Question

A piece of property is 100 ft by 100 ft. The owner wants to build brick...

A piece of property is 100 ft by 100 ft. The owner wants to build brick wall around the property on four sides. The owner asks her son (project manager) to handle the project. The project manager plans to hire one person to build one side of wall a week. According to the project      manager’s plan, it will take one person four weeks to finish the project. It’s estimated to cost $500 labor a week and $500 materials to build one side of wall.

Once the project starts, the project manager finds out that it actually takes the person 1.5 weeks and $600 materials to build the first side of wall.

Calculate CPI, SPI, BAC, and EAC of the project. (20 points)

How do you provide a status report to the owner if you are the project manager?

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Answer:

1)

Given the size of the property asIkrJyJAAAAAElFTkSuQmCC.

Estimated cost of the labor per week is $500.

Cost of materials to build one side of the wall is $500.

According to estimation, the Project Value by the end of the week given as,

            xYAAMEFAAAEFwAAwQUAuMP8D5c7QSDWkTQ+AAAAA

Therefore, the estimated project value is $10000.

Once the project started, by the end of constructing one side of the wall took about 1.5 weeks and the cost of material as $600.

So, the Earned Value to construct one side of wall in one and half week is given as,

            2keiuP72chvnVS6S3y5h4AAMTyqIn9vhIAAODeiy

Therefore, the earned value by the end of 1.5 weeks is $10000.

The Earned Value for end of week is given as,

             1qooCzbL8bA0YyRW30q4nGrLn63VBzZvMRoVYGgv

Therefore, the earned value by the end of 1 week is $900.

The schedule performance index SPI is given as,

            B3tbDn80M4BwEdtBxAAf4T2D6Pps8iRpwuYAAAAA

Therefore, SPI = 0.9.

The cost performance index is given as,

             17ADgE4BCAQwAOATgE4AAOATgE4BCAQwA+skLLbf

Therefore, CPI = 0.9.

The cost of budget at completion of project is BAC is given as,

             EkG5hjToG6TQBIAQAgBQCAFABwMPwHj38y+jQFuo

Therefore, BAC=$40000.

The estimation at completion EAC is given as,

             QeQAmTqh1mExgAAAABJRU5ErkJggg==

Therefore, EAC=$44444.44.

2)

Project Report:

Report

Calculations

Substitution of values

Final values

Project planned cost by the end of one week:

Material cost + Labor cost

$500 + $500

$10000.00

Project actual cost by the end of one week:

Material cost + labor cost

$400 + $500

$    900.00

Project delay time:

One and half week * 4 - 1 week *4

1.5*4-1*4

2 weeks

Overhead of Project value:

$500*6 + $600*4

$ 5400.00

Add a comment
Know the answer?
Add Answer to:
A piece of property is 100 ft by 100 ft. The owner wants to build brick...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Question 1: The following data and table illustrate a small project: Activity A was completed on...

    Question 1: The following data and table illustrate a small project: Activity A was completed on schedule • Activity B started as planned but it is expected to take four weeks more Activity C started as planned but finished one week later • %age of completion of activity D is 60% ACWP at the end of week 10 = SR 90400 Activity Original Planned Start Time Original Planned Finish Time Wage Complete Amount Completed BCWP Amount Scheduled BCWS Amount Spent...

  • At week 10 of a project below to improve distance learning platform, assume that the planned...

    At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks. ACTIVITY PRE- DECESSORS DURATION (WEEKS) BUDGET ($) ACTUAL COST ($) % COMPLETE A - 5 500 640 100 B A 3 300 400 100 C B 4 320 310 80 D B 6 600 250 60 E C,D 3 300...

  • please answer #2 The Stratton Township Park The Stratton Township Park is located on a piece...

    please answer #2 The Stratton Township Park The Stratton Township Park is located on a piece of property that contains two golf courses, a swimming pool, and 800 acres of woods and open spaces. Three years ago, the Stratton Parks Department (Stratton) carved out miles of trails to allow visitors to hike the property and enjoy nature. To make that experience more enjoyable for visitors and available to school groups, Stratton decided to offer guided tours that have proven popular....

  • please answer #5 The Stratton Township Park The Stratton Township Park is located on a piece...

    please answer #5 The Stratton Township Park The Stratton Township Park is located on a piece of property that contains two golf courses, a swimming pool, and 800 acres of woods and open spaces. Three years ago, the Stratton Parks Department (Stratton) carved out miles of trails to allow visitors to hike the property and enjoy nature. To make that experience more enjoyable for visitors and available to school groups, Stratton decided to offer guided tours that have proven popular....

  • please answer question #4 The Stratton Township Park The Stratton Township Park is located on a...

    please answer question #4 The Stratton Township Park The Stratton Township Park is located on a piece of property that contains two golf courses, a swimming pool, and 800 acres of woods and open spaces. Three years ago, the Stratton Parks Department (Stratton) carved out miles of trails to allow visitors to hike the property and enjoy nature. To make that experience more enjoyable for visitors and available to school groups, Stratton decided to offer guided tours that have proven...

  • CASE 7: RELEVANT COST ANALYSIS (CICA) Fence Company Ltd. (FC) was incorporated in March 20X4, and...

    CASE 7: RELEVANT COST ANALYSIS (CICA) Fence Company Ltd. (FC) was incorporated in March 20X4, and is equally owned by Robert and Morris Wood. The company constructs residential wood fences. FC's first year was a difficult one. It is now late March 20X5, and the Wood brothers are making plans to improve FC's performance. Having decided that they need outside advice, they asked you to meet with them. At the meeting, you asked the brothers to describe their operations and...

  • You might be familiar with Crazy Eddy, an owner of the “Crazy Eddy’s” home electronics stores...

    You might be familiar with Crazy Eddy, an owner of the “Crazy Eddy’s” home electronics stores that used to exist when you were younger (though maybe too young to remember). Some of the larger superstores like Best Buy and Circuit City moved in and began squeezing Eddy. As it turned out his tagline, “where the prices are insane,” was quite true, and he was forced out of business. Unbeknownst to many, Eddy was an avid skier, and his desire to...

  • What an Executive Summary Is An executive summary is a specific type of document that does...

    What an Executive Summary Is An executive summary is a specific type of document that does two things: it summarizes a research article, and it offers recommendations as to how information from the article can be used. Some long reports can contain an executive summary section, as indicated in the Pearson handbook. Write a 2 pahe Executive Summary In business contexts, an executive summary is always written for a specific purpose: to explain the information in the article to a...

  • ABC Company - Biographical Information ABC Company is a family owned business which Jonathan started 15...

    ABC Company - Biographical Information ABC Company is a family owned business which Jonathan started 15 years ago, issuing 900 shares of the 1000 authorized, at a par value of $100 a share. ABC Company is a small manufacturer which produces ladies’ sports apparel. The business has employed as many as 30 people; however, sales have slipped the last three years, according to Jonathan, due to competition in the marketplace, and the economy. Currently, the business employs nine people, including...

  • Select two of the discussion questions and analyze the case study using project management principles. Apply...

    Select two of the discussion questions and analyze the case study using project management principles. Apply your knowledge of project management to the facts presented in the case study to describe how you would proceed. We only need to answer one of the questions. A thorough answer will probably require 300 to 500 words for each question.   Feel free to use text bullets, tables, or graphics to summarize your points. Questions Q1: Make or Buy decision – Describe the make...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT