Question

For the following precedence relationship, answer questions 5 thru 9. Activity Preceding Activity Optimistic Time (weeks) 10

Areas Under the One-Tailed Standard Normal Curve This table provides the area between the mean and some score For example, wh

0 0
Add a comment Improve this question Transcribed image text
Answer #1

First, we need to calculate the mean time for the activities. Following formula can be used to calculate the mean time

= (t +4, +) where. t = Mean Time to = Optimistic Time t = Most Likely Time t = Pessimistic Time

Activity Optimistic Time Most Likely time Pessimistic time Mean Time N CUI NON MOON N CONNU

The precedence relationship diagram is as follows:

ED=28 Lo=28 EF=36 LE = 36 EA = 21 LA =21 B Dit Ea=38 pha=38 A = 28 tc=28 28 JE Eq=33 Lq=36 Critical paths is A - B - Daf - G

As per the network diagram:

5. The project duration for the above project is 38 weeks

6. The slack for activity C is 0 weeks because this activity comes on the critical path.

7. The critical path for the above projects are:

a) A-B-D-F-G

b) A-C-F-G

8. Following formula can be used to calculate the probability in less than 35 weeks

1586906610745_image.png

where,

Ts = Target Value

Te = Mean completion time

o = Standard Deviation

To calculate the standard deviation, first variance needs to be calculated for critical path.

1586906771661_image.png

Activity Optimistic Time Most Likely time Pessimistic time Mean Time Variance NC UNAN NEW 7 2.777778 2 0.111111 5 1.777778 8

o = Sum of Critical path Variances o = 11.889 o=3.44

DZI.-I, 35-38 = Prob.{Z S-0.8720}=0.1916 o 3.44

Therefore, the probability of finishing the project in less than 35 weeks is 19.22 percent

9. By referring the precedence network diagram:

The slack for activity E is 36-33 = 3 weeks

Heyy! Please hit thumbs up. If you like the answer. Thanks

Add a comment
Know the answer?
Add Answer to:
For the following precedence relationship, answer questions 5 thru 9. Activity Preceding Activity Optimistic Time (weeks)...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Assume the hold time of callers to a cable company is normally distributed with a mean...

    Assume the hold time of callers to a cable company is normally distributed with a mean of 5.0 minutes and a standard deviation of 0.6 minute. Determine the percent of callers who are on hold at least 5.2 minutes. _______% Use Standard Distribution Table Z 0.00 0.01 0.02 0.03 0.04 0.05 0.06 0.07 0.08 0.09 0.0 0.0000 0.0040 0.0080 0.0120 0.0160 0.0199 0.0239 0.0279 0.0319 0.0359 0.1 0.0398 0.0438 0.0478 0.0517 0.0557 0.0596 0.0636 0.0675 0.0714 0.0753 0.2 0.0793 0.0832...

  • SCENARIO A Answer the questions in the following scenario. Be sure to show all your working....

    SCENARIO A Answer the questions in the following scenario. Be sure to show all your working. The scenario is for the 2017/18 financial year. You will need to refer to the Australian Taxation Office’s (ATO’s) website for the tax rates and the medicare levy. Include the URL reference or a screen shot to demonstrate the information you obtained. Stevie Slick is a real estate agent. She earn $583 per week plus a commission of 0.5% on properties she sells. In...

  • 1. What percentage of the general population have deviation IQs higher than 115?

