Question

TABLE 6-3 Na Activity Network diagram data for a large project Initial Node Final Node Estimated Duration wa uut + WNN- ter t

Need help with #5 only. Please Help me out. It's due this Thursday, Feb 27th. Below is my Exercise 3.

Exercise 3:

(9.8) 5 (1,12) Saved to this PC D.4) (A, 10) (1,10) (B,12) /6,4) (1,6) (,6) (C, 8) (K, 8) (H,8) B. Time taken by all possible

0 0
Add a comment Improve this question Transcribed image text
Answer #1

Dated: Page No.: A (6,8) (512) 8 1024) 2 (8, 2) 3 4Lylo 5 ,4) G). (278) [96) Let a Source node be: node 1 Minimum Distance frDzied: / Node 6 : 7 (18) Node 118) (18+8=26) minemum distance Node 2: — (26) Nocle. 8 (10) (26+ 10s36) As from this bath we g

Add a comment
Know the answer?
Add Answer to:
Need help with #5 only. Please Help me out. It's due this Thursday, Feb 27th. Below...
Your Answer:

Post as a guest

Your Name:

What's your source?

Earn Coins

Coins can be redeemed for fabulous gifts.

Not the answer you're looking for? Ask your own homework help question. Our experts will answer your question WITHIN MINUTES for Free.
Similar Homework Help Questions
  • Microsoft Project Assignment Description A system development project has been defined to contain the following list of...

    Microsoft Project Assignment Description A system development project has been defined to contain the following list of activities along with their estimated times for completion. The project will start on 5/1/2019. Project Data Provided: Activity ID Activity Name Days Predecessors Optimistic(O) Realistic(R) Pessimistic(P) 1 Gather Requirement 1 2 3 2 Analyze processes 1 2 6 1 3 Define DFDs 0.5 1 1.5 2 4 Design Processes 2 7 12 2 5 Design database 4 7 22 3 6 Design UI...

  • Please help me with this question (( clear draw Please)) Draw the network diagram, including all...

    Please help me with this question (( clear draw Please)) Draw the network diagram, including all calculations of nodes using the following format: Early Start Duration Early Finish Task Name Late Sta rt Slack Late Finish List the networkpaths below: Determine the criticalpath(s). What is it and what is its duration? Activity Duration Dependency Start 0 A 6 Start B 1 A C 3 A,B D 5 A, B E 12 Start F 4 D, E G 2 C, F...

  • Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J --...

    Consider the network described in the table below. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 7 L J 10 6 5 M J 3 3 3 N K, M 9 5 1 O K, M 10 7 4 P L, N 10 8 3 Draw the network diagram and answer the following questions. (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path....

  • QUESTION 2 Given the following information, you are to determine the following Project network. Early, late...

    QUESTION 2 Given the following information, you are to determine the following Project network. Early, late and slack activity times. Project duration. Critical path Task Predecessor Duration A None 8 B A 5 C A 10 D A 15 E A 10 F B 12 G C, D 12 H E, 7 I G, H 7 J F,G,I 10 K J 12

  • Activity on arrow construction

    QUESTION 1 The following table provides information about a particular project:ActivityDuration (Days)PrecedingActivityA5_B6_C4AD3AE1AF4EG14D,EH12B,CI2G,H (a)   Represent the project by means of a simple network diagram.        (b)   Prepare in tabular form, an activity schedule showing the following details: Earliest-start, earliest-finish, latest-start, latest-finish and slack times.         (c)   Identify the critical path.                                                               ...

  • Consider the following project where times are in weeks. Activity Duration Immediate Predecessors A B с...

    Consider the following project where times are in weeks. Activity Duration Immediate Predecessors A B с D E F G H A.B B A с E,F 8 12 7 4 2 3 7 3 DF a) Determine the activity schedule (ES, EF, LS, and LF) as well as slack using the information from the table above (11 marks) b) Determine all the possible paths of this project and determine the shortest possible time this project can be completed? (4 marks)...

  • The ABC Manufacturing Co. has made a decision to replace an existing production line with new...

    The ABC Manufacturing Co. has made a decision to replace an existing production line with new equipment. This project will require several tasks (jobs) with precedence relationships and duration (days) as shown in the following table. The project will be finished when activities A-J are all finished. Activity predecessor Optimistic Most likely Pessimistic Expected A - 4 5 12 B A 3 4.5 15 C A 2 3 4 D C 6 8 22 E B 4 6 8 F...

  • Please help with 1-2!! Network diagram: Exercise # 4 Based on Excercise 3 from Module 6: 1. Perform a Forward...

    Please help with 1-2!! Network diagram: Exercise # 4 Based on Excercise 3 from Module 6: 1. Perform a Forward Pass and a Backward Pass of the network diagram above 2. Which Activities has the same Early Finish as they have Late Finish? Note: The project starts on Day "O" Early Start Duration Early Finsh Task Name Late Start Late Finish Slack A 2. 2 6 4 H Exercise # 4 Based on Excercise 3 from Module 6: 1. Perform...

  • Hello, I need help in the following exercises from book: Project Management: Achieving competitive advantage (4th...

    Hello, I need help in the following exercises from book: Project Management: Achieving competitive advantage (4th ed.).Jeffery Pinto Exercise 9.1 Consider the following information that you have compiled re- garding the steps needed to complete a project. You have identi- fied all relevant steps and have made some determinations re- garding predecessor/successor relationships. Using MS Project, develop a simple network diagram for this project, showing the links among the project activities. Activity Predecessors A – Survey site — B –...

  • Plan ME Develop a loading schedule for each resource below. (Figure 8.3) EE ME 0 1...

    Plan ME Develop a loading schedule for each resource below. (Figure 8.3) EE ME 0 1 2 3 4 5 6 7 8 9 10 11 12 Fill in the times below for a resource activity schedule. ID/RES ES LSEF LF SL 1-EE Schedule 2.EE Legend ES ID EF 3-ME SL LS DUR LF 4.EE 5-ME 6-ME 7-EE Resource EX8-1 (Static) Given the network plan that... Given the network plan that follows, compute the early, late, and slack times. What...

ADVERTISEMENT
Free Homework Help App
Download From Google Play
Scan Your Homework
to Get Instant Free Answers
Need Online Homework Help?
Ask a Question
Get Answers For Free
Most questions answered within 3 hours.
ADVERTISEMENT
ADVERTISEMENT