the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. the following table describes the tasks involved in the production of a mint chocolate chip cookie.
| Task | Predecessor | Time (seconds) |
| U | ----- | 4 |
| V | U | 14 |
| W | V | 12 |
| X | V | 10 |
| Y | W | 6 |
| Z | X,Y | 8 |
1. Draw a predence diagram for the tasks listed above.
2. Without considering projected demands, what is the minimum possible cycle time for this production line?
3. For output to equal projected demand, what should be the actual cycle time for this production line?
4. For output equal projected demand, what is the minimum number of workstatsions needed?
5. For output to equal projected demand, what will be the effciency of the production line that uses the minimum number of workstations?
1.

2.
Minimum cycle time = time taken by longest task = 14 seconds
3.Actual cycle time = Time available for production/ desired output = (8*3600)/1440 = 20 seconds
4.
Minimum number of machine = Time required to produce desired output/Time available for production
= (1440*54)/(8*3600) [ Sum of all task times = 55]
= 2.7
= 3(Rounded to nearest whole number)
the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans to use this new production line eight hours a day in ord...
the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. the following table describes the tasks involved in the production of a mint chocolate chip cookie. Task Predecessor Time (seconds) U ----- 4 V U 14 W V 12 X V 10 Y W...
Answer questions 32-37, they are all oart of the same
question
Theres no more information provided,what are you asking for?
Questions 32 to 37 refer to the following: The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved...
An unnamed company is designing a product layout for a new product. It plans to use this production line to meet projected demand of 320 units per 7.00 hour day, and the tasks necessary to produce this product are as follows... Task Time (sec) Predecessor u 30 none v 33 u w 4 v x 17 u, v y 51 x z 23 v, y If the company wants the output rate to be equal to demand, what is the...
A company is designing a product layout for a new product. It
plans to use this production line eight hours a day in order to
meet a schedule of 400 units per day. The tasks necessary to
produce this product are detailed in the table below.
a. Draw the network described in the table.
b. What is the required cycle time (in seconds) in order to meet the schedule?
c. What is the theoretical minimum number of workstations needed to...
QUESTION 37 A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day. The tasks necessary to produce this product are detailed in the table below. Task Predecessor Time (seconds) 50 А B А 20 С А 26 D 40 B, C C E 30 a. Draw the network described in the table. b. What is the required...
QUESTION 6 An industrial food processor needs to design a product layout for a new line of frozen pizza. The company plans to use this new production line ten hours a day in order to meet projected demand of 1,000 pizzas per day. The following table describes the tasks involved in the production of a frozen pizza. Task Immediate Predecessors Task Duration (Seconds) none 10 B C,D F E Design this layout using the decision rule of Longest Processing Time...
QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: Task Time(secs) Immediate Predecessor a 34 none b 20 a c 10 b d 16 b e 10 c f 24 d,e g 38 f For output to equal forecasted demand, what will be the second...
Your scientists have perfected Harry Potter's invisibility cloak and are ramping up production. It plans to use this production line sixteen hours a day in order to meet projected demand of 1600 units. The tasks necessary to produce this product are: Task Time (minutes) Predecessor Get Cloth 4 none Get Bat Wings 5 none Boil Toil and Trouble 15.4 none Stir in ingredients 1 Bat Wings & Boil Paint onto Cloth 11.0 Stir & Cloth Package for delivery 2.0 Paint...
1. [Layout Strategy-Line Balancing] The call center department of Jax-steel company needs to service 3,000 calls per 40-hour workweek. The process of servicing calls can be broken down into the six stations listed above. The precedence and time requirements for each element are as follows in the table below. The manager wants a new operational analyst to draw and label a precedence diagram for the service process. Finally, the manager needs to balance the line, calculate the efficiency of the...
ANSWER THE FOLLOWING QUESTIONS 1: Mr. Meadows Cookie Company makes a variety of chocolate chip cookies in the plant in Albion, Michigan. Based on orders received and forecasts of buying habits, it is assumed that the demand for the next three months is 600, 800 and 450, expressed in thousands of cookies. During a 50-day period when there were 80 workers, the company produced 2.4 million cookies. Assume that the number of workdays in each month is 25. There are...