Explain step by step
Golden Oldies is a small company that burns music CDs for non-technical senior citizens. The table below contains information on the steps required to burn and package a CD. (Their equipment is quite old, hence, the long burn time.) No specific demand numbers are available, however, the cycle time should not exceed 30 minutes in order to meet demand requirements.
| Task | Description | Req'd Time (in minutes) | Predecessor |
|---|---|---|---|
| A | Set up equipment | 10 | None |
| B | Test equipment | 12 | A |
| C | Select songs | 26 | None |
| D | Burn CD | 15 | B, C |
| E | Package CD | 6 | D |
(Missing questions from prior question)
Given your task assignments to workstations, what is the actual number of workstations required?
What is the cycle time (in minutes) for this production
line?
What is the combined idle time (in minutes) for this production line?
What is the overall efficiency for this production line? (Write
your answer as a percentage, and display your answer to
two decimal places.)
Number of workstations will be 3, because the cycle time should not increase 30 sec. and the task time of 69 can be accommodated in minimum 3 workstations.
Cycle time = 26 sec, which is equal to the time taken by longest task.
Idle time for the production line = (26x3) -69 =9 sec. per cycle.
Efficiency of the production line = 69/3x26 = 0.8846
Explain step by step Golden Oldies is a small company that burns music CDs for non-technical...
The operations manager of an instruments company is balancing an
assembly line. The company needs to build 96 instruments per
24-hour day. The assembly line activities are:
a. Draw the precedence diagram.
b. If the daily (24-hour) production rate is 96 units, what is
the greatest possible cycle time?
c. If the cycle time after allowances is given as 10 minutes,
what is the daily (24-hour) production rate?
d. With a 10-minute cycle time, what is the theoretical minimum
number...
Your scientists have perfected Harry Potter's invisibility cloak and are ramping up production. It plans to use this production line sixteen hours a day in order to meet projected demand of 1600 units. The tasks necessary to produce this product are: Task Time (minutes) Predecessor Get Cloth 4 none Get Bat Wings 5 none Boil Toil and Trouble 15.4 none Stir in ingredients 1 Bat Wings & Boil Paint onto Cloth 11.0 Stir & Cloth Package for delivery 2.0 Paint...
... 9.13 Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 50 chairs. There are eight tasks: TASK PERFORMANCE TIME (min) TASK MUST FOLLOW TASK LISTED BELOW A,B F, G a) Draw a precedence diagram of this operation. b) What is...
The Action Toy Company has decided to manufacture a new toy tractor, the production of which is broken into six steps. The demand for the tractor is 4,800 units per 40-hour workweek. TASK, PERFORMANCE TIME(SECONDS), PREDECESSORS A 20 None B 30 A C 15 A D 15 A E 10 B,C F 30 D,E A) Draw a precedence diagram B) What is the cycle time? C) What is the theoretical minimum number of workstations? D) Assign tasks to workstations E)...
3. Illinois Furniture, Inc., produces all types of office furniture. The "Executive Secretary” is a chair that has been designed using ergonomics to provide comfort during long work hours. The chair sells for $130. There are 480 minutes available during the day, and the average daily demand has been 48 chairs. the eight tasks required to produce the chair and the precedence diagram are shown below TASK PERFORMANCE TIME (min) ULUI Precedence diagram a. What is the cycle time for...
QUESTION 37 A company is designing a product layout for a new product. It plans to use this production line eight hours a day in order to meet a schedule of 400 units per day. The tasks necessary to produce this product are detailed in the table below. Task Predecessor Time (seconds) 50 А B А 20 С А 26 D 40 B, C C E 30 a. Draw the network described in the table. b. What is the required...
A small electronics company assembles power supplies for use in computers, printers and FAX machines. They want to set up an assembly line to make their operation more efficient and plan to use line balancing with the incremental utilization heuristic. The demand for power supplies is 200 per hour, and the productive time per hour is 52 minutes. Task Tasks that must immediately preceede time to perform task A - 0.56 B A 0.34 C A 0.11 D A 0.09...
The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4 comma 5004,500 units per 40-hour workweek: Task Performance Time (seconds) Predecessors A 2424 minus− B 3030 A C 1414 A D 1515 A E 1212 B, C F 3030 D, E This exercise only contains parts b, c, d, e, and f. b) Given the demand, the cycle time for the...
Question d) The idle time for the assembly line per cycle =
_____ minute(s)
The Mach 10 is a one-person sailboat manufactured by Creative Leisure. The final assembly plant is in Cupertino, California. The assembly area is available for production of the Mach 10 for 200 minutes per day. (The rest of the time it is busy making other products.) The daily demand is 60 boats. Given the following information: Task Predecessors Performance Time (mins) 2. 1 1 A B...
the maker of the world famous chocolate chip cookies needs to design a product layout for a new product, mint chocolate chip. the company plans to use this new production line eight hours a day in order to meet projected demand of 1,440 cases per day. the following table describes the tasks involved in the production of a mint chocolate chip cookie. Task Predecessor Time (seconds) U ----- 4 V U 14 W V 12 X V 10 Y W...