Question

The following information is provided for the tasks on a project. Times are in days. Task Time Predecessor A 12 B 21 B, C F 1

0 0
Add a comment Improve this question Transcribed image text
Answer #1

CKDG в Possible path | Duration (days) Maximum A-C-D-G-H 12 + 8 + 6+ 5 + 17 = 48 No A-C-E-F-H 12 + 8 + 7 + 15 + 17 = 59 No B-NO I e R т 13 Task Time Early start Early finish Late start Late finish Slack 14 A 12 O =P14+014 1=S14-014 =R16 =S14-Q14 15 BNote: 1. During forward pass if an activity is preceded by multiple activities, then the early start time for that activity w

Slack = Late finish - Early Finish

Na talk to care finish ate store Late finish|slack 13 N O P Q RS 13 Task | Time Early start Early finish Late start |Late fin

Slack is 0 for activities B,F,E,H

Thus, critical path = B-E-F-H

Time to complete the project = Early finish of the activity H = 60 days

Slack for task G = 12 days

Project duration will increase by 2 days i.e. from 60 to 62 if the task A duration increases by 3 days.

Possible path Duration (days) Maximum
A-C-D-G-H (12+3) + 8 + 6+ 5 + 17 = 51 No
A-C-E-F-H (12+3) + 8 + 7 + 15 + 17 = 62 No
B-E-F-H 21 + 7 + 15 + 17 = 60 Yes
Add a comment
Know the answer?
Add Answer to:
The following information is provided for the tasks on a project. Times are in days. Task...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 2. Using the information in Table 1, assuming that the project team will work a standard...

    2. Using the information in Table 1, assuming that the project team will work a standard working week (5 working days in 1 week) and that all tasks will start as soon as possible: Table 1: Project description Task Description Predecessor/s Duration (working days) 5 15 25 15 A B A B с D E F G H Requirement Analysis Systems Design Programming Telecoms Hardware Installation Integration System Testing Training/Support Handover and Go-Live B B 30 CD E, F 10...

  • QUESTION 2 Given the following information, you are to determine the following Project network. Early, late...

    QUESTION 2 Given the following information, you are to determine the following Project network. Early, late and slack activity times. Project duration. Critical path Task Predecessor Duration A None 8 B A 5 C A 10 D A 15 E A 10 F B 12 G C, D 12 H E, 7 I G, H 7 J F,G,I 10 K J 12

  • Consider the following project, all durations are in days. Find the critical path and which tasks...

    Consider the following project, all durations are in days. Find the critical path and which tasks have slack. What is the probability the project will be done in 50 days? How about in 53 days? Suppose any task can be crashed for up to two days for the same cost per day, but that tasks A and N cannot be crashed at all. Which tasks should be crashed if the project needed to be completed in 45 days with at...

  • Given the following information about a small project, Task     Duration         Immediate Estimates        Predecessors A      &n

    Given the following information about a small project, Task     Duration         Immediate Estimates        Predecessors A          2 days              None B          5 days              A C          4 days              B D          9 days              A E          4 days              B & D F          12 days            E & C Draw a network diagram. Identify the critical path, earliest start and finish and slack for each task. Using MS Excel, produce a Gantt chart for this project. What would happen if a new estimate for task D increases...

  • 39. Consider the following project, and answer the next 5 questions based on this data: Task...

    39. Consider the following project, and answer the next 5 questions based on this data: Task ID Duration (Days) Predecessors 2 70 - 3 30 2 4 120 3 5 120 2 6 120 5 7 120 3,6 8 150 3,6 9 115 3,6 10 130 7,9 11 90 7,9 12 30 7,9 13 120 7,9 14 75 10 15 30 14 16 85 6 17 165 16 18 90 16 19 90 17,18 20 20 8,11,13,15,19 What is the...

  • It was determined on the following project that the duration for the tasks contained some uncertainty....

    It was determined on the following project that the duration for the tasks contained some uncertainty. After more research, the optimistic and pessimistic values were determined. 1. a. Calculate the expected time and variance (using the 95 percent level of confidence) for each activity. b. Determine the critical path and time for completion c. Calculate the probably that the project will finish in 30 days. Calculate the probably of completing the project in 27 days. Other than the critical path,...

  • Consider the following data for a project to install a new server at the Northland Pines...

    Consider the following data for a project to install a new server at the Northland Pines High​ School:                                                                                                           Activity Activity Time​ (days) Immediate​ Predecessor(s) A 44 minus− B 55 A C 44 A D 44 B E 11 B F 55 ​B, C G 22 ​D, E H 66 F I 55 F J 88 ​G, H, I a. Choose the correct network diagram below. A. SFB5C4D4F5G2I5H6E1A4J8 x y graph B. SFB5C4D4F5G2I5H6E1A4J8 x y graph C. SFB5C4D4F5G2J8H6E1A4I5 x y...

  • 9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activit...

    9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20 points) Predecessor Duration (Days) Activity A, B C, D F,G 9. Given the following information in the table, construct an activity on the node diagram. Label the critical path as well as the early and late start/finish times and the slack for each activity. (20...

  • Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic...

    Given the following activity list and times in days: (15 points) Activity           Optimistic       Most Likely     Pessimistic                         Time                Time                Time A                     7                      10                    12 B                     6                      8                      14 C                     5                      9                      12 D                     12                    14                    21 E                      10                    12                    15 F                      4                      5                      8 G                     1                      3                      8 H                     12                    15                    17 NOTE 1: ASSUME THE CRITTCAL PATH IS “B-E-H”. Calculate the schedule duration of the critical path in days. What is the probability of the project being completed...

  • Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A...

    Given the following activities and precedents, draw a PERT/CPM diagram. ACTIVITY IMMEDIATE PREDECESSOR DURATION (DAYS) A - 10 B - 12 C A 4 D A, B 8 E A, B 9 F C 10 G D, F 12 H E, G 15 Answer the following: What is the critical path? How long will it take to complete this project? Can activity E be delayed without delaying the completion of the project? If so, how many days?

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT