Question

3. Using the project information below, draw the AON diagram, complete forward and backward pass, and identify the critical p
0 0
Add a comment Improve this question Transcribed image text
Answer #1

The AON diagram is provided in the attached picture. Each box represents an activity with its name and duration written within the box and all four corners, i.e, Top left, top right, bottom left and bottom right have the information about Early start, Easrly Finish, Laste start and Late finish respectively. Same symbolic representatin is described in the picture too.

All the forward and backward calculations are mentioned as described above on each activity box.

The Critical path has double arrows. ABEFG is the critical path. Critical path is the longest duration path amongst all the available paths. On critical path, Early start of Each node is equal to Late start and Early finish of each node is equal to Late finish.

F.S+5 13 13 14 An - 13 To s.st5 I WV fifth 3 10 Ες . UU duration Es: Early steht - Activity Ef: Early frush Ls: hate start Lf

Add a comment
Know the answer?
Add Answer to:
3. Using the project information below, draw the AON diagram, complete forward and backward pass, and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • From the following information, develop an AON project network. Complete the forward and backward pass, compute...

    From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? ID Description Predecessor Time A Survey site None 3 B Excavate site A 5 C Install power lines B 2 D Install drainage B 5 E Pour foundation C, D 4 The project will take _ days. The critical path is _ The late start on Activity C is _...

  • Please use the information below to draw and solve the network on a piece of paper...

    Please use the information below to draw and solve the network on a piece of paper by: • Complete the forward and backward pass • Identify the critical path Fill in the requested information (Example: ESA - Early Start of Activity A; LFA - Late Finish of Activity A, etc) Duration 3 Predecessor Relationship N 2 - Activity Activity ID Contract sign A Survey Target market C Data collection Presentation Analyze results Demographics G Closing H FS Lag 3 N...

  • 1. For the following schedule, Draw the AON network diagram for the project and calculate the...

    1. For the following schedule, Draw the AON network diagram for the project and calculate the schedule. а. Summarize the schedule in a tabular form, showing ES, EF, LS, LF, TF, and FF for each activity b. Denote the critical path on the network. C. d. Perform a cost analysis based on an early start, late start, and target schedule for the project. Plot the cumulative cost distribution for the three S-curves on one graph. e. f. Plot the cumulative...

  • QUESTION 1 Please use the information below to draw and solve the network on a piece...

    QUESTION 1 Please use the information below to draw and solve the network on a piece of paper by: Complete the forward and backward pass Identify the critical path Fill in the requested information (Example: ESA Early Start of Activity A; LFA Late Finish of Activity A, etc) Relationship Activity Contract sign Predecessor Activity ID Duration 3 А Survey В 2 А Target market C Data В,С D 7 collection Presentation 2 FS Lag 3 E В Analyze F 2...

  • Assignment for week 5 Given the following information, draw the project network

    Assignment for week 5Given the following information, draw the project network. Compute the early, late and slack times for the project network. which activities are on the critical path have only the start or finish of the activity on the critical path?ID duration finish to start finish to start additional lag lag predecessor lag Relationship A 2 none 0 none 0B 4 A 0 none 0C 6 A 0 finish-finish C to F 7D 8 A 0 none 0E 18...

  • A project manager discovers that his team has neglected tocomplete the network diagram for the...

    A project manager discovers that his team has neglected to complete the network diagram for the project. the network diagram is shown below. however the project manager has some information available, specifically that each activity a-g, has a different duration between one and seven weeks. also the slack time for each of the activity is known as shown belowDuration (weeks): 1,2,3,4,5,6,7 Slack time (weeks): 0,0,0,1,1,3,7 A D E G B FINISH START C F Using the clues provided below, determine...

  • ASSIGNMENT- Scheduling a. Draw the EARLY start Gantt chart and state the critical activities b. Draw...

    ASSIGNMENT- Scheduling a. Draw the EARLY start Gantt chart and state the critical activities b. Draw the LATE start Gantt chart c. Draw the AON chart - Forward pass d. Draw the AON chart - Backward pass e. Identify the critical path from the table (follow ppt/notes) MUST BE DONE NEATLY! ACTIVITY WEEKS PRECEDENCE A B с D E F 3 4 5 7 2 4 3 A B B E C,D GF H

  • 1. Given the major activities and their duration for a building project as follows: Activity DurationSuccessors...

    1. Given the major activities and their duration for a building project as follows: Activity DurationSuccessors B,C D,E,F HI,J K,L L,M K,L 10 4 (a) Draw the precedence network. (b) Calculate the EST, EFT, LST and LFT of each activity using the forward pass and backward pass methods entire project about a delay of the activity D by 3 days? (Remark: please redraw the diagram to verify (c) Highlight/identify the critical path in the precedence network and find the duration...

  • Consider the project network information in Table 1 of Case Study A on Page 3 below....

    Consider the project network information in Table 1 of Case Study A on Page 3 below. Assuming the project starts at time zero and all activity connections are finish-to-start, draw an Activity on the Node (AON) network diagram of the project, determine the expected project completion time, state the critical activities and critical path(s). Crash the project by 1 week and state the total crash cost. (b) (18 nar Case Study A Table 1 below contains activities associated with a...

  • Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the...

    Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the critical path. (3 points) (b) What is the project duration? ( points) (c) What is the slack time of activity F? ( points) Q4 The network diagram of a project is shown below E.4 B.3 G.5 D.5 A.7 F.2 C.4 (a) Use two-pass method to determine the critical path. (3 points) (b) What is the project...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT