8,000,000 6,000,000 3,000,000 8,000,000 7,000,000 4,000,000 5,000,000 Required: 1. How much is Fender Construction charging to build this athletic stadium? In other words, what is the contract price...

  • Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021,...

    Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,960,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings to Axelrod under the...

  • Exercise 6-23 (Static) Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion...

    Exercise 6-23 (Static) Income (loss) recognition; Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] Brady Construction Company contracted to build an apartment complex for a price of $5,000,000. Construction began in 2021 and was completed in 2023. The following is a series of independent situations, numbered 1 through 6, involving differing costs for the project. All costs are stated in thousands of dollars. Situation 1 2 3 4 Costs Incurred During Year 2021 2022 2023 1,500 2,100...

  • Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates...

    Check my work 10 Curtiss Construction Company, Inc., entered into a fixed-price contract with Axelrod Associates on July 1, 2021, to construct a four-story office building. At that time, Curtiss estimated that it would take between two and three years to complete the project. The total contract price for construction of the building is $4,000,000. The building was completed on December 31, 2023. Estimated percentage of completion, accumulated contract costs incurred, estimated costs to complete the contract, and accumulated billings...

  • McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun...

    McCombs Contractors received a contract to construct a mental health facility for $2,500. Construction was begun in 2023 and completed in 2024. Cost and other data are presented below: 2024 $1,300 Costs incurred during the year Estimated costs to complete Billings during the year Cash collections during the year 2023 $1,500 1,200 1,200 1,000 1,300 1,500 1. Compute the amount of revenue and gross profit recognized during 2023 and 2024. 2. Assume that McCombs recognizes revenue on this contract over...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT