Consider the following data for a project to install a new server at the Northland Pines High School:
|
Activity |
Activity Time (days) |
Immediate Predecessor(s) |
|
A |
44 |
minus− |
|
B |
55 |
A |
|
C |
44 |
A |
|
D |
44 |
B |
|
E |
11 |
B |
|
F |
55 |
B, C |
|
G |
22 |
D, E |
|
H |
66 |
F |
|
I |
55 |
F |
|
J |
88 |
G, H, I |
a. Choose the correct network diagram below.
A.
SFB5C4D4F5G2I5H6E1A4J8
x y graph
B.
SFB5C4D4F5G2I5H6E1A4J8
x y graph
C.
SFB5C4D4F5G2J8H6E1A4I5
x y graph
D.
SFB5C4D4F5G2I5H6E1A4J8
x y graph
b. Calculate the critical path for this project.
The critical path is
▼
and the project duration is
nothing
days. (Enter your response as a whole number.)
c. How much slack is in each of the activities G, H, and I?
|
Activity |
Activity Time (days) |
On criticalpath? |
Slack (days) |
|
G |
22 |
▼ |
nothing |
|
H |
66 |
▼ |
nothing |
|
I |
55 |
▼ |
nothing |
Click to select your answer(s).
Consider the following data for a project to install a new server at the Northland Pines...
From the following information, develop an AON project network. Complete the forward and backward pass, compute activity slack, and identify the critical path. How many days will the project take? ID Description Predecessor Time A Survey site None 3 B Excavate site A 5 C Install power lines B 2 D Install drainage B 5 E Pour foundation C, D 4 The project will take _ days. The critical path is _ The late start on Activity C is _...
b. Determine the project’s critical path and duration.(this is
number b wuestion) please answer this two b and c questions
Reliable Garage is completing production of the J2000 kit car. The following data are available for the project Activity Activity Time (days) Immediate Predecessor(s 10 D, E,G A-B-C-D-H 4 4 A-B-C-F-G-H b. Determine the pr A-B-C-E-H The critical path isand the project duration is I duration. day(s). (Enter your response as a whole number.) c. Calculate the slack for each...
Pik-Fast, a chain of convenience stores, is planning to open a new store. The activities required, their immediate predecessors, and the optimistic, most likely, and pessimistic estimates of their times (in days) are provided below. Activity Description Immediate Predecessors Optimistic Time (days) Most Likely Time (days) Pessimistic Time (days) TE ES EF LF LS Slack Standard Dev Variance A Select manager -- 10 12 20 13 0 1.67 B Select site -- 8 15 22 15 0 2.33 C Hire workers...
Reliable Garage is completing production of the J2000 kit car. The following data are available for the project: Activity Activity Time (days) Immediate Predecessor(s) A 3 − B 4 A C 5 B D 7 C E 6 C F 2 C G 4 F H 4 D, E, G Determine the project's critical path and duration. The critical path is A-B-C-D-H and the project duration is 23 day(s). (Enter your response as a whole number.) c. What is...
The following info is available for drawing a PERT network using AOA. *(More than one answer may be selected)* Activity Immediate Predecessors Activity Duration (days) A -- 10 B -- 13 C A 12 D B 15 E A 13 F C 16 G D,E 10 H G,F 5 a. the critical path includes: B, D, G, and H. b. the slack on activity G is not 11 days. c. there is one critical path. d. the total duration to...
A project for improving a billing process has the following precedence relationships and activity times: Activity Activity Time (weeks) Immediate Predecessor(s) B, C I Q7 Moow E F, G b. Calculate the slack for each activity. Which activities are on the critical path? Activity Activity Time (weeks) On critical path? Yes Slack (weeks) D 0 Yes 0 0 00000000 @ Tm I
Activity Activity Predecessor Time (days) A -- 4 B -- 12 C A, B 15 D A, B 8 E A, B 6 F C, D, E 14 G C, D, E 3 H F, G 6 The expected completion time for the project above is? 27 days 68 days 47 days 30 days The critical path for the project is? B, C, F, H B, C, F, G, H A, C, F, G A, C, E, H How much...
QUESTION 2 Given the following information, you are to determine the following Project network. Early, late and slack activity times. Project duration. Critical path Task Predecessor Duration A None 8 B A 5 C A 10 D A 15 E A 10 F B 12 G C, D 12 H E, 7 I G, H 7 J F,G,I 10 K J 12
In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: Activity Immediate Predecessor(s) Time (days) A minus− 55 B A 44 C A 66 D B 66 E B 44 F C 44 G D 66 H E, F 99 Carl's team should be able to complete the project in ? days.
The following information is provided for the tasks on a project. Times are in days. Task Time Predecessor A 12 B 21 B, C F 15 G 5 F, G H 17 [Select ] The critical path is [Select ] The time to complete this project will be The slack for task G is Select ] If the duration on task A increases by three days, how long will the project take to complete? I Select ]