What is the critical path for the network below?

End

0 0
Add a comment Improve this question Transcribed image text
Answer #1

This project has three network paths

Path 1= Start -B-G-I-End = 4+8+ 6 = 18

Path 2= start-A-C-E-H-End = 6+4+6+5 = 21

Path 3 = Start-A-D-F-H-End = 6+5+6+5 = 22

The critical path in this network is start - A-D-F-H-End with the path value of 22.

Add a comment
Know the answer?
Add Answer to:
What is the critical path for the network below? End
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT