An unnamed company is designing a product layout for a new product. It plans to use this production line to meet projected demand of 320 units per 7.00 hour day, and the tasks necessary to produce this product are as follows...

Task Time (sec) Predecessor
u 30 none
v 33 u
w 4 v
x 17 u, v
y 51 x
z 23 v, y

If the company wants the output rate to be equal to demand, what is the desired cycle time in seconds?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Total Task Time = 30+33+4+17+51+23 = 158 seconds

Total Available Time = 7*60*60 = 25200 seconds

Output rate = Demand = 320 units per day

Desired Cycle Time = Total Available Time/Demand

Desired Cycle Time = 25200/320 = 78.75 seconds

Add a comment
Know the answer?
Add Answer to:
An unnamed company is designing a product layout for a new product. It plans to use...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • A company is designing a product layout for a new product. It plans to use this...

    A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day. The tasks necessary to produce this product are detailed in the table below. a. Draw the network described in the table. b. What is the required cycle time (in seconds) in order to meet the schedule? c. What is the theoretical minimum number of workstations needed to...

  • the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans to use this new production line eight hours a day in ord...

    the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. the following table describes the tasks involved in the production of a mint chocolate chip cookie. Task Predecessor Time (seconds) U ----- 4 V U 14 W V 12 X V 10 Y W...

  • QUESTION 37 A company is designing a product layout for a new product. It plans to...

    QUESTION 37 A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day. The tasks necessary to produce this product are detailed in the table below. Task Predecessor Time (seconds) 50 А B А 20 С А 26 D 40 B, C C E 30 a. Draw the network described in the table. b. What is the required...

  • the maker of the world famous chocolate chip cookies needs to design a product layout for...

    the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. the following table describes the tasks involved in the production of a mint chocolate chip cookie. Task Predecessor Time (seconds) U ----- 4 V U 14 W V 12 X V 10 Y W...

  • QUESTION 19 QRS Corp. is designing a product layout for a new product. They plan to...

    QUESTION 19 QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: Compute the required cycle time for this production line? Immediate Task Timesecs) Predecessor А 34 24A 14 A С D 20 B,C E 10C 30 DE G 45 F 30 seconds 40 seconds 45...

  • QRS Corp. is designing a product layout for a new product. They plan to use this...

    QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: Task Time(secs) Immediate Predecessor a 34 none b 20 a c 10 b d 16 b e 10 c f 24 d,e g 38 f For output to equal forecasted demand, what will be the second...

  • QUESTION 6 An industrial food processor needs to design a product layout for a new line...

    QUESTION 6 An industrial food processor needs to design a product layout for a new line of frozen pizza. The company plans to use this new production line ten hours a day in order to meet projected demand of 1,000 pizzas per day. The following table describes the tasks involved in the production of a frozen pizza. Task Immediate Predecessors Task Duration (Seconds) none 10 B C,D F E Design this layout using the decision rule of Longest Processing Time...

  • Answer questions 32-37, they are all oart of the same question Theres no more information provided,what...

    Answer questions 32-37, they are all oart of the same question Theres no more information provided,what are you asking for? Questions 32 to 37 refer to the following: The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved...

  • Your scientists have perfected Harry Potter's invisibility cloak and are ramping up production. It plans to...

    Your scientists have perfected Harry Potter's invisibility cloak and are ramping up production. It plans to use this production line sixteen hours a day in order to meet projected demand of 1600 units. The tasks necessary to produce this product are: Task Time (minutes) Predecessor Get Cloth 4 none Get Bat Wings 5 none Boil Toil and Trouble 15.4 none Stir in ingredients 1 Bat Wings & Boil Paint onto Cloth 11.0 Stir & Cloth Package for delivery 2.0 Paint...

  • operational management

    A company is designing a product layout for a new product. It plans to use thisproduction line eight hours a day in order to meet a schedule of 300 units per day.The tasks necessary to produce this product are detailed in the table below.Task PredecessorTime  (seconds)A -- 55B A 46C -- 21D -- 22E B, D 70F C, E 20(a) Draw the network described in the table.(b) Without regard to a production schedule, what is the minimum possible cycle time  (in seconds) for this situation; what is the maximum?  (c) What is the...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT