Procest time eday) at WC 10 process time (day) at wc 20. Due Date) (A s 3, 10) (B 3 6 25) and (C 9 5 20) For this problem the
0 0
Add a comment Improve this question Transcribed image text
Answer #1

ANSWER: A. Job A

Scheduling using Johnson's rule: Select the job with the shortest processing time, if that is for Operation 1 (WC10), then schedule the job first, if that is for Operation 2 (WC20), then schedule the job last. Remove the jobs which are scheduled from further consideration. Repeat the process until all jobs are scheduled. Using Johnson's rule, jobs are scheduled as follows:

Minimum processing time is 3, for job A it is on WC20 , so A is scheduled at last. for job B it is on WC10, so B is scheduled the first. C is scheduled after B.

B-C-A

Flowtime
Job WC10 WC20 WC10 WC20
B 3 6 3 9
C 9 5 12 17
A 5 3 17 20

We see that flowtime (or completion time on WC20) of job A is greater than its due date. Therefore, job A will not meet the due date.

Add a comment
Know the answer?
Add Answer to:
Procest time eday) at WC 10 process time (day) at wc 20. Due Date) (A s...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 240 18 20 232 14 30 240 6 40 245 30 50 255 26 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT According to the LPT rule, the sequence of...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is...

    a) Using the EDD (earliest due date) decision rule for sequencing the jobs, the order is (to resolve a tie, use the order in which the jobs were received): At Morgan's Transformer Rebuilding, following jobs (below) are ready for dispatching to a work center. The processing times, date job received, and due dates for the jobs are given below. In what sequence would the jobs be ranked according to the decision rules on the left Sequence Job 1 Date Job...

  • Processing times and due dates of 9 jobs are given as follows: Job Proc Time Due Date 15 43 10 38...

    Processing times and due dates of 9 jobs are given as follows: Job Proc Time Due Date 15 43 10 38 35 40 25 20 40 Assume that all jobs arrive at time 0 a) (3 points) Generate a schedule that minimizes the mean flow time. Break ties with the smallest job number first (i.e., if 3 and 8 have identical parameters, 3 should be scheduled first). b) (3 points) Calculate mean flow time, mean tardiness, and maximum tardiness of...

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 260 8 20 252 18 30 260 26 40 270 32 50 275 14 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT? b. What is the average completion (flow) time?...

  • ABC Enterprises has five jobs that must be scheduled for production at a work center. Below...

    ABC Enterprises has five jobs that must be scheduled for production at a work center. Below are the processing times and due dates for each job.                                     Job Processing Time (in days) Due Date (days from today) 1 7 14 2 5 21 3 3 10 4 2 7 5 6 9                                                                                                                            Schedule the jobs by sequencing them using the Earliest Due Date (EDD) priority rule. What is the average flow time? Show your Work and round your...

  • Question 20, Math problem 20. The Mowry Machine Shop still has five jobs to be pro-...

    Question 20, Math problem 20. The Mowry Machine Shop still has five jobs to be pro- cessed as of 8 A.M. today (day 23) at its bottleneck opera- tion. The day when the order arrived, processing time, and promised due dates are given in the following table. The jobs are listed in the order of arrival. Time Since Order Arrived (days ago) Processing Time (days) Due Date (days from now) Job А 11 10 22 10 8 В 13 8...

  • Processing times and due dates of 9 ¡obs are given as follows: Job Proc Time Due...

    Processing times and due dates of 9 ¡obs are given as follows: Job Proc Time Due Date 9 10 38 15 43 35 40 25 20 40 Assume that all jobs arrive at time 0 a) (3 points) Generate a schedule that minimizes the mean flow time. Break ties with the smallest job number first (i.e, if 3 and 8 have identical parameters, 3 should be scheduled first). b) (3 points) Calculate mean flow time, mean tardiness, and maximum tardiness...

  • You have 5 jobs to process. If you process them in the current order, what will...

    You have 5 jobs to process. If you process them in the current order, what will be the average tardiness for the five jobs? Job А Processing Time Days Due from Today 16 24 20 16 22 40 12 17 10 с D E 18 26.4 28.0 35.4 30.6 23.2

  • 4. [10 points] Today is Nov 15. The following jobs need to be scheduled on the...

    4. [10 points] Today is Nov 15. The following jobs need to be scheduled on the same machine. Job Processing Time (Davs) Due Date Nov 30 Dec 22 Nov 18 Dec 3 Nov 29 12 a. Schedule the jobs according to i. Shortest processing time ii. Earliest due date. iii. Longest processing time. b. For the SPT& EED schedules from part a, calculate the average completion time.

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT