Question

4. a. To be effective, the risk management process should be applied throughout the project and at all levels of system decom

0 0
Add a comment Improve this question Transcribed image text
Answer #1

4.

To be effective, the risk management process should

Correct answer is "a. be applied throughput the project and at all levels of system decomposition and project organization"

Rationale: Risk management is the process of identifying, analyzing and responding to any risk that arises over the life cycle of a project to help the project remain on track and meet its goal.

5.

Which of the following help to define the deliverables of the project

Correct answer is "a. Work Breakdown Structure"

Rationale: WBS (Work breakdown structure) define the main project deliverables and level i.e. define the deliverables of the project and break them down into components and have them decomposed into levels.

6.

As given,

PV= $5000

EV= $5250

AC= $5500

BAC= $25000

Schedule Variance (SV) = Earned Value – Planned Value

SV = EV – PV = $5250 - $5000 = $250

Cost Variance (CV) = Earned Value – Actual Cost

CV = EV – AC= $5250 - $5500 = - $250

CPI= EV/ AC = 5250/ 5500 = 0.95

EAC = BAC/ CPI = 25000/ 0.95 = $26315

Correct answer is "d. SV = $250, CV= - $250, EAC = $26,315"


Please give thumbs up/ likes if you find this answer helpful. Thank you!

Add a comment
Know the answer?
Add Answer to:
4. a. To be effective, the risk management process should be applied throughout the project and...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • 1 What should not be covered by a risk management plan? a Roles and responsibilities for...

    1 What should not be covered by a risk management plan? a Roles and responsibilities for handling project risks b Timing of project risk management activities c The methodological approach used for risk management d Individual risks and potential responses to them 2 You are assigned as the project manager to a project which had a one-time cost variance in the past caused by unexpected rework which has meanwhile been finished. You perform earned value analysis and get the following...

  • Project risk management is an iterative process that begins with a plan for how risks will be man...

    Project risk management is an iterative process that begins with a plan for how risks will be managed throughout the life of the project. Risks must first be identified and analyzed. Then risk responses and action steps must be developed. The risk management plan should also include the steps, processes, or procedures that will be used to continually monitor risk during the project. Defining requirements for a process improvement project can be particularly challenging. Depending on the extent and complexity...

  • At week 10 of a project below to improve distance learning platform, assume that the planned...

    At week 10 of a project below to improve distance learning platform, assume that the planned values (PV) are based on time proportionality but the “% Complete” values for earned values (EV) are from the workers actually doing the tasks. ACTIVITY PRE- DECESSORS DURATION (WEEKS) BUDGET ($) ACTUAL COST ($) % COMPLETE A - 5 500 640 100 B A 3 300 400 100 C B 4 320 310 80 D B 6 600 250 60 E C,D 3 300...

  • •Please help develop an overall delivery Process using the below to be in line with Agile project...

    •Please help develop an overall delivery Process using the below to be in line with Agile project management Project Management Office The Project Management Office (PMO) is an effective means for centralising all Project initiatives. It is the discipline of planning, organising and managing resources to bring about the successful completion of specific project goals and objectives. The key objective of PMO is to ensure all projects are executed on track, on schedule, within budget, and in adherence to business...

  • I need help with the attached assignment. I attached the question and completed assigment. I just...

    I need help with the attached assignment. I attached the question and completed assigment. I just need help with answering one more question which is which is: Discuss a strategy that you would use to communicate the status of the project to stakeholders? Project Monitoring and Control Assignment Complete the following items for this assignment: 1. Read through the Case 13.1 Tree Trimming Project Case in Larson and Gray. Respond to Questions 1 and 2 of the case. Use Microsoft...

  • RADICO’S CHALLENGE The executive staff at Radico Corporation was quite pleased with the one-day training program...

    RADICO’S CHALLENGE The executive staff at Radico Corporation was quite pleased with the one-day training program they attended on the benefits of using agile and Scrum on some of their projects. Radico provided products and services to both public and private sector clients, almost all of it through competitive bidding. IT was not required for any of the products and services Radico provided. Agile and Scrum had proven to be successful on internal IT projects, but there were some concerns...

  • Case 18: Chipotle Mexican Grill, Inc.: The International Challenge Do overseas markets offer attractive growth opportunities for chipotle? If so should, chipotle replicate its US strategy in overs...

    Case 18: Chipotle Mexican Grill, Inc.: The International Challenge Do overseas markets offer attractive growth opportunities for chipotle? If so should, chipotle replicate its US strategy in overseas markets, or does if need to adjust the local circumstances- if so how? In particular, should chipotle directly own and manage its overseas restaurants or should I opt for a joint venture or franchising? Complete a porter 5 forces analysis for the firm plus “1” technology impact? Case 18 Chipotle Mexican Grill,...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT