Question on Project 2, Steps. Help. Thanks

Question on Project 2, Steps. Help. Thanks Provide ALL possible paths for the completion of the...
1. Calculate total time required to complete each path. Determine the Critical Path(s). Complete the table by indicating the Critical Path (CP), the amount of slack and whether the task is a milestone. Task Predecessors Duration CP (Yes/No)? Slack (Amount)? Milestone? PROJECT 2 A2 - 1 B2 A2 2 C2 A2 2 D2 B2, C2 3 E2 D2 2 F2 D2 3 G2 E2,F2 2 2. Draw a PERT (Network) chart for PROJECT 2. 3. Draw a...
Please show me the answer and how to place it on a spreadsheet. Thanks. 13.7 Table EX 13.7 shows the precedence relationships among the activities to complete a project. Table EX 13.7 Activity Predecessor Duration (Weeks) A – 6 B – 2 C A 4 D B 5 E B 2 F C, D 4 G C, D 7 H E, G 5 I F 4 Construct an activity on node network for the project. Identify the paths and path...
5.) Consider a project whose activities are listed in the table below. Activity A will have slack time as long as… Activity Immediate Predecessors A None B None C A D B E C, D F E G E a. Duration of A < Duration of B b. Duration of A + Duration of C > Duration of B + Duration of D c. Duration of A + Duration of C < Duration of B + Duration of D...
Please help me answer all the questions. Please show work so I
can understand the process. Thanks! (:
Problem #1 (8 points) 41 Given a table of activities associated with a project, their durations and preceding activities: activityDuration Precedes ol ne : A (start) 1 wks B,C D.E F.G 1 wk 3 wks 2 wks 1 wk 1 wk 2 wks 2 wks 2 wks (end) 2 points Draw an Activity on Nodes (AoN) diagram of the project, including activity...
Consider the following project, all durations are in days. Find the critical path and which tasks have slack. What is the probability the project will be done in 50 days? How about in 53 days? Suppose any task can be crashed for up to two days for the same cost per day, but that tasks A and N cannot be crashed at all. Which tasks should be crashed if the project needed to be completed in 45 days with at...
QUESTION 9 Consider the following project; for which activities is it possible that the slack can be greater than zero? Activity Immediate Predecessors B, E a. Only activities B or E could have slack, but they could not both have slack. Ob. Only activities B or C could have slack, but they could not both have slack. Oc. It is possible for any or all activities in this project to have slack. Od. It is possible for either all three...
2) The following tasks been assigned for a project following the steps needed to develop a project network. Show al necessary steps and graphical representations. Find: 1 Critical Path for this project 2) Total free slack times for each activity 3) Total completion Time 4) The latest time that the activity D must be started to complete the project by day 54 Activity Predecessor Activity Time A |None None M,L.K 3) How would you calculate the duration of an activity...
question 3.12
Chapter 3 Project Management 91 Table for 3.8 Time Activity Immediate Code Description in hours) Predecesur Planning Find location determine resource requirements Purchasing Requisition of lumber and sand Excavation Planning Dig and grade Sawing Planning Saw lumber inte appropriate sizes Placement Purchasing Position lumber in comect locations Sawing. c om Assembly Nail lamber together Placement Tafill Put sand in and under the equipment Ambly Outfill Put dirt a nd the equipment Assembly Decoration Put grass all over the...
QUESTION 1
Part1. The total expected project completion time is:
A. 10 days
B. 11 days
C. 15 days
D. none of the above
Part 2. What is the effect of a delay of 1 day in distributing
tickets?
A. no impact
B. the project will delay by one day
C. the project will delay by more than one day
D. same as the effect of a delay of 1 day in setting up radio
ads
Part 3. What is...