QRS Corp. is designing a product layout for a new product. They plan to use this...

QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product:

Task Time(secs) Immediate
Predecessor
a 34 none
b 20 a
c 10 b
d 16 b
e 10 c
f 24 d,e
g 38 f

For output to equal forecasted demand, what will be the second task performed at the second workstation of the production line that uses the fewest number of stations?

a

b

c

d

e

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Total Available time = 10 hour

Demand = 900 units /10 hour = 90 units / hr

Cycle time = 60*60/90 = 40 sec.

Total Task time = 152 seconds

Theoretical minimum number of workstations = Total Task time / cycle time = 152 / 40 =3.8 = 4

The work allocation is as follows.

Work Station Tasks Time Idle time
1 a 34 6
2 b,c,e 40 0
3 d,f 40 0
4 g 38 2

From above, The required task is C,

Add a comment
Know the answer?
Add Answer to:
QRS Corp. is designing a product layout for a new product. They plan to use this...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • QUESTION 19 QRS Corp. is designing a product layout for a new product. They plan to...

    QUESTION 19 QRS Corp. is designing a product layout for a new product. They plan to use this production line 10 hours a day in order to meet forecasted demand of 900 units per day. The following table describes the tasks necessary to produce this product: Compute the required cycle time for this production line? Immediate Task Timesecs) Predecessor А 34 24A 14 A С D 20 B,C E 10C 30 DE G 45 F 30 seconds 40 seconds 45...

  • QUESTION 37 A company is designing a product layout for a new product. It plans to...

    QUESTION 37 A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day. The tasks necessary to produce this product are detailed in the table below. Task Predecessor Time (seconds) 50 А B А 20 С А 26 D 40 B, C C E 30 a. Draw the network described in the table. b. What is the required...

  • A company is designing a product layout for a new product. It plans to use this...

    A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day. The tasks necessary to produce this product are detailed in the table below. a. Draw the network described in the table. b. What is the required cycle time (in seconds) in order to meet the schedule? c. What is the theoretical minimum number of workstations needed to...

  • An unnamed company is designing a product layout for a new product. It plans to use...

    An unnamed company is designing a product layout for a new product. It plans to use this production line to meet projected demand of 320 units per 7.00 hour day, and the tasks necessary to produce this product are as follows... Task Time (sec) Predecessor u 30 none v 33 u w 4 v x 17 u, v y 51 x z 23 v, y If the company wants the output rate to be equal to demand, what is the...

  • QUESTION 6 An industrial food processor needs to design a product layout for a new line...

    QUESTION 6 An industrial food processor needs to design a product layout for a new line of frozen pizza. The company plans to use this new production line ten hours a day in order to meet projected demand of 1,000 pizzas per day. The following table describes the tasks involved in the production of a frozen pizza. Task Immediate Predecessors Task Duration (Seconds) none 10 B C,D F E Design this layout using the decision rule of Longest Processing Time...

  • Answer questions 32-37, they are all oart of the same question Theres no more information provided,what...

    Answer questions 32-37, they are all oart of the same question Theres no more information provided,what are you asking for? Questions 32 to 37 refer to the following: The maker of the world-famous Chocolate Chip Cookies needs to design a product layout for a new product, Mint Chocolate Chip. The company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. The following table describes the tasks involved...

  • Francis Johnson's plant needs to design an efficient assembly line to make a new product. The...

    Francis Johnson's plant needs to design an efficient assembly line to make a new product. The assembly line needs to produce 12 units per hour, and there is room for only five workstations. The tasks and the order in which they must be performed are shown in the following table. Tasks cannot be split, and it would be too expensive to duplicate any task. TASK TIME IMMEDIATE TASK (MINUTES) PREDECESSOR 2.5 2.0 2.0 3.0 3.0 3.0 3.0 A,B, C b....

  • the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans to use this new production line eight hours a day in ord...

    the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. the following table describes the tasks involved in the production of a mint chocolate chip cookie. Task Predecessor Time (seconds) U ----- 4 V U 14 W V 12 X V 10 Y W...

  • Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal...

    Stanford Rosenberg Computing wants to establish an assembly line for producing a new product, the Personal Digital Assistant (PDA). The tasks, task times, and immediate predecessors for the tasks are as follows: Task Immediate Predecessor A B с D E Time (sec) 12 14 8 5 18 A A B,C D Rosenberg's goal is to produce 180 PDAs per hour. a) The cycle time for the production of a PDA = 20.57 seconds (round your response to two decimal places)....

  • Problem Statement: A factory producing the new COVID-19 at-home testing kits is determining how to best...

    Problem Statement: A factory producing the new COVID-19 at-home testing kits is determining how to best line balance their production process. There are 12 steps to the production process, and they are presented below, along with their predecessors and how long it takes to complete each task. Assume all times are in minutes. This facility operates for 7 hours per day. Task C D E F G H I J K L A B Nil A B B B B...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT