ANSWER 1:
The activities on the critical path are A - B - F
ANSWER 2:
The total project completion time is 13 weeks.
ANSWER 3:
The slack time for each activity is:
A - 0
B - 0
C - 1
E - 1
F - 0
(Calculations are provided below)
![11,1] 0,0] @ B8) (3,13) AB) 237 F) C (②) (4) 6,7)](http://img.homeworklib.com/questions/0d1612a0-d785-11ea-9726-b1106bb0e92f.png?x-oss-process=image/resize,w_560)
The above network diagram shows the activities along with their duration, early start time, and latest finish time. The nodes have been numbered for better understanding. The numbers writtn above each node n the form of (a, b) denote the early start time (here, denoted by 'a') and late finish time (here, denoted by 'b'). For example, (6, 7) is written above node 3. Here, '6' denotes early start time and '7' denotes late finish time. The early strat time and late finish time have been computed as per the forward pass and backward pass techniques.
| Activity | Start Node | End Node | Duration | Early Start | Late finish | Early Finish | Late start | Slack |
| A | 1 | 2 | 3 | 0 | 3 | 3 | 0 | 0 |
| B | 2 | 4 | 8 | 3 | 11 | 11 | 3 | 0 |
| C | 2 | 3 | 3 | 3 | 7 | 6 | 4 | 1 |
| E | 3 | 4 | 4 | 6 | 11 | 10 | 7 | 1 |
| F | 4 | 5 | 2 | 11 | 13 | 13 | 11 | 0 |
The formulas used for the above calculations:
1. Early Finish = Early Start + Duration
For example, for Activity A, Early Finish = 0 + 3 = 3
2. Late Start = Late Finish - Duration
For example, for Activity B, Late Start = 11 - 8 = 3
3. Slack = Late Start - Early Start
For example, for Activity C, Slack = 4 - 3 = 1
Similarly, the rest have been computed.
CRITICAL PATH:
The activities which have zero slack are critical activities. The critical activities make up the critical path. Thus, the critical path for this case is:
A - B - F
The total project completion time is computed by adding the duration of the critical activities. Thus the total project completion time:
= 3 + 8 + 2
= 13 weeks
The total project completion time is 13 weeks.
The following is a table of activities associated with a project at Rafay Ishfaq's software firm...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what adivities each must precede Activity Duration (weeks) Precedes A (start) Fendi This exercise contains only parts and d. b) The activities on the critical path are c) The total project completion time for Rafay Ishlad's software firm is weeks. (Enter your response as a whole number) d) Determine the slack time for each of the activities. (Enter your...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Duration(Weeks) Activity Precedes 3 A(start) В.С В 2 5 C F E 2 F F(end) b- The activites on the critical path are: A C- F c- The total project completion time for Rafay Ishfaq's software firm is weeks. d- Determine the slack time for each of the activities. e- What is the total...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Activity Duration (weeks) Precedes A (start) 2 B, C B 2 E C 6 F E 3 F F (end) 4 — This exercise contains only parts b, c, and d. b) Define the critical path, listing all critical activities in chronological order. Critical path activities are the activities that lie on the longest...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Duration (weeks) Activity A (start) Precedes B, C Crash Cost/Week $400 $100 $200 $300 $400 F F (end) 2 Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how many weeks should each activity be crashed in order to...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Activity Duration (weeks) Precedes Crash Cost/Week A (start) 2 B, C $ 370 B 2 E $ 130 C 4 F $ 200 E 1 F $ 150 F (end) 2 — $ 420 Suppose that Rafay is only given 5 weeks (instead of 8) to...
Problem 3.28 - Bookmatch Problem The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Activity Duration (weeks) Precedes Crash Cost/Week A (start) 11 B, C $ 400 B 11 E $ 100 C 44 F $ 200 E 22 F $ 300 F (end) 22 long dash— $ 400 Suppose that Rafay is only given...
Suppose that Rafay is only given 7 weeks (instead of 10) to
complete the project . By how many weeks should each activity be
crashed in order to meet the deadline? Assume that you can crash an
activity down to 0 weeks duration.
Activity
Each Activity Should be Reduced BY (weeks)
A
(weeks)- ?
B
(weeks)- ?
C
(weeks)- ?
D
(weeks)- ?
E
(weeks)- ?
F
(weeks)- ?
What is the total crashing cost ?
The following is a...
5.) Consider a project whose activities are listed in the table below. Activity A will have slack time as long as… Activity Immediate Predecessors A None B None C A D B E C, D F E G E a. Duration of A < Duration of B b. Duration of A + Duration of C > Duration of B + Duration of D c. Duration of A + Duration of C < Duration of B + Duration of D...
The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) A 2 3 2 B с D E F 4 A B B с DE E 1 3 G 2 Determine the amount of slack time for Activity E Ola. O weeks b. 1 week c. 2 weeks d. 3 weeks
A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...