    1. What percentage of the general population have deviation IQs higher than 115?                                                           Appendix AAreas under the standard normal curveArea between 0 and z0.000.010.020.030.040.050.060.070.080.090.00.00000.00400.00800.01200.01600.01990.02390.02790.03190.03590.10.03980.04380.04780.05170.05570.05960.06360.06750.07140.07530.20.07930.08320.08710.09100.09480.09870.10260.10640.11030.11410.30.11790.12170.12550.12930.13310.13680.14060.14430.14800.15170.40.15540.15910.16280.16640.17000.17360.17720.18080.18440.18790.50.19150.19500.19850.20190.20540.20880.21230.21570.21900.22240.60.22570.22910.23240.23570.23890.24220.24540.24860.25170.25490.70.25800.26110.26420.26730.27040.27340.27640.27940.28230.28520.80.28810.29100.29390.29670.29950.30230.30510.30780.31060.31330.90.31590.31860.32120.32380.32640.32890.33150.33400.33650.33891.00.34130.34380.34610.34850.35080.35310.35540.35770.35990.36211.10.36430.36650.36860.37080.37290.37490.37700.37900.38100.38301.20.38490.38690.38880.39070.39250.39440.39620.39800.39970.40151.30.40320.40490.40660.40820.40990.41150.41310.41470.41620.41771.40.41920.42070.42220.42360.42510.42650.42790.42920.43060.43191.50.43320.43450.43570.43700.43820.43940.44060.44180.44290.44411.60.44520.44630.44740.44840.44950.45050.45150.45250.45350.45451.70.45540.45640.45730.45820.45910.45990.46080.46160.46250.46331.80.46410.46490.46560.46640.46710.46780.46860.46930.46990.47061.90.47130.47190.47260.47320.47380.47440.47500.47560.47610.47672.00.47720.47780.47830.47880.47930.47980.48030.48080.48120.48172.10.48210.48260.48300.48340.48380.48420.48460.48500.48540.48572.20.48610.48640.48680.48710.48750.48780.48810.48840.48870.48902.30.48930.48960.48980.49010.49040.49060.49090.49110.49130.49162.40.49180.49200.49220.49250.49270.49290.49310.49320.49340.49362.50.49380.49400.49410.49430.49450.49460.49480.49490.49510.49522.60.49530.49550.49560.49570.49590.49600.49610.49620.49630.49642.70.49650.49660.49670.49680.49690.49700.49710.49720.49730.49742.80.49740.49750.49760.49770.49770.49780.49790.49790.49800.49812.90.49810.49820.49820.49830.49840.49840.49850.49850.49860.49863.00.49870.49870.49870.49880.49880.49890.49890.49890.49900.49902. What proportion of the normal curve lies between a Z-score of -2.50 and a Z-score of 1.50?3. What proportion of the scores in a normal distribution are higher than a T-score of 70?4. What Z-score has 90% of the scores below it?5. What deviation IQ score ranges would include 90% of the population?

  • QUESTION 1 (15 marks) Studd Enterprises sells big-screen televisions. A concern of management is the number...

    QUESTION 1 (15 marks) Studd Enterprises sells big-screen televisions. A concern of management is the number of televisions sold each day. A recent study revealed the number of days that a given number of televisions were sold. # of TV units sold #of days Answer the questions below. For each part, show your calculations and/or explain briefly how you arrived at your answer, as appropriate or needed. Required: a. Convert the frequency distribution above into a probability distribution (or relative...

  • Question No: 3 (a) A factory produces 2.5% of defective items.If a sample of 200 items...

    Question No: 3 (a) A factory produces 2.5% of defective items.If a sample of 200 items is taken at random from the production. What is the probability that there will be at least four collision in a week? (2 Marks) 50,where t (b) The failure distribution function F(t) of a building system is given F(t) = 1-e is in years. Determine the following: (i) The system will last more than 6 years (ii) hazard function h(t) (3 Marks) (C) A...

  • A network consists of the following list. Times are given in weeks. Activity Preceding Time (weeks)...

    A network consists of the following list. Times are given in weeks. Activity Preceding Time (weeks) Activity Predecessor Duration A 4 B 9 C A 5 D B A 3 E D C 4 Calculate the ES, EF, LS, LF, slack for each activity. List the critical activities for this project.

  • CRA CDs Inc. wants the mean lengths of the “cuts” on a CD to be 170...

    CRA CDs Inc. wants the mean lengths of the “cuts” on a CD to be 170 seconds (2 minutes and 50 seconds). This will allow the disk jockeys to have plenty of time for commercials within each 10-minute segment. Assume the distribution of the length of the cuts follows a normal distribution with a standard deviation of nine seconds. Suppose that we select a sample of 16 cuts from various CDs sold by CRA CDs Inc. Use Appendix B.1 for...

  • A project for improving a billing process has the following precedence relationships and activity times: Activity...

    A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) B, C I Q7 Moow E F, G b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Yes Slack (weeks) D 0 Yes 0 0 00000000 @ Tm I

  • The following table shows estimates of activity times (weeks) for a project: Activity Optimistic Time Most...

    The following table shows estimates of activity times (weeks) for a project: Activity Optimistic Time Most Probable Time Pessimistic Time A 3 4.5 9 B 1.5 2 2.5 C 5 6 7 D 4 4.5 8 E 5 6 7 F 1 2.5 7 G 7 9 11 Suppose that the critical path is A-B-D-F-G. Use Appendix A to answer the questions. Do not round intermediate calculations. Round your answers to three decimal places. What is the probability that the...

  • Problem 3 A project for improving a billing process has the following precedence relationships and activity...

    Problem 3 A project for improving a billing process has the following precedence relationships and activity times: Activity Time (weeks) Activity Immediate Predecessor(s) A В 7 C 7 A В, С D 14 Е 10 5 D E Н F, G a. Choose the correct network diagram below. O A. O B. в O C. O D. S в Problem 3 Question Help O D. O C b. Calculate the slack for each activity. Which activities are on the critical...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT