Early Start (ES), Early Finish (EF), Late Start (LS), and Late Finish (LF) for each activity can be computed using the following formulae.
ES of the starting activities =
0
ES of all other activities = Max. (EF of their immediate
predecessors)
EF of an activity = Its ES + Its duration
LF of ending activity = Max. (their
EF)
LF of all other activities = Min. (LS of their immediate
successors)
LS of an activity = Its LF - Its duration
Slack = LF - EF
| Activity | Predecessors | Successors | Duration | ES | EF | LS | LF | Slack |
| A | - | B, C | 3 | 0 | 3 | 0 | 3 | 0 |
| B | A | E | 2 | 3 | 5 | 4 | 6 | 1 |
| C | A | F | 5 | 3 | 8 | 3 | 8 | 0 |
| E | B | F | 2 | 5 | 7 | 6 | 8 | 1 |
| F | C, E | - | 3 | 8 | 11 | 8 | 11 | 0 |
The critical path is constituted of activities with zero slack.
(b) Activities on the critical path are A-C-F
(c) The total completion time for the project = 11 weeks
(d) and (e)
| Activity | Slack |
| A | 0 |
| B | 1 |
| C | 0 |
| E | 1 |
| F | 0 |
The following is a table of activities associated with a project at Rafay Ishfaq's software firm...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Activity A (start) B с E F(end) Duration (weeks) 3 8 3 4 Precedes B, C F E F 2 This exercise contains only parts b, c, and d. b) The activities on the critical path are A-B-F c) The total project completion time for Rafay Ishfaq's software firm is 13 weeks. (Enter your...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what adivities each must precede Activity Duration (weeks) Precedes A (start) Fendi This exercise contains only parts and d. b) The activities on the critical path are c) The total project completion time for Rafay Ishlad's software firm is weeks. (Enter your response as a whole number) d) Determine the slack time for each of the activities. (Enter your...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations and what activities each must precede: Activity Duration (weeks) Precedes A (start) 2 B, C B 2 E C 6 F E 3 F F (end) 4 — This exercise contains only parts b, c, and d. b) Define the critical path, listing all critical activities in chronological order. Critical path activities are the activities that lie on the longest...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Duration (weeks) Activity A (start) Precedes B, C Crash Cost/Week $400 $100 $200 $300 $400 F F (end) 2 Suppose that Rafay is only given 5 weeks (instead of 7) to complete the project. By how many weeks should each activity be crashed in order to...
The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Activity Duration (weeks) Precedes Crash Cost/Week A (start) 2 B, C $ 370 B 2 E $ 130 C 4 F $ 200 E 1 F $ 150 F (end) 2 — $ 420 Suppose that Rafay is only given 5 weeks (instead of 8) to...
Problem 3.28 - Bookmatch Problem The following is a table of activities associated with a project at Rafay Ishfaq's software firm in Chicago, their durations, what activities each must precede and the crash cost to reduce duration per week: Activity Duration (weeks) Precedes Crash Cost/Week A (start) 11 B, C $ 400 B 11 E $ 100 C 44 F $ 200 E 22 F $ 300 F (end) 22 long dash— $ 400 Suppose that Rafay is only given...
Suppose that Rafay is only given 7 weeks (instead of 10) to
complete the project . By how many weeks should each activity be
crashed in order to meet the deadline? Assume that you can crash an
activity down to 0 weeks duration.
Activity
Each Activity Should be Reduced BY (weeks)
A
(weeks)- ?
B
(weeks)- ?
C
(weeks)- ?
D
(weeks)- ?
E
(weeks)- ?
F
(weeks)- ?
What is the total crashing cost ?
The following is a...
QUESTION 14 A firm is planning a project for the development of a new product. The network of activities and data are shown follow. Time Immediate Activity (weeks) Predecessor 2 5 В 4 C 5 В 6 В.С D,E F What are the slack times of Activities D and E? 0 and 0, respectively 1 and 1, respectively 2 and 0, respectively 0 and 1, respectively 1 and 0, respectively shown follow. A firm is planning a project for the...
5.) Consider a project whose activities are listed in the table below. Activity A will have slack time as long as… Activity Immediate Predecessors A None B None C A D B E C, D F E G E a. Duration of A < Duration of B b. Duration of A + Duration of C > Duration of B + Duration of D c. Duration of A + Duration of C < Duration of B + Duration of D...
A Question 11 The following table provides a list of activities in a project, along with their respective durations and precedence requirements: Immediate Duration Activity Predecessor(s) (weeks) 2 B 3 C B D А E A.C 1 F DE 3 с 3 2 6 G Determine the amount of slack time for Activity E: a. O weeks b. 1 week C. 2 weeks O d. 3 weeks Question 12 Assume that activity A has the following times: Early start time...