Question

Job K76b is for 200 units, and has the following information. Using day 100 as the...

Job K76b is for 200 units, and has the following information. Using day 100 as the due date, construct a backward schedule to determine the start date. Queue time, wait time and move time are quoted in days. Setup time and run time is quoted in standard hours:

Work center Queue time Setup time Run time Wait time Move time
12 2 8 0,4 1 2
14 1 4 0,1 1 2
16 2 8 0,5 1 1
18 2 2 0,4 1 1
0 0
Add a comment Improve this question Transcribed image text
Answer #1
Work center Start Time Queue time Set up Starts Setup time
(in hrs)
Run time
(in Hrs)
Run
Finish
Wait time Move time Finish Time
12 70.42 2 72.42 8 0.4 76.08 1 2 79.08
14 79.08 1 80.08 4 0.1 81.08 1 2 84.08
16 84.08 2 86.08 8 0.5 90.58 1 1 92.58
18 92.58 2 94.58 2 0.4 98.00 1 1 100.00
So the start date should be Day 70
Add a comment
Know the answer?
Add Answer to:
Job K76b is for 200 units, and has the following information. Using day 100 as the...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • please answer this ABC's machine shop is considering the use of priority scheduling rule in the...

    please answer this ABC's machine shop is considering the use of priority scheduling rule in the fabrication shop and must decide whether to use: a. Critical ratio (CR) Earliest due date (EDD) C. Shortest operation next (SON)/Shortest processing time 9SPT) d. Order Slack Order No. Total Remaining Time Remaining Current operation Manufacturing until Due Date Processing time Time (days) (days) (days) А 12 15 10 14 D 18 15 19 Using the four sequencing rules, compute the scheduling priority for...

  • The production floor produces 8500 units/day and the associated direct-operated store sells 50 units/hour with the...

    The production floor produces 8500 units/day and the associated direct-operated store sells 50 units/hour with the selling price at $120/unit. The direct-operated store operates 12 hours/day and 365 days/year, but the production works for 250 working days/year. Given that the production setup cost per production run is $1500 and the holding cost per year is $5/unit. (a) Calculate the optimal batch size for each production run. (b) What is the maximum inventory level with regard to the optimal batch size?...

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 260 8 20 252 18 30 260 26 40 270 32 50 275 14 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT? b. What is the average completion (flow) time?...

  • ABC Enterprises has five jobs that must be scheduled for production at a work center. Below...

    ABC Enterprises has five jobs that must be scheduled for production at a work center. Below are the processing times and due dates for each job.                                     Job Processing Time (in days) Due Date (days from today) 1 7 14 2 5 21 3 3 10 4 2 7 5 6 9                                                                                                                            Schedule the jobs by sequencing them using the Earliest Due Date (EDD) priority rule. What is the average flow time? Show your Work and round your...

  • First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are reviewing...

    First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are reviewing the Gantt chart at the end of day 4. Job D was scheduled to begin early on day 2 and take 6.5 days. As of now (the review point after day 4), it is 2 days ahead of schedule. Job E should begin on day 1 and take 3 days. It was on time. Job F was to begin on day 3, but maintenance...

  • Problem 16-17 Given the following information on job times and due dates Job Time Due Date (Hours...

    Problem 16-17 Given the following information on job times and due dates Job Time Due Date (Hours) (Hours) Job 3.5 2.0 4.5 5.0 2.5 6.0 18 20 Determine the optimal processing sequence using (1) First come, first served, (2) Shortest processing time, (3) Earliest due date, and (4) Critical ratio. a-1. Sequence for First come, first served (Click to select) Sequence for Shortest processing time Click to select) Sequence for Earliest due date (Click to select) Click to select) Sequence...

  • First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are reviewing...

    First Printing and Copy Center has 4 jobs to be scheduled. Production scheduling personnel are reviewing the Gantt chart at the end of day 4. Job D was scheduled to begin early on day 2 and take 6.5 days. As of now (the review point after day 4), it is 2 days ahead of schedule. Job E should begin on day 1 and take 3 days. It was on time. Job F was to begin on day 3, but maintenance...

  • Question 1: Sequence the jobs shown below by using a Gantt chart. Assume that the move...

    Question 1: Sequence the jobs shown below by using a Gantt chart. Assume that the move time between machines is one hour. Sequence the jobs in priority order 1, 2, 3, 4. Job Work Center/Machine Hours                                  Due Date (days) 1 A/3, B/2, C/2 3 2 C/2, A/4 2 3 B/6, A/1, C/3 4 4 C/4, A/1, B/2 3 Using finite capacity scheduling, draw a Gantt chart for the schedule (Marks 0.5) What is the makespan? (Marks 0.5) How much machine...

  • The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE...

    The following jobs are waiting to be processed at a small machine​ center: JOB DUE DATE DURATION (DAYS) 10 240 18 20 232 14 30 240 6 40 245 30 50 255 26 All dates are specified as manufacturing planning calendar days. Assume that all jobs arrived on day 200 ​(yesterday) in the order shown but are not scheduled to begin until day 201 (today). a. Sequence the jobs according to LPT According to the LPT rule, the sequence of...

  • You make fancy, custom l light fixtures. You currently have orders from four important customers. The...

    You make fancy, custom l light fixtures. You currently have orders from four important customers. The list below describes the work (the load) that is currently in production, which works 8 hours per day, M-F, with one highly skilled employee. There is no other work in the work center, it is the beginning of the day 3/4, a Monday, no work has been done on any job. Work must be completed by NOON of the day it is due to...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